Directory of Power Plants in California
Plant Name | Utility | Location | Balancing Authority | Annual Generation | Plant Date | Last Update | Fuel Types |
---|---|---|---|---|---|---|---|
Lemoore 1 | AES Distributed Energy | Lemoore, CA | California Independent System Operator (CISO) | 1.4 GWh | Jan 2016 | Dec 2024 | Solar |
FRV SI Transport Solar LP | FRV SI Transport Solar, L.P. (Sacremento) | Sacramento, CA | California Independent System Operator (CISO) | 1.4 GWh | Jul 2010 | Dec 2024 | Solar |
La Joya Del Sol | CVI CleanCapital Solar 1 LLC | Fresno, CA | California Independent System Operator (CISO) | 1.4 GWh | Nov 2012 | Dec 2024 | Solar |
ZCO | Wind Stream Operations LLC | Tehachapi, CA | California Independent System Operator (CISO) | 1.4 GWh | Nov 1985 | Dec 2024 | Wind |
Dinuba Wastewater Treatment Plant | AES Distributed Energy | Dinuba, CA | California Independent System Operator (CISO) | 1.4 GWh | Oct 2011 | Dec 2024 | Solar |
Valley Sanitary District WTP Solar | Tesla Inc. | Indio, CA | Los Angeles Department of Water and Power (LDWP) | 1.4 GWh | Nov 2016 | Dec 2024 | Solar |
Chuckawalla Valley State Prison | SunE CPA CDC1 LLC | Blythe, CA | California Independent System Operator (CISO) | 1.4 GWh | May 2006 | Dec 2024 | Solar |
CSD 2- Freedom High | CleanCapital Holdings | Oakley, CA | California Independent System Operator (CISO) | 1.4 GWh | Jul 2013 | Dec 2024 | Solar |
Meridian Vineyards | CVI CleanCapital Solar 1 LLC | Paso Robles, CA | California Independent System Operator (CISO) | 1.4 GWh | Nov 2010 | Dec 2023 | Solar |
Intel Folsom | Tesla Inc. | Folsom, CA | Balancing Authority of Northern California (BANC) | 1.4 GWh | Jun 2010 | Dec 2023 | Solar |
City of Madera WWTP | SunE GIL1, LLC | Madera, CA | California Independent System Operator (CISO) | 1.4 GWh | Aug 2009 | Dec 2024 | Solar |
Chambers 4 - Redland LGB4 | MN8 Energy LLC | Redlands, CA | California Independent System Operator (CISO) | 1.4 GWh | Feb 2019 | Dec 2024 | Solar |
CSU Fresno Solar Project | MMA Fresno Power LP | Fresno, CA | California Independent System Operator (CISO) | 1.4 GWh | Nov 2007 | Dec 2024 | Solar |
Lancaster Baptist Church | Tesla Inc. | Lancaster, CA | California Independent System Operator (CISO) | 1.4 GWh | Nov 2011 | Dec 2024 | Solar |
Alta Powerhouse | Pacific Gas & Electric Co. | Alta, CA | California Independent System Operator (CISO) | 1.4 GWh | Oct 1902 | Dec 2024 | Water |
Stage Gulch Solar | Stage Gulch Solar, LLC | Petaluma, CA | California Independent System Operator (CISO) | 1.5 GWh | Mar 2018 | Dec 2024 | Solar |
Clovis North High School | Tesla Inc. | Fresno, CA | California Independent System Operator (CISO) | 1.5 GWh | Nov 2017 | Dec 2024 | Solar |
Clovis East High School | Tesla Inc. | Clovis, CA | California Independent System Operator (CISO) | 1.5 GWh | Mar 2018 | Dec 2024 | Solar |
Energy Center | University of Redlands | Redlands, CA | California Independent System Operator (CISO) | 1.5 GWh | Jan 2007 | Dec 2024 | Natural Gas |
2127 Harris Solar Project | Solarenewal LLC | Live Oak, CA | California Independent System Operator (CISO) | 1.5 GWh | Mar 2014 | Dec 2024 | Solar |
Strata Roof 1 | Strata Manager, LLC | Sacramento, CA | Balancing Authority of Northern California (BANC) | 1.5 GWh | Apr 2013 | Dec 2024 | Solar |
SunE- E Philadelphia Ontario | SunEdison LLC | Ontario, CA | California Independent System Operator (CISO) | 1.5 GWh | Feb 2016 | Dec 2024 | Solar |
Oltmans SCE at Champagne | California PV Energy LLC | Ontario, CA | California Independent System Operator (CISO) | 1.5 GWh | Nov 2013 | Dec 2024 | Solar |
Port of LA Solar FiT Project | Los Angeles Department of Water & Power | San Pedro, CA | Los Angeles Department of Water and Power (LDWP) | 1.5 GWh | Sep 2015 | Dec 2024 | Solar |
Intel Folsom Phase 2 | Tesla Inc. | Folsom, CA | Balancing Authority of Northern California (BANC) | 1.5 GWh | Sep 2012 | Dec 2024 | Solar |
Nunn | CD US Solar MT 2 LLC | Apple Valley, CA | California Independent System Operator (CISO) | 1.6 GWh | Jun 2013 | Dec 2024 | Solar |
Bishop Ranch BR 1-X | Bollinger Canyon Road BR 1-X Solar Project 2020 | San Ramon, CA | California Independent System Operator (CISO) | 1.6 GWh | Feb 2022 | Dec 2024 | Solar |
SMUD at Lawrence | Sacramento PV Energy, LLC | Elk Grove, CA | Balancing Authority of Northern California (BANC) | 1.6 GWh | Nov 2011 | Dec 2024 | Solar |
Dos Palos | Greenbacker Renewable Energy Corporation | Dos Palos, CA | California Independent System Operator (CISO) | 1.6 GWh | Oct 2021 | Dec 2024 | Solar |
Grassland 1&2 Solar Project | Yolo County of | Davis, CA | California Independent System Operator (CISO) | 1.6 GWh | Jun 2013 | Jun 2024 | Solar |
CSUF State College | MN8 Energy LLC | Fullerton, CA | California Independent System Operator (CISO) | 1.6 GWh | Nov 2016 | Dec 2024 | Solar |
Tahquitz High School | AES Distributed Energy | Hemet, CA | California Independent System Operator (CISO) | 1.6 GWh | Aug 2012 | Dec 2024 | Solar |
FAA NorCal TRACON | Enfinity NorCal 1 FAA LLC | Mather AFB, CA | Balancing Authority of Northern California (BANC) | 1.6 GWh | Nov 2012 | Dec 2024 | Solar |
Alticor Inc - Solar Project | MN8 Energy LLC | Buena Park, CA | California Independent System Operator (CISO) | 1.6 GWh | Nov 2017 | Dec 2024 | Solar |
Manteca Land PV | AES Distributed Energy | Manteca, CA | California Independent System Operator (CISO) | 1.6 GWh | Nov 2017 | Dec 2024 | Solar |
Tulare Akers Professional Center | SoCore Energy LLC | Visalia, CA | California Independent System Operator (CISO) | 1.6 GWh | Oct 2019 | Dec 2024 | Solar |
2097 Helton Solar Project | Solarenewal LLC | Merced, CA | California Independent System Operator (CISO) | 1.6 GWh | Mar 2014 | Dec 2024 | Solar |
Foundation Cemex Madison | Foundation CA Fund V Manager, LLC | Madison, CA | California Independent System Operator (CISO) | 1.6 GWh | Jul 2012 | Dec 2024 | Wind |
Pacific Ethanol Madera Solar Array | Seaboard Energy California, LLC | Madera, CA | California Independent System Operator (CISO) | 1.6 GWh | Jul 2018 | Dec 2024 | Solar |
SCE-Snowline-Duncan Road (South) | SunEdison LLC | Phelan, CA | California Independent System Operator (CISO) | 1.6 GWh | Sep 2014 | Dec 2024 | Solar |
Kettering Solar 1 | Tesla Inc. | Lancaster, CA | California Independent System Operator (CISO) | 1.6 GWh | May 2014 | Dec 2024 | Solar |
SDCCD - Miramar | CleanCapital Holdings | San Diego, CA | California Independent System Operator (CISO) | 1.6 GWh | Jan 2011 | Dec 2024 | Solar |
USG 2 | ZGlobal Inc | El Centro, CA | Imperial Irrigation District (IID) | 1.6 GWh | Nov 2015 | Dec 2023 | Solar |
SunEdison Procter & Gamble Oxnard | SunE U6 Holdings LLC | Oxnard, CA | California Independent System Operator (CISO) | 1.6 GWh | Sep 2009 | Dec 2024 | Solar |
Las Virgenes Municipal Water District | Tesla Inc. | Calabasas, CA | California Independent System Operator (CISO) | 1.6 GWh | Jan 2014 | Dec 2024 | Solar |
Gridley Main | Altus Power America Management, LLC | Gridley, CA | California Independent System Operator (CISO) | 1.6 GWh | Feb 2013 | Dec 2024 | Solar |
Catalina Express | Altus Power America Management, LLC | San Pedro, CA | California Independent System Operator (CISO) | 1.7 GWh | Nov 2020 | Dec 2024 | Solar |
Corcoran | Terraform Arcadia | Corcoran, CA | California Independent System Operator (CISO) | 1.7 GWh | Dec 2013 | Dec 2024 | Solar |
Castle Rock Vineyards | Castle Rock Cooling | Delano, CA | California Independent System Operator (CISO) | 1.7 GWh | Aug 2010 | Dec 2024 | Solar |
Lindberg Field Solar 2 | Lindberg Field Solar 2, LLC | San Diego, CA | California Independent System Operator (CISO) | 1.7 GWh | Jan 2017 | Dec 2024 | Solar |
Lavio Solar | Lavio Solar, LLC | Petaluma, CA | California Independent System Operator (CISO) | 1.7 GWh | Mar 2018 | Dec 2024 | Solar |
Kroger La Habra | Ralph's Grocery Company | La Habra, CA | California Independent System Operator (CISO) | 1.7 GWh | Mar 2020 | Dec 2024 | Solar |
North Bay Solar 1 | AES Distributed Energy | Fairfield, CA | California Independent System Operator (CISO) | 1.7 GWh | Jul 2013 | Dec 2024 | Solar |
San Antonio West Solar Rooftop | SS San Antonio West LLC | Chino, CA | California Independent System Operator (CISO) | 1.7 GWh | Jul 2012 | Dec 2024 | Solar |
Government Plaza Solar | SoCore Energy LLC | Visalia, CA | California Independent System Operator (CISO) | 1.7 GWh | Oct 2020 | Dec 2024 | Solar |
Bishop Ranch - BR 1-Y | Distributed Solar Development, LLC | San Ramon, CA | California Independent System Operator (CISO) | 1.7 GWh | Feb 2022 | Dec 2024 | Solar |
West Village Solar - Array 2 Community S | CHF-Davis I, LLC | Davis, CA | California Independent System Operator (CISO) | 1.7 GWh | Apr 2022 | Dec 2023 | Solar |
Niagara Bottling Stockton | ClearGen LLC | Stockton, CA | California Independent System Operator (CISO) | 1.7 GWh | Dec 2017 | Dec 2023 | Solar |
Chula Vista Energy Center | Wellhead Services, Inc | Chula Vista, CA | California Independent System Operator (CISO) | 1.7 GWh | Apr 2001 | Dec 2024 | Natural Gas |
Marina South | Altus Power America Management, LLC | San Pedro, CA | California Independent System Operator (CISO) | 1.8 GWh | Nov 2020 | Dec 2024 | Solar |
West Village Solar - Array 1Community So | CHF-Davis I, LLC | Davis, CA | California Independent System Operator (CISO) | 1.8 GWh | Apr 2022 | Dec 2023 | Solar |
Grossmont HS Solar Project | MN8 Energy LLC | El Cajon, CA | California Independent System Operator (CISO) | 1.8 GWh | Nov 2018 | Dec 2024 | Solar |
Cottonwood Solar, LLC Cottonwood Carport | Onward Energy | Novato, CA | California Independent System Operator (CISO) | 1.8 GWh | Apr 2016 | Dec 2024 | Solar |
Zero Waste Energy Development Co LLC | Zero Waste Energy Development Company LLC | San Jose, CA | California Independent System Operator (CISO) | 1.8 GWh | Jan 2015 | Dec 2024 | Other Biomass Gas |
Summer Solar D2 | AES Distributed Energy | Lancaster, CA | California Independent System Operator (CISO) | 1.8 GWh | Jun 2014 | Dec 2024 | Solar |
Santa Rosa Junior College Petaluma Solar | Sonoma County Junior College District | Petaluma, CA | California Independent System Operator (CISO) | 1.8 GWh | Jun 2018 | Dec 2023 | Solar |
RE-VFO LLC | RE-VFO LLC | Visalia, CA | California Independent System Operator (CISO) | 1.8 GWh | Apr 2009 | Dec 2024 | Solar |
2081 Terzian Solar Project | Solarenewal LLC | Reedley, CA | California Independent System Operator (CISO) | 1.8 GWh | Jan 2014 | Dec 2024 | Solar |
Lake Elsinore Canopies - Lakeside HS | Standard Solar | Lake Elsinore, CA | California Independent System Operator (CISO) | 1.8 GWh | Feb 2022 | Dec 2024 | Solar |
Guadalupe Solar Farm | County of Santa Clara (CA) | San Jose, CA | California Independent System Operator (CISO) | 1.9 GWh | Aug 2018 | Dec 2024 | Solar |
SeaWorld Aquatica | Onyx Asset Services Group | Chula Vista, CA | California Independent System Operator (CISO) | 1.9 GWh | Apr 2018 | Dec 2023 | Solar |
Blue Skies Solar, LLC | Blue Skies Solar, LLC | Arvin, CA | PacifiCorp West (PACW) | 1.9 GWh | Nov 2021 | Dec 2023 | Solar |
Temescal Canyon RV, LLC | Temescal Canyon RV, LLC | Corona, CA | California Independent System Operator (CISO) | 1.9 GWh | Apr 2011 | Dec 2024 | Solar |
Open Sky Ranch Inc | Bravo REC Management LLC | Riverdale, CA | California Independent System Operator (CISO) | 1.9 GWh | Jun 2024 | Dec 2024 | Solar |
Firebaugh-CCS-PV-1 | Mike Woolf Farming | Firebaugh, CA | California Independent System Operator (CISO) | 1.9 GWh | Feb 2015 | Dec 2024 | Solar |
Foundation Wal-Mart Red Bluff | Foundation CA Fund VI Manager LLC | Red Bluff, CA | California Independent System Operator (CISO) | 1.9 GWh | Aug 2012 | May 2025 | Wind |
CSD 2 - Heritage High | CleanCapital Holdings | Brentwood, CA | California Independent System Operator (CISO) | 1.9 GWh | Aug 2013 | Dec 2024 | Solar |
Kettering Solar 2 | Tesla Inc. | Lancaster, CA | California Independent System Operator (CISO) | 1.9 GWh | May 2014 | Dec 2024 | Solar |
Teichert Materials-Teichert Vernalis | Foundation HA Energy Generation, LLC | San Joaquin, CA | California Independent System Operator (CISO) | 1.9 GWh | Sep 2010 | Dec 2024 | Wind |
Bakersfield 111 | Bakersfield 111 LLC | Bakersfield, CA | PacifiCorp West (PACW) | 1.9 GWh | Jun 2015 | Dec 2024 | Solar |
Mira Loma | Costco Wholesale | Mira Loma, CA | California Independent System Operator (CISO) | 1.9 GWh | Oct 2011 | Dec 2024 | Solar |
Maclay Solar Project | Los Angeles Department of Water & Power | Sylmar, CA | Los Angeles Department of Water and Power (LDWP) | 1.9 GWh | Mar 2017 | Jan 2024 | Solar |
Gilead Foster City Solar Project | Gilead Sciences Inc. Foster City | Foster City, CA | California Independent System Operator (CISO) | 1.9 GWh | Mar 2021 | Dec 2024 | Solar |
North Juvenile Detention Center Solar | SoCore Energy LLC | Visalia, CA | California Independent System Operator (CISO) | 2.0 GWh | Oct 2019 | Dec 2024 | Solar |
US GSA - Sacramento | Tesla Inc. | Sacramento, CA | Balancing Authority of Northern California (BANC) | 2.0 GWh | Feb 2018 | Dec 2024 | Solar |
California PV Energy at ISD WWTP | California PV Energy LLC | Oakley, CA | California Independent System Operator (CISO) | 2.0 GWh | Jul 2014 | Dec 2024 | Solar |
Medline Ind. Phase 2 Tracy | EnterSolar | Tracy, CA | California Independent System Operator (CISO) | 2.0 GWh | Mar 2018 | Dec 2024 | Solar |
Building G | Golden Springs Development Company LLC | Santa Fe Springs, CA | California Independent System Operator (CISO) | 2.0 GWh | Aug 2016 | Dec 2024 | Solar |
Palo Verde College | Scale Sustainable I, LLC | Blythe, CA | California Independent System Operator (CISO) | 2.0 GWh | Jul 2009 | Dec 2023 | Solar |
Solar Star Palo Alto I, LLC | DG 1 Acquisition Co., LLC | Palo Alto, CA | California Independent System Operator (CISO) | 2.0 GWh | Jul 2019 | Dec 2024 | Solar |
Heliocentric | Heliocentric LLC | Palmdale, CA | California Independent System Operator (CISO) | 2.0 GWh | Feb 2012 | Dec 2024 | Solar |
SCCCD - Clovis Community College | Forefront Power, LLC | Fresno, CA | California Independent System Operator (CISO) | 2.0 GWh | Nov 2018 | Dec 2024 | Solar |
Sacramento (SMUD) | Terraform Arcadia | Sacramento, CA | Balancing Authority of Northern California (BANC) | 2.0 GWh | Jul 2014 | Dec 2024 | Solar |
Rancho Cordova Medical Offices | KP Rancho Cordova Medical Offices Solar, LLC | Rancho Cordova, CA | Balancing Authority of Northern California (BANC) | 2.0 GWh | Mar 2021 | Dec 2024 | Solar |
PFMG Solar Grossmont Helix LLC | Altus Power America Management, LLC | La Mesa, CA | California Independent System Operator (CISO) | 2.0 GWh | Apr 2018 | Dec 2024 | Solar |
Bakersfield Industrial PV 1 | AES Distributed Energy | Bakersfield, CA | California Independent System Operator (CISO) | 2.1 GWh | Nov 2017 | Dec 2024 | Solar |
Univ of California San Diego Solar | University of California San Diego | La Jolla, CA | California Independent System Operator (CISO) | 2.1 GWh | Nov 2008 | Dec 2024 | Solar |
SC 1 Data Center, Phase 2 | Xeres Ventures LLC | Santa Clara, CA | California Independent System Operator (CISO) | 2.1 GWh | Aug 2011 | May 2025 | Distillate Fuel Oil |
Sacramento Point West Medical Offices | KP Sacramento Point West Medical Offices Solar, LLC | Sacramento, CA | Balancing Authority of Northern California (BANC) | 2.1 GWh | Oct 2020 | Dec 2024 | Solar |
IGS OXR1 | Greenbacker Renewable Energy Corporation | Oxnard, CA | California Independent System Operator (CISO) | 2.1 GWh | Jul 2024 | Dec 2024 | Solar |
Browse Power Plants By California Counties
Figures are based on December 2024 generation numbers.County | State Rank | Active Plants | Dec 2024 Generation |
---|---|---|---|
Mendocino County, CA | # 55 | 5 | 12.3 GWh |
Glenn County, CA | # 54 | 2 | 18.7 GWh |
Marin County, CA | # 53 | 3 | 19.0 GWh |
Sierra County, CA | # 52 | 3 | 31.4 GWh |
Napa County, CA | # 51 | 9 | 49.2 GWh |
Santa Cruz County, CA | # 50 | 6 | 56.2 GWh |
Tehama County, CA | # 49 | 7 | 59.7 GWh |
San Francisco County, CA | # 48 | 10 | 84.6 GWh |
San Mateo County, CA | # 47 | 10 | 133.3 GWh |
Nevada County, CA | # 46 | 12 | 207.0 GWh |
Yolo County, CA | # 45 | 15 | 222.2 GWh |
Siskiyou County, CA | # 44 | 8 | 242.5 GWh |
Mariposa County, CA | # 43 | 2 | 299.7 GWh |
Santa Barbara County, CA | # 42 | 18 | 334.0 GWh |
Lassen County, CA | # 41 | 9 | 341.0 GWh |
San Benito County, CA | # 40 | 6 | 346.0 GWh |
Humboldt County, CA | # 39 | 10 | 469.7 GWh |
Merced County, CA | # 38 | 30 | 475.2 GWh |
Calaveras County, CA | # 37 | 6 | 542.0 GWh |
Trinity County, CA | # 36 | 5 | 560.5 GWh |
Amador County, CA | # 35 | 8 | 659.7 GWh |
Mono County, CA | # 34 | 9 | 785.9 GWh |
Ventura County, CA | # 33 | 32 | 825.9 GWh |
Lake County, CA | # 32 | 10 | 912.2 GWh |
Madera County, CA | # 31 | 28 | 1.0 TWh |
Tulare County, CA | # 30 | 68 | 1.1 TWh |
Inyo County, CA | # 29 | 23 | 1.2 TWh |
El Dorado County, CA | # 28 | 15 | 1.4 TWh |
County | State Rank | Active Plants | Dec 2024 Generation |
---|---|---|---|
Yuba County, CA | # 27 | 5 | 1.6 TWh |
Sutter County, CA | # 26 | 8 | 1.9 TWh |
Plumas County, CA | # 25 | 13 | 2.0 TWh |
Placer County, CA | # 24 | 23 | 2.0 TWh |
San Joaquin County, CA | # 23 | 45 | 2.3 TWh |
Alameda County, CA | # 22 | 46 | 2.5 TWh |
Stanislaus County, CA | # 21 | 25 | 2.7 TWh |
Tuolumne County, CA | # 20 | 23 | 2.8 TWh |
Colusa County, CA | # 19 | 3 | 2.9 TWh |
Solano County, CA | # 18 | 40 | 3.1 TWh |
Orange County, CA | # 17 | 59 | 3.3 TWh |
Butte County, CA | # 16 | 25 | 3.6 TWh |
Monterey County, CA | # 15 | 29 | 3.7 TWh |
Kings County, CA | # 14 | 57 | 4.1 TWh |
Santa Clara County, CA | # 13 | 74 | 4.4 TWh |
San Diego County, CA | # 12 | 150 | 5.1 TWh |
Sonoma County, CA | # 11 | 26 | 5.3 TWh |
Sacramento County, CA | # 10 | 64 | 6.5 TWh |
Shasta County, CA | # 9 | 46 | 7.4 TWh |
Fresno County, CA | # 8 | 109 | 7.9 TWh |
Imperial County, CA | # 7 | 84 | 9.7 TWh |
San Bernardino County, CA | # 6 | 203 | 13.3 TWh |
Contra Costa County, CA | # 5 | 56 | 13.6 TWh |
Riverside County, CA | # 4 | 159 | 14.5 TWh |
San Luis Obispo County, CA | # 3 | 22 | 20.7 TWh |
Los Angeles County, CA | # 2 | 307 | 20.8 TWh |
Kern County, CA | # 1 | 311 | 34.4 TWh |