Sutter Home Winery TCC

8998 N River Road, Paso Robles, CA 93446

Plant Summary Information

Sutter Home Winery TCC is ranked #788 out of 849 solar farms in California in terms of total annual net electricity generation.

Sutter Home Winery TCC generated 244.0 MWh during the 3-month period between September 2024 to December 2024.

Plant NameSutter Home Winery TCC
Utility NameREC SHW, LLC
LocationSan Luis Obispo County, CA
Initial Operation DateMay 2024
Last Update Dec 2024
Annual Generation 1.1 GWh
Annual Consumption 3.8 k MMBtu
Ranked #11,401 out of 12,553 Power Plants Nationwide
Ranked #6,073 out of 6,410 Solar Power Plants Nationwide
Ranked #1,521 out of 1,601 California Power Plants
Ranked #788 out of 849 California Solar Power Plants
Fuel Types Solar

Map of Sutter Home Winery TCC

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Sutter Home Winery TCC.

Create Your Account Today

Monthly Net Generation for Sutter Home Winery TCC

Sutter Home Winery TCC Details

Summary Information
Plant NameSutter Home Winery TCC (68630)
Plant Address8998 N River Road, Paso Robles, CA 93446
UtilityREC SHW, LLC (67006)
Latitude, Longitude35.73561, -120.68527
Generation Dates on FileMay 2024 to Dec 2024
Initial Operation DateMay 2024
Annual Generation 1.1 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator (CISO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment
Transmission / Distribution OwnerPacific Gas & Electric Co. (14328) CA
Grid Voltage 12.47 kV
Energy StorageNo

Generator SHTCC Details Operating May 2024

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity1.1 MW
Summer Capacity1.1 MW
Winter Capacity1.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateMay 2024
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Solar Details
Single Axis TrackingYes
Azimuth Angle180
DC Net Capacity1.2 MW
Crystalline SiliconYes
Net Metering AgreementYes
Net Metering DC Capacity0.4 MW
Virtual Net Metering AgreementYes
Virtual Net Metering DC Capacity0.7 MW

Sutter Home Winery TCC Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#6063Wilzig Associates, LLCEast Rutherford, NJ1.1 GWh
#6064Goldman Sachs Carports SolarCohoes, NY1.1 GWh
#6065Industry MetroLink PV 1Industry, CA1.1 GWh
#6066MA Solar Storage 1 HybridSterling, MA1.1 GWh
#6067SV Gardner 1 (Lutz) CSGGardner, IL1.1 GWh
#6068500 Virginia SolarFt. Washington, PA1.1 GWh
#6069Harmon DC Totowa NJTotowa, NJ1.1 GWh
#6070Patriots StadiumBridgewater, NJ1.1 GWh
#6071Decatur Co. Solar RES (IN)Greensburg, IN1.1 GWh
#6072Warrior Solar PartnersFrankfort, NY1.1 GWh
#6074Fareway Customer Hosted 1 MW SolarBoone, IA1.1 GWh
#6075UMass BostonDorchester, MA1.1 GWh
#6076SunEdison LV Sutton Plant SiteWilmington, NC1.1 GWh
#6078MLH 3Gainesville, FL1.1 GWh
#6079Martins Creek Solar NC, LLCMurphy, NC1.1 GWh
#6080Roger Road WWTPTucson, AZ1.1 GWh
#6081Nordhoff PlaceChatsworth, CA1.1 GWh
#6082CVEC Round 4 Brewster Captn Golf CourseBrewster, MA1.1 GWh
#6083Google Bayhill Solar PV and MicrogridSan Bruno, CA1.0 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Sutter Home Winery TCC.

Plant NamePlant LocationAnnual GenerationDistance
Aera San Ardo Cogen FacilitySan Ardo, CA17.2 GWh17.9 mi
Atascadero State HospitalAtascadero, CA2.8 GWh19 mi
Blackjack SolarKing City, CA8.8 GWh36.2 mi
CA Flats Solar 130, LLCShandon, CA258.8 GWh17.8 mi
CA Flats Solar 150, LLCShandon, CA299.6 GWh17.8 mi
CA-DGS RFP-Pleasant Valley State PrisonCoalinga, CA4.0 GWh36.5 mi
CA-DGS-California Men's ColonySan Luis Obispo, CA4.6 GWh28.3 mi
Camp San Luis ObispoSan Luis Obispo, CA158.0 MWh28.7 mi
CED AvenalAvenal, CA9.7 GWh34.9 mi
Coalinga 25D CogenCoalinga, CA42.3 GWh33.2 mi
Coalinga Cogeneration FacilityCoalinga, CA35.9 GWh35 mi
Firestone Walker Brewery - Phase 1Paso Robles, CA3.3 GWh9.7 mi
Meridian VineyardsPaso Robles, CA1.0 GWh8 mi
Nacimiento Hydro ProjectBradley, CA18.2 GWh11.9 mi
Paso Robles - Municipal AirportPaso Robles, CA6.0 GWh4.8 mi
Salinas River CogenerationSan Ardo, CA255.3 GWh18.1 mi
Sand Drag LLCAvenal, CA28.2 GWh36.4 mi
Stenner Creek SolarSan Luis Obispo, CA9.5 GWh28.7 mi
Sun City Project LLCAvenal, CA33.9 GWh36.5 mi
Vintner SolarTempleton, CA4.2 GWh12.3 mi