Dry Lake Solar Energy Center
TBD, Moapa, NV 89025Plant Summary Information
Dry Lake Solar Energy Center is ranked #30 out of 107 power plants in Nevada in terms of total annual net electricity generation.
Dry Lake Solar Energy Center generated 78.6 GWh during the 3-month period between December 2024 to March 2025.
Plant Name | Dry Lake Solar Energy Center |
---|---|
Utility Name | Nevada Power Co |
Location | Clark County, NV |
Initial Operation Date | May 2024 |
Last Update | Mar 2025 |
Annual Generation | 339.1 GWh |
Annual Consumption | 1.2 M MMBtu |
Ranked #1,748 out of 12,288 Power Plants Nationwide | |
Ranked #145 out of 6,174 Solar Power Plants Nationwide | |
Ranked #30 out of 107 Nevada Power Plants | |
Ranked #13 out of 60 Nevada Solar Power Plants | |
Fuel Types | Solar |
Previous Operator |
Nevada Power Company DBA NV Energy (2019 to 2019) Nevada Power Co (2020 to 2024) |
Map of Dry Lake Solar Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Dry Lake Solar Energy Center.
Monthly Net Generation for Dry Lake Solar Energy Center
Dry Lake Solar Energy Center Details
Summary Information | |
---|---|
Plant Name | Dry Lake Solar Energy Center (63933) |
Plant Address | TBD, Moapa, NV 89025 |
Utility | Nevada Power Co (13407) |
Latitude, Longitude | 36.42726, -114.89072 |
Generation Dates on File | May 2024 to Mar 2025 |
Initial Operation Date | May 2024 |
Annual Generation | 339.1 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Nevada Power Company (NEVP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Nevada Power Co (13407) NV |
Grid Voltage | 230.00 kV |
Energy Storage | Yes |
Generator DLES1 Details Operating May 2024
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 100 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 100 MW |
Winter Capacity | 100 MW |
Minimum Load | 1 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | May 2024 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Electricity used for energy storage |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 150 |
---|---|
Maximum Charge Rate | 100 MW |
Maximum Discharge Rate | 100 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 150 |
Storage Enclosure Type | CS |
Excess Wind And Solar Generation | P |
Ac Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 63933 |
Direct Support Gen Id | DLES1 |
Support T D Asset | Yes |
Generator DLPV1 Details Operating May 2024
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 150 MW |
Nameplate Power Factor | 0.95 |
Summer Capacity | 150 MW |
Winter Capacity | 130 MW |
Minimum Load | 1 MW |
---|---|
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | May 2024 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Bifacial | Yes |
Azimuth Angle | 2 |
DC Net Capacity | 180 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Dry Lake Solar Energy Center Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#135 | Prairie Wolf Solar LLC | Ashmore Township, IL | 367.9 GWh |
#136 | Edwards Sanborn E1B | Mojave, CA | 348.6 GWh |
#137 | Blythe Solar III, LLC Hybrid | Blythe, CA | 353.1 GWh |
#138 | Solar Gen 2 Solar Facility | Calipatria, CA | 364.2 GWh |
#139 | Red Tailed Hawk Solar LLC | Pierce, TX | 360.9 GWh |
#140 | Zier Solar | Brackettville, TX | 354.4 GWh |
#141 | Copper Mountain Solar 2 | Boulder City, NV | 356.1 GWh |
#142 | Calhoun Solar | Battle Creek, MI | 356.0 GWh |
#143 | BigBeau Solar, LLC | Rosamond, CA | 353.1 GWh |
#144 | Wright Solar Park | Los Banos, CA | 354.3 GWh |
#146 | Camilla Solar Energy Project | Camilla, GA | 353.8 GWh |
#147 | Lund Hill Solar | Bickleton, WA | 352.8 GWh |
#148 | Centinela Solar Energy | Calexico, CA | 352.7 GWh |
#149 | Newport Solar Project | Newport, AR | 352.5 GWh |
#150 | Blythe Solar II, LLC | Blythe, CA | 337.6 GWh |
#151 | Aragorn Solar Project | Van Horn, TX | 347.3 GWh |
#152 | Orion III Solar Project | Buckholts, TX | 347.2 GWh |
#153 | Upton County Solar | McCamey, TX | 345.3 GWh |
#154 | Edwards Sanborn E1A | Mojave, CA | 329.9 GWh |
#155 | Crooked Lake Solar, LLC | Blytheville, AR | 344.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Dry Lake Solar Energy Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Apex Generating Station | Las Vegas, NV | 1.4 TWh | 4 mi |
Apex Solar PV Power Project | North Las Vegas, NV | 50.3 GWh | 5.1 mi |
Arrow Canyon Solar Hybrid | Moapa, NV | 614.0 GWh | 3.4 mi |
Chuck Lenzie Generating Station | Apex, NV | 4.8 TWh | 3.5 mi |
Gemini Solar Hybrid | Unincorporated, NV | 2.0 TWh | 5.5 mi |
Harry Allen | Las Vegas, NV | 3.4 TWh | 0.7 mi |
Harry Allen Solar Energy LLC | Apex, NV | 298.3 GWh | 3.2 mi |
IGS VGT | North Las Vegas, NV | 2.1 GWh | 13.9 mi |
Moapa Southern Paiute | Moapa, NV | 623.1 GWh | 9.8 mi |
Mountain View Solar | North Las Vegas, NV | 55.2 GWh | 4.8 mi |
Nellis Air Force Base Solar Array | Las Vegas, NV | 23.8 GWh | 14.7 mi |
Nellis Solar PV II | North Las Vegas, NV | 36.4 GWh | 17.6 mi |
Nevada Cogen Assoc#1 GarnetVly | Las Vegas, NV | 351.5 GWh | 6 mi |
Nevada Cogen Associates 2 Black Mountain | Las Vegas, NV | 332.2 GWh | 14 mi |
Playa Solar 1, LLC | North Las Vegas, NV | 186.3 GWh | 1.6 mi |
Playa Solar 2 | North Las Vegas, NV | 255.8 GWh | 1.6 mi |
Republic Services Renewable Energy, LLC | Las Vegas, NV | 26.3 GWh | 4.8 mi |
Silverhawk | North Las Vegas, NV | 2.8 TWh | 4.1 mi |
Spectrum Solar PV Power Project | Las Vegas, NV | 84.0 GWh | 13.7 mi |
TJX Las Vegas | North Las Vegas, NV | 2.4 GWh | 16.2 mi |