Chuck Lenzie Generating Station
11405 US Highway 93, Apex, NV 89124Plant Summary Information
Chuck Lenzie Generating Station is ranked #1 out of 110 power plants in Nevada in terms of total annual net electricity generation.
Chuck Lenzie Generating Station is comprised of 6 generators and generated 1.7 TWh during the 3-month period between April 2025 to July 2025.
Plant Name | Chuck Lenzie Generating Station |
---|---|
Utility Name | Nevada Power Co |
Location | Clark County, NV |
Initial Operation Date | January 2006 |
Last Update | Jul 2025 |
Annual Generation | 4.8 TWh |
Annual Consumption | 40.0 M MMBtu |
Ranked #229 out of 12,530 Power Plants Nationwide | |
Ranked #111 out of 2,241 Natural Gas Power Plants Nationwide | |
Ranked #1 out of 110 Nevada Power Plants | |
Ranked #1 out of 17 Nevada Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Chuck Lenzie Generating Station
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Chuck Lenzie Generating Station.
Monthly Net Generation for Chuck Lenzie Generating Station
Chuck Lenzie Generating Station Details
Summary Information | |
---|---|
Plant Name | Chuck Lenzie Generating Station (55322) |
Plant Address | 11405 US Highway 93, Apex, NV 89124 |
Utility | Nevada Power Co (13407) |
Latitude, Longitude | 36.38372, -114.92178 |
Generation Dates on File | Feb 2006 to Jul 2025 |
Initial Operation Date | January 2006 |
Annual Generation | 4.8 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Nevada Power Company (NEVP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Wells |
Ash Impoundment | |
Transmission / Distribution Owner | Nevada Power Co (13407) NV |
Grid Voltage | 500.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name | KERN RIVER GAS TRANSMISSION CO |
Natural Gas Storage | No |
Generator CTG1 Details Operating January 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | PB1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 201.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 184 MW |
Winter Capacity | 179 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator CTG2 Details Operating January 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | PB1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 201.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 184 MW |
Winter Capacity | 179 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator ST1 Details Operating January 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | PB1 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 329.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 253 MW |
Winter Capacity | 265 MW |
Minimum Load | 45 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | January 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Generator CTG3 Details Operating April 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | PB2 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 201.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 184 MW |
Winter Capacity | 179 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator CTG4 Details Operating April 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | PB2 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 201.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 184 MW |
Winter Capacity | 179 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Generator ST2 Details Operating April 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | PB2 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 329.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 253 MW |
Winter Capacity | 265 MW |
Minimum Load | 45 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Chuck Lenzie Generating Station Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#101 | Waterford Power, LLC | Waterford, OH | 5.0 TWh |
#102 | Zeeland Generating Station | Zeeland, MI | 5.0 TWh |
#103 | Redbud Power Plant | Luther, OK | 5.0 TWh |
#104 | CPV Valley Energy Center | Wawayanda, NY | 5.0 TWh |
#105 | Pasadena Cogeneration | Pasadena, TX | 5.0 TWh |
#106 | Rio Nogales Power Project | Seguin, TX | 4.9 TWh |
#107 | Hill Top Energy Center, LLC | Carmichaels, PA | 4.9 TWh |
#108 | Morgan Energy Center | Decatur, AL | 4.9 TWh |
#109 | Choctaw County | French Camp, MS | 4.9 TWh |
#110 | Potomac Energy Center, LLC | Leesburg, VA | 4.8 TWh |
#112 | Keys Energy Center | Brandywine, MD | 4.8 TWh |
#113 | John Sevier | Rogersville, TN | 4.8 TWh |
#114 | Ironwood LLC | Lebanon, PA | 4.8 TWh |
#115 | PSEG Linden Generating Station | Linden, NJ | 4.7 TWh |
#116 | Taft Cogeneration Facility | Hahnville, LA | 4.8 TWh |
#117 | West Riverside Energy Center | Beloit, WI | 4.7 TWh |
#118 | Formosa Utility Venture Ltd | Point Comfort, TX | 4.7 TWh |
#119 | H L Culbreath Bayside Power Station | Tampa, FL | 4.6 TWh |
#120 | Red Hawk | Arlington, AZ | 4.6 TWh |
#121 | TVA Southaven Combined Cycle | Southaven, MS | 4.5 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Chuck Lenzie Generating Station.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Apex Generating Station | Las Vegas, NV | 1.2 TWh | 3.1 mi |
Apex Solar PV Power Project | North Las Vegas, NV | 50.3 GWh | 2.7 mi |
Arrow Canyon Solar Hybrid | Moapa, NV | 609.0 GWh | 6.8 mi |
Dry Lake Solar Energy Center | Moapa, NV | 353.4 GWh | 3.5 mi |
Gemini Solar Hybrid | Unincorporated, NV | 2.2 TWh | 8.7 mi |
Harry Allen | Las Vegas, NV | 3.3 TWh | 3.4 mi |
Harry Allen Solar Energy LLC | Apex, NV | 300.4 GWh | 3.7 mi |
IGS VGT | North Las Vegas, NV | 2.1 GWh | 10.5 mi |
Moapa Southern Paiute | Moapa, NV | 617.7 GWh | 13.2 mi |
Mountain View Solar | North Las Vegas, NV | 53.3 GWh | 2.4 mi |
Nellis Air Force Base Solar Array | Las Vegas, NV | 23.8 GWh | 11.3 mi |
Nellis Solar PV II | North Las Vegas, NV | 32.4 GWh | 14.1 mi |
Nevada Cogen Assoc#1 GarnetVly | Las Vegas, NV | 322.6 GWh | 2.8 mi |
Nevada Cogen Associates 2 Black Mountain | Las Vegas, NV | 336.4 GWh | 11.2 mi |
Playa Solar 1, LLC | North Las Vegas, NV | 182.1 GWh | 1.8 mi |
Playa Solar 2 | North Las Vegas, NV | 255.1 GWh | 1.8 mi |
Republic Services Renewable Energy, LLC | Las Vegas, NV | 26.3 GWh | 3.1 mi |
Silverhawk | North Las Vegas, NV | 2.8 TWh | 2.7 mi |
Spectrum Solar PV Power Project | Las Vegas, NV | 84.0 GWh | 11 mi |
TJX Las Vegas | North Las Vegas, NV | 2.4 GWh | 12.8 mi |