Brazoria West
2546 County Road 23, Damon, TX 77422Plant Summary Information
Brazoria West is ranked #25 out of 150 solar farms in Texas in terms of total annual net electricity generation.
Brazoria West generated 96.7 GWh during the 3-month period between November 2023 to February 2024.
Plant Name | Brazoria West |
---|---|
Utility Name | Brazoria West Solar Project, LLC |
Location | Brazoria County, TX |
Initial Operation Date | September 2022 |
Last Update | Feb 2024 |
Annual Generation | 441.2 GWh |
Annual Consumption | 1.5 M MMBtu |
Ranked #1,488 out of 11,455 Power Plants Nationwide | |
Ranked #68 out of 5,173 Solar Power Plants Nationwide | |
Ranked #274 out of 726 Texas Power Plants | |
Ranked #25 out of 150 Texas Solar Power Plants | |
Fuel Types | Solar |
Map of Brazoria West
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Brazoria West.
Monthly Net Generation for Brazoria West
Brazoria West Details
Summary Information | |
---|---|
Plant Name | Brazoria West (64447) |
Plant Address | 2546 County Road 23 Damon, TX 77422 |
Utility | Brazoria West Solar Project, LLC (64108) |
Latitude, Longitude | 29.191, -95.663 |
Generation Dates on File | Jun 2022 to Feb 2024 |
Initial Operation Date | September 2022 |
Annual Generation | 441.2 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | CenterPoint Energy (8901) TX |
Grid Voltage | 138.00 kV |
Energy Storage | No |
Generator GEN1 Details Operating September 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 200 MW |
Summer Capacity | 200 MW |
Winter Capacity | 200 MW |
Minimum Load | 0.1 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | September 2022 |
---|---|
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Multiple Fuels | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Azimuth Angle | 180 |
DC Net Capacity | 260 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Brazoria West Plant Owners
Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#58 | ANSON Solar Center, LLC | Anson, TX | 473.8 GWh |
#59 | Muscle Shoals | Cherokee, AL | 473.2 GWh |
#60 | RE Garland | Rosamond, CA | 451.8 GWh |
#61 | Townsite Solar Project Hybrid | Boulder City, NV | 446.9 GWh |
#62 | Brazoria County Solar Project (Danciger) | Damon, TX | 456.8 GWh |
#63 | RE Tranquillity | Cantua Creek, CA | 444.4 GWh |
#64 | Desert Sunlight 250, LLC | Desert Center, CA | 450.0 GWh |
#65 | Aragorn Solar Project | Van Horn, TX | 448.2 GWh |
#66 | Springbok Solar Farm 2 | Cantil, CA | 444.6 GWh |
#67 | Imperial Solar Energy Center West | Seeley, CA | 444.2 GWh |
#69 | Shakes Solar | Carrizo Springs, TX | 440.0 GWh |
#70 | Hickory Park Solar Hybrid | Camilla, GA | 433.5 GWh |
#71 | Holstein 1 Solar Farm | Wingate, TX | 434.5 GWh |
#72 | CED Crane Solar | Crane, TX | 433.6 GWh |
#73 | Mesquite Solar 1 | Tonopah, AZ | 433.0 GWh |
#74 | Riverstart Solar Park LLC | Modoc, IN | 426.5 GWh |
#75 | Impact Solar 1 | Deport, TX | 426.4 GWh |
#76 | Castle Gap Solar Hybrid | McCarney, TX | 423.2 GWh |
#77 | Solar Gen 2 Solar Facility | Calipatria, CA | 420.1 GWh |
#78 | Samson Solar Energy | Cunningham, TX | 417.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Brazoria West.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
BASF Freeport Works | Feeeport, TX | 595.6 GWh | 20.8 mi |
Braes Bayou Plant | Richmond, TX | 313.2 GWh | 20.2 mi |
Brazoria County Solar Project (Danciger) | Damon, TX | 456.8 GWh | 6 mi |
Brotman Power Station | Rosharon, TX | 285.5 GWh | 18.2 mi |
Cascade Solar (TX) | Wharton, TX | 21.9 GWh | 21.8 mi |
Cutlass Solar 1 LLC | Richmond, TX | 227.9 GWh | 15.7 mi |
Fighting Jays Solar Project | Needville, TX | 518.0 GWh | 12.6 mi |
Freeport Energy | Freeport, TX | 2.5 TWh | 20.7 mi |
Freeport Energy Center | Freeport, TX | 1.4 TWh | 21.4 mi |
HEB00110 | Missouri City, TX | 269.7 MWh | 25.1 mi |
HEB00292 | Bay City, TX | 285.5 MWh | 22.9 mi |
Jack Fusco Energy Center | Thompsons, TX | 3.6 TWh | 19.6 mi |
Longbow Solar, LLC | Liverpool, TX | 194.0 GWh | 23 mi |
Mark One Power Station | Angleton, TX | 114.8 GWh | 14.2 mi |
Mckeever | Fresno, TX | 503.0 MWh | 24.6 mi |
Oyster Creek Unit VIII | Freeport, TX | 2.9 TWh | 24.2 mi |
Praxair | Clute, TX | 340.1 MWh | 21 mi |
Sweeny Cogen Facility | Old Ocean, TX | 2.4 TWh | 9.5 mi |
W A Parish | Thompsons, TX | 11.5 TWh | 20.3 mi |
Wagyu | Damon, TX | 206.8 GWh | 3.6 mi |