intersection of HWY 93 and Gra, North Las Vegas, NV 59165Plant Summary Information
Playa Solar 1, LLC is ranked #47 out of 112 power plants in Nevada in terms of total annual net electricity generation.
Playa Solar 1, LLC generated 63.5 GWh during the 3-month period between March 2026 to June 2026.
| Plant Name | Playa Solar 1, LLC |
|---|---|
| Utility Name | EDF Renewable Asset Holdings, Inc. |
| Location | Clark County, NV |
| Initial Operation Date | October 2017 |
| Last Update | Jun 2026 |
| Annual Generation | 189.1 GWh |
| Annual Consumption | 718.8 k MMBtu |
| Ranked #2,628 out of 13,094 Power Plants Nationwide | |
| Ranked #508 out of 7,027 Solar Power Plants Nationwide | |
| Ranked #47 out of 112 Nevada Power Plants | |
| Ranked #25 out of 63 Nevada Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operators |
First Solar Project Development (2014 to 2014) First Solar Asset Management (2015 to 2016) EDF Renewable Asset Holdings, Inc. (2017 to 2025) |
Map of Playa Solar 1, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Playa Solar 1, LLC.
Monthly Net Generation for Playa Solar 1, LLC
Monthly Plant Fuel Consumption for Playa Solar 1, LLC
Playa Solar 1, LLC Details
| Summary Information | |
|---|---|
| Plant Name | Playa Solar 1, LLC (59827) |
| Plant Address | intersection of HWY 93 and Gra, North Las Vegas, NV 59165 |
| Utility | EDF Renewable Asset Holdings, Inc. (57170) |
| Latitude, Longitude | 36.408, -114.908 |
| Generation Dates on File | Jun 2017 to Jun 2026 |
| Initial Operation Date | October 2017 |
| Annual Generation | 189.1 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Nevada Power Company (NEVP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Nevada Power Co (13407) NV |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator GEN01 Details Operating October 2017
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 79 MW |
| Summer Capacity | 79 MW |
| Winter Capacity | 79 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | October 2017 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Fixed Tilt | No |
| DC Net Capacity | 99 MW |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Playa Solar 1, LLC Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #498 | Three Creeks | Parrish, FL | 192.5 GWh |
| #499 | Gilchrist County Solar | Newberry, FL | 191.7 GWh |
| #500 | Kelso Solar | Benton, MO | 191.2 GWh |
| #501 | Tilden Solar | Coulterville, IL | 190.9 GWh |
| #502 | Honeybell | TBD, FL | 190.6 GWh |
| #503 | Blackwater Solar | Bickley, GA | 190.6 GWh |
| #504 | Buttonwood | Fort Pierce, FL | 190.2 GWh |
| #505 | RE Astoria | Rosamond, CA | 189.6 GWh |
| #506 | Buckeye Solar | Williamsport, OH | 189.5 GWh |
| #507 | Speckled Perch | TBD, FL | 189.1 GWh |
| #509 | Ivanpah 1 | Nipton, CA | 196.5 GWh |
| #510 | Mule Creek Renewable Energy Center | Panama City, FL | 188.8 GWh |
| #511 | Steel Solar LLC | Plymouth, UT | 188.7 GWh |
| #512 | Southampton Solar, LLC | Newsoms, VA | 188.6 GWh |
| #513 | Sadler Solar | Emporia, VA | 188.4 GWh |
| #514 | Second Division Solar | West Columbia, TX | 188.2 GWh |
| #515 | Hog Bay | TBD, FL | 188.0 GWh |
| #516 | Crossroads Solar (IN) | Van Buren Township, IN | 187.9 GWh |
| #517 | White Pine Solar, LLC | Butler, GA | 187.9 GWh |
| #518 | Bell Ridge Solar | Trenton, FL | 187.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Playa Solar 1, LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Apex Generating Station | Las Vegas, NV | 1.7 TWh | 3 mi |
| Apex Solar PV Power Project | North Las Vegas, NV | 48.0 GWh | 3.7 mi |
| Arrow Canyon Solar Hybrid | Moapa, NV | 604.1 GWh | 5 mi |
| Chuck Lenzie Generating Station | Apex, NV | 6.3 TWh | 1.8 mi |
| Dry Lake Solar Energy Center | Moapa, NV | 401.9 GWh | 1.6 mi |
| Gemini Solar Hybrid | Unincorporated, NV | 2.1 TWh | 7 mi |
| Harry Allen | Las Vegas, NV | 3.0 TWh | 1.6 mi |
| Harry Allen Solar Energy LLC | Apex, NV | 300.5 GWh | 2.8 mi |
| IGS VGT | North Las Vegas, NV | 2.1 GWh | 12.2 mi |
| Moapa Southern Paiute | Moapa, NV | 612.9 GWh | 11.4 mi |
| Mountain View Solar | North Las Vegas, NV | 52.3 GWh | 3.4 mi |
| Nellis Air Force Base Solar Array | Las Vegas, NV | 23.4 GWh | 13.1 mi |
| Nellis Solar PV II | North Las Vegas, NV | 11.1 GWh | 15.9 mi |
| Nevada Cogen Assoc#1 GarnetVly | Las Vegas, NV | 271.8 GWh | 4.5 mi |
| Nevada Cogen Associates 2 Black Mountain | Las Vegas, NV | 254.0 GWh | 12.7 mi |
| Playa Solar 2 | North Las Vegas, NV | 259.8 GWh | 0 mi |
| Republic Services Renewable Energy, LLC | Las Vegas, NV | 25.5 GWh | 3.9 mi |
| Silverhawk | North Las Vegas, NV | 2.7 TWh | 2.9 mi |
| Spectrum Solar PV Power Project | Las Vegas, NV | 81.8 GWh | 12.5 mi |
| TJX Las Vegas | North Las Vegas, NV | 2.3 GWh | 14.5 mi |