Playa Solar 2
intersection of HWY 93 and Gra, North Las Vegas, NV 59165Plant Summary Information
Playa Solar 2 is ranked #41 out of 110 power plants in Nevada in terms of total annual net electricity generation.
Playa Solar 2 generated 77.5 GWh during the 3-month period between June 2025 to September 2025.
| Plant Name | Playa Solar 2 |
|---|---|
| Utility Name | EDF Renewable Asset Holdings, Inc. |
| Location | Clark County, NV |
| Initial Operation Date | August 2017 |
| Last Update | Sep 2025 |
| Annual Generation | 254.8 GWh |
| Annual Consumption | 943.7 k MMBtu |
| Ranked #2,174 out of 12,539 Power Plants Nationwide | |
| Ranked #309 out of 6,400 Solar Power Plants Nationwide | |
| Ranked #41 out of 110 Nevada Power Plants | |
| Ranked #20 out of 61 Nevada Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operator |
First Solar Asset Management (2015 to 2016) EDF Renewable Asset Holdings, Inc. (2017 to 2024) |
Map of Playa Solar 2
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Playa Solar 2.
Monthly Net Generation for Playa Solar 2
Playa Solar 2 Details
| Summary Information | |
|---|---|
| Plant Name | Playa Solar 2 (60261) |
| Plant Address | intersection of HWY 93 and Gra, North Las Vegas, NV 59165 |
| Utility | EDF Renewable Asset Holdings, Inc. (57170) |
| Latitude, Longitude | 36.408, -114.908 |
| Generation Dates on File | Jul 2017 to Sep 2025 |
| Initial Operation Date | August 2017 |
| Annual Generation | 254.8 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Nevada Power Company (NEVP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Nevada Power Co (13407) NV |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator GEN1 Details Operating August 2017
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 100 MW |
| Summer Capacity | 100 MW |
| Winter Capacity | 100 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | August 2017 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| DC Net Capacity | 136.9 MW |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Playa Solar 2 Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #299 | West Line Solar, LLC | City of Eloy, AZ | 260.3 GWh |
| #300 | Oak Solar | Gaston, NC | 259.8 GWh |
| #301 | Bellflower Solar 1 | Lewisville, IN | 259.3 GWh |
| #302 | Emerald Grove | Crane, TX | 258.8 GWh |
| #303 | Paris Solar | Union Grove, WI | 257.8 GWh |
| #304 | Eldorado Solar I | Eldorado, IL | 257.0 GWh |
| #305 | Quinto Solar PV Project | Gustine, CA | 257.0 GWh |
| #306 | Elara Solar | Pearsall, TX | 256.2 GWh |
| #307 | Willow Spring Solar, LLC | Rosamond, CA | 255.9 GWh |
| #308 | Elm Branch Solar 1 | Bardwell, TX | 255.7 GWh |
| #310 | SR Snipesville III | Denton, GA | 254.7 GWh |
| #311 | Bluebell Solar II | Sterling, TX | 254.4 GWh |
| #312 | Maverick Solar 6, LLC | Desert Center, CA | 245.0 GWh |
| #313 | East Line Solar | Coolidge, AZ | 252.9 GWh |
| #314 | Onion River | Sheboygan Cedar Grove, WI | 252.6 GWh |
| #315 | Springbok 3 Solar Farm Hybrid | Cantil, CA | 252.6 GWh |
| #316 | Peacock Energy Project | Taft, TX | 252.1 GWh |
| #317 | Hickory Solar | Jerseyville, IL | 251.8 GWh |
| #318 | Boomtown Renewable Energy Center | Carmi, IL | 250.1 GWh |
| #319 | West of the Pecos Solar | TBD, TX | 249.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Playa Solar 2.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Apex Generating Station | Las Vegas, NV | 1.3 TWh | 3 mi |
| Apex Solar PV Power Project | North Las Vegas, NV | 50.3 GWh | 3.7 mi |
| Arrow Canyon Solar Hybrid | Moapa, NV | 600.6 GWh | 5 mi |
| Chuck Lenzie Generating Station | Apex, NV | 5.1 TWh | 1.8 mi |
| Dry Lake Solar Energy Center | Moapa, NV | 356.8 GWh | 1.6 mi |
| Gemini Solar Hybrid | Unincorporated, NV | 2.2 TWh | 7 mi |
| Harry Allen | Las Vegas, NV | 3.1 TWh | 1.6 mi |
| Harry Allen Solar Energy LLC | Apex, NV | 296.7 GWh | 2.8 mi |
| IGS VGT | North Las Vegas, NV | 2.1 GWh | 12.2 mi |
| Moapa Southern Paiute | Moapa, NV | 613.1 GWh | 11.4 mi |
| Mountain View Solar | North Las Vegas, NV | 51.9 GWh | 3.4 mi |
| Nellis Air Force Base Solar Array | Las Vegas, NV | 23.8 GWh | 13.1 mi |
| Nellis Solar PV II | North Las Vegas, NV | 32.4 GWh | 15.9 mi |
| Nevada Cogen Assoc#1 GarnetVly | Las Vegas, NV | 323.2 GWh | 4.5 mi |
| Nevada Cogen Associates 2 Black Mountain | Las Vegas, NV | 341.3 GWh | 12.7 mi |
| Playa Solar 1, LLC | North Las Vegas, NV | 182.9 GWh | 0 mi |
| Republic Services Renewable Energy, LLC | Las Vegas, NV | 26.3 GWh | 3.9 mi |
| Silverhawk | North Las Vegas, NV | 2.7 TWh | 2.9 mi |
| Spectrum Solar PV Power Project | Las Vegas, NV | 84.0 GWh | 12.5 mi |
| TJX Las Vegas | North Las Vegas, NV | 2.4 GWh | 14.5 mi |