Arrow Canyon Solar Hybrid is ranked #41 out of 6,200 solar farms nationwide in terms of total annual net electricity generation.

Arrow Canyon Solar Hybrid generated 186.1 GWh during the 3-month period between March 2025 to June 2025.

Plant NameArrow Canyon Solar Hybrid
Utility NameArrow Canyon Solar LLC
LocationClark County, NV
Initial Operation DateDecember 2023
Last Update Jun 2025
Annual Generation 605.9 GWh
Annual Consumption 2.4 M MMBtu
Ranked #1,112 out of 12,327 Power Plants Nationwide
Ranked #41 out of 6,200 Solar Power Plants Nationwide
Ranked #19 out of 107 Nevada Power Plants
Ranked #5 out of 60 Nevada Solar Power Plants
Fuel Types Solar

Map of Arrow Canyon Solar Hybrid

Full Screen Map
Use Ctrl + scroll to zoom the map
Use two fingers to move the map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Arrow Canyon Solar Hybrid.

Create Your Account Today

Monthly Net Generation for Arrow Canyon Solar Hybrid

80k80k60k60k40k40k20k20k0020232023Jul '23Jul '2320242024Jul '24Jul '2420252025
Download SVG
Download PNG
Download CSV

Arrow Canyon Solar Hybrid Details

Summary Information
Plant NameArrow Canyon Solar Hybrid (62248)
Plant AddressTBD, Moapa, NV 89025
UtilityArrow Canyon Solar LLC (61768)
Latitude, Longitude36.45926, -114.84439
Generation Dates on FileDec 2022 to Jun 2025
Initial Operation DateDecember 2023
Annual Generation 605.9 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityNevada Power Company (NEVP)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerNevada Power Co (13407) NV
Grid Voltage 230.00 kV
Energy StorageYes

Generator 1 Details Operating December 2023

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity200 MW
Summer Capacity200 MW
Winter Capacity200 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2023
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Time From Cold Shutdown To Full Load12H
Multiple FuelsNo
Solar Details
Dual Axis TrackingYes
BifacialYes
DC Net Capacity273 MW
Crystalline SiliconYes
Net Metering AgreementNo
Virtual Net Metering AgreementNo

Generator 2 Details Operating December 2023

TechnologyBatteries
Prime MoverBattery
OwnershipSingle Owner
Nameplate Capacity75 MW
Summer Capacity75 MW
Winter Capacity75 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateDecember 2023
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceElectricity used for energy storage
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full LoadOVER
Multiple FuelsNo
Energy Storage Details
Nameplate Energy Capacity MWH375
Maximum Charge Rate40 MW
Maximum Discharge Rate40 MW
Storage TechnologyLIB
Nameplate Reactive Power Rating75
Storage Enclosure TypeCS
ArbitrageP
Excess Wind And Solar GenerationYes
DC Tightly CoupledYes
Direct Support Of Another UnitYes
Direct Support Plant Id62248
Direct Support Gen Id1
Support T D AssetNo

Arrow Canyon Solar Hybrid Plant Owners

Owner NameAddressGeneratorOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#31Lumina Solar ProjectSnyder, TX685.5 GWh
#32Lumina II Solar ProjectSnyder, TX684.6 GWh
#33Prospero Solar IIAndrews, TX683.0 GWh
#34Silver State Solar Power SouthPrimm Valley, NV675.2 GWh
#35McCoy Solar Energy Project HybridBlythe, CA646.7 GWh
#36Desert Sunlight 300, LLCDesert Center, CA666.9 GWh
#37Arlington Energy Center IIBlythe, CA639.8 GWh
#38IP Radian, LLCBrookesmith, TX647.1 GWh
#39AquamarineLemoore, CA646.4 GWh
#40Genesis Solar Energy ProjectBlythe, CA631.8 GWh
#42Stateline SolarNipton, CA619.9 GWh
#43Oberon II Solar ProjectDesert Center, CA600.1 GWh
#44Moapa Southern PaiuteMoapa, NV616.7 GWh
#45Copper Mountain Solar 3Boulder City, NV612.7 GWh
#46Blythe Mesa Solar IIBlythe, CA592.4 GWh
#47Victory PassDesert Center, CA600.3 GWh
#48Oberon Solar ProjectDesert Center, CA583.3 GWh
#49California Valley Solar RanchCalifornia Valley, CA597.7 GWh
#50Mojave Solar ProjectHinkley, CA592.9 GWh
#51Titan Solar ProjectVan Horn, TX592.9 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Arrow Canyon Solar Hybrid.

Plant NamePlant LocationAnnual GenerationDistance
Apex Generating StationLas Vegas, NV1.3 TWh7.1 mi
Apex Solar PV Power ProjectNorth Las Vegas, NV50.3 GWh8.5 mi
Chuck Lenzie Generating StationApex, NV5.0 TWh6.8 mi
Dry Lake Solar Energy CenterMoapa, NV348.6 GWh3.4 mi
Eagle Shadow Mountain Solar FarmMoapa, NV915.3 GWh14.8 mi
Gemini Solar HybridUnincorporated, NV2.2 TWh2.2 mi
Harry AllenLas Vegas, NV3.3 TWh3.8 mi
Harry Allen Solar Energy LLCApex, NV298.6 GWh6 mi
IGS VGTNorth Las Vegas, NV2.1 GWh17.2 mi
Moapa Southern PaiuteMoapa, NV616.7 GWh6.4 mi
Mountain View SolarNorth Las Vegas, NV53.6 GWh8.2 mi
Nellis Air Force Base Solar ArrayLas Vegas, NV23.8 GWh18 mi
Nevada Cogen Assoc#1 GarnetVlyLas Vegas, NV323.1 GWh9.1 mi
Nevada Cogen Associates 2 Black MountainLas Vegas, NV334.7 GWh16.3 mi
Playa Solar 1, LLCNorth Las Vegas, NV180.5 GWh5 mi
Playa Solar 2North Las Vegas, NV253.1 GWh5 mi
Republic Services Renewable Energy, LLCLas Vegas, NV26.3 GWh7.2 mi
SilverhawkNorth Las Vegas, NV2.9 TWh7.4 mi
Spectrum Solar PV Power ProjectLas Vegas, NV84.0 GWh15.9 mi
TJX Las VegasNorth Las Vegas, NV2.4 GWh19.5 mi