Centinela Solar Energy
319 Brockman Road, Calexico, CA 92231Plant Summary Information
Centinela Solar Energy is ranked #38 out of 886 solar farms in California in terms of total annual net electricity generation.
Centinela Solar Energy generated 89.5 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Centinela Solar Energy |
|---|---|
| Utility Name | Centinela Solar Energy LLC |
| Location | Imperial County, CA |
| Initial Operation Date | July 2013 |
| Last Update | Dec 2025 |
| Annual Generation | 448.6 GWh |
| Annual Consumption | 1.6 M MMBtu |
| Ranked #1,488 out of 13,094 Power Plants Nationwide | |
| Ranked #155 out of 7,027 Solar Power Plants Nationwide | |
| Ranked #94 out of 1,607 California Power Plants | |
| Ranked #38 out of 886 California Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operators |
Centinela Solar Energy LLC (2013 to 2025) CD Arevon USA, Inc. (2020 to 2021) Arevon Energy, Inc. (2022 to 2024) |
Map of Centinela Solar Energy
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Centinela Solar Energy.
Monthly Net Generation for Centinela Solar Energy
Monthly Plant Fuel Consumption for Centinela Solar Energy
Centinela Solar Energy Details
| Summary Information | |
|---|---|
| Plant Name | Centinela Solar Energy (58430) |
| Plant Address | 319 Brockman Road, Calexico, CA 92231 |
| Utility | Centinela Solar Energy LLC (58427) |
| Latitude, Longitude | 32.68694, -115.64778 |
| Generation Dates on File | Jul 2013 to Dec 2025 |
| Initial Operation Date | July 2013 |
| Annual Generation | 448.6 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | San Diego Gas & Electric Co (16609) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator CSE3 Details Operating October 2013
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 34.2 MW |
| Summer Capacity | 33.4 MW |
| Winter Capacity | 33.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | October 2013 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 90 |
| DC Net Capacity | 49.7 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator CSE4 Details Operating December 2013
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 34.2 MW |
| Summer Capacity | 33.4 MW |
| Winter Capacity | 33.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | December 2013 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 90 |
| DC Net Capacity | 49.8 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator CSE1 Details Operating July 2013
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 34.2 MW |
| Summer Capacity | 33.4 MW |
| Winter Capacity | 33.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 2013 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 90 |
| DC Net Capacity | 48.9 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator CSE2 Details Operating August 2013
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 26.6 MW |
| Summer Capacity | 25.6 MW |
| Winter Capacity | 25.6 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | August 2013 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 90 |
| DC Net Capacity | 38.6 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator CSE5 Details Operating April 2014
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 19 MW |
| Summer Capacity | 18.6 MW |
| Winter Capacity | 18.6 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | April 2014 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 90 |
| DC Net Capacity | 27.6 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator CSE6 Details Operating May 2014
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 26.6 MW |
| Summer Capacity | 25.6 MW |
| Winter Capacity | 25.6 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 2014 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 90 |
| DC Net Capacity | 38.3 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Centinela Solar Energy Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #145 | Golden Triangle | Lowndes, MS | 456.4 GWh |
| #146 | Taygete II Energy Project | Coyanosa, TX | 462.9 GWh |
| #147 | Hecate Energy Longhorn Solar LLC | Jacksboro, TX | 461.4 GWh |
| #148 | Sandrini Solar 200 | Mettler, CA | 457.7 GWh |
| #149 | Hornshadow Solar II, LLC | Castle Dale, UT | 456.4 GWh |
| #150 | Horizon Solar | Pearsall, TX | 455.8 GWh |
| #151 | Pisgah Ridge Solar, LLC | Richland, TX | 453.7 GWh |
| #152 | Techren Solar II LLC | Boulder, NV | 452.3 GWh |
| #153 | White Wing Solar | Yuma, AZ | 451.0 GWh |
| #154 | Pixley Solar Energy | Medicine Lodge, KS | 448.9 GWh |
| #156 | Sun Streams 3 | Arlington, AZ | 413.1 GWh |
| #157 | Pleinmont Solar 2 | Spotsylvania, VA | 445.6 GWh |
| #158 | Mesquite Solar 3, LLC | Tonopah, AZ | 443.8 GWh |
| #159 | Serrano | Marana, AZ | 416.5 GWh |
| #160 | Cutlass Solar II | Richmond, TX | 441.8 GWh |
| #161 | Imperial Valley Solar, LLC | Calexico, CA | 441.7 GWh |
| #162 | Tres Bahias | Port Lavaca, TX | 438.7 GWh |
| #163 | Pike Solar Hybrid | Fountain, CO | 436.5 GWh |
| #164 | Dunns Bridge I Solar | Wheatfield, IN | 436.0 GWh |
| #165 | Muscle Shoals | Cherokee, AL | 435.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Centinela Solar Energy.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Campo Verde Solar | El Centro, CA | 292.7 GWh | 6.5 mi |
| Centinela State Prison | Sacramento, CA | 18.0 GWh | 12.4 mi |
| Drew Solar LLC | Calexico, CA | 308.2 GWh | 1 mi |
| Drop 5 (CA) | Calexico, CA | 5.6 GWh | 14.9 mi |
| El Centro Hybrid | El Centro, CA | 913.4 GWh | 10.1 mi |
| Heber Geothermal | Heber, CA | 376.3 GWh | 7.8 mi |
| Heber Solar | Heber, CA | 24.1 GWh | 6.5 mi |
| Imperial Solar Energy Center South | Calexico, CA | 251.1 GWh | 1.7 mi |
| Imperial Solar Energy Center West | Seeley, CA | 357.0 GWh | 9.7 mi |
| Imperial Valley Solar, LLC | Calexico, CA | 441.7 GWh | 3.7 mi |
| IVC Solar | Imperial, CA | 4.2 GWh | 12.9 mi |
| Mount Signal Solar Farm II | Calexico, CA | 364.5 GWh | 1.7 mi |
| Mount Signal Solar Farm V | Calexico, CA | 635.0 GWh | 4.7 mi |
| Second Imperial Geothermal | Heber, CA | 275.2 GWh | 6.8 mi |
| SEPV Imperial Dixieland East | Imperial, CA | 5.3 GWh | 10.3 mi |
| SEPV Imperial Dixieland West | Imperial, CA | 8.5 GWh | 10.6 mi |
| Sol Orchard El Centro PV | El Centro, CA | 45.1 GWh | 10 mi |
| USG 1 | El Centro, CA | 3.0 GWh | 14.2 mi |
| USG 2 | El Centro, CA | 2.0 GWh | 14.4 mi |
| Wistaria Ranch Solar | Calexico, CA | 269.4 GWh | 1.8 mi |