Cutlass Solar II
Intersection of Boothline Rd a, Richmond, TX 77469Plant Summary Information
Cutlass Solar II is ranked #59 out of 215 solar farms in Texas in terms of total annual net electricity generation.
Cutlass Solar II generated 95.6 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Cutlass Solar II |
|---|---|
| Utility Name | Cutlass II Solar LLC |
| Location | Fort Bend County, TX |
| Initial Operation Date | July 2024 |
| Last Update | Dec 2025 |
| Annual Generation | 417.8 GWh |
| Annual Consumption | 1.5 M MMBtu |
| Ranked #1,548 out of 12,613 Power Plants Nationwide | |
| Ranked #152 out of 6,463 Solar Power Plants Nationwide | |
| Ranked #310 out of 816 Texas Power Plants | |
| Ranked #59 out of 215 Texas Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operator |
CT Cutlass II Solar LLC (2022 to 2022) Cutlass II Solar LLC (2023 to 2024) |
Map of Cutlass Solar II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cutlass Solar II.
Monthly Net Generation for Cutlass Solar II
Monthly Plant Fuel Consumption for Cutlass Solar II
Cutlass Solar II Details
| Summary Information | |
|---|---|
| Plant Name | Cutlass Solar II (66262) |
| Plant Address | Intersection of Boothline Rd a, Richmond, TX 77469 |
| Utility | Cutlass II Solar LLC (65361) |
| Latitude, Longitude | 29.39, -95.78 |
| Generation Dates on File | Jul 2024 to Dec 2025 |
| Initial Operation Date | July 2024 |
| Annual Generation | 417.8 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | pending |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | Wells |
| Ash Impoundment | |
| Transmission / Distribution Owner | CenterPoint Energy (8901) TX |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator SAREN Details Operating July 2024
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 202.8 MW |
| Nameplate Power Factor | 0.93 |
| Summer Capacity | 200 MW |
| Winter Capacity | 200 MW |
|---|---|
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 2024 |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| Tilt Angle | 52 |
| DC Net Capacity | 271 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Cutlass Solar II Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #142 | Hickory Park Solar Hybrid | Camilla, GA | 431.4 GWh |
| #143 | AP Sunray LLC | Knippa, TX | 429.9 GWh |
| #144 | Muscle Shoals | Cherokee, AL | 426.6 GWh |
| #145 | Big Cypress Solar, LLC | Crawfordsville, AR | 426.3 GWh |
| #146 | Chaparral Springs | Rosamond, CA | 413.9 GWh |
| #147 | Brazoria County Solar Project (Danciger) | Damon, TX | 422.9 GWh |
| #148 | Brazoria West | Damon, TX | 422.6 GWh |
| #149 | Pearl River Solar Park LLC | Morton, MS | 418.9 GWh |
| #150 | Golden Triangle | Lowndes, MS | 411.8 GWh |
| #151 | Sherco Solar I | Clear Lake, MN | 418.6 GWh |
| #153 | Huck Finn Renewable Energy Center | Vandalia, MO | 417.1 GWh |
| #154 | TS Power Plant | Battle Mountain, NV | 1.7 TWh |
| #155 | Sun Streams, LLC | Arlington, AZ | 411.7 GWh |
| #156 | Sandrini Solar 200 | Mettler, CA | 411.3 GWh |
| #157 | Oak Ridge Solar | Oak Ridge, LA | 409.6 GWh |
| #158 | Misae Solar | Childress, TX | 408.9 GWh |
| #159 | Greasewood Solar | Fort Stockton, TX | 408.3 GWh |
| #160 | Ash Creek Solar | Abbott, TX | 405.6 GWh |
| #161 | Crane Solar Project | Crane, TX | 405.5 GWh |
| #162 | Scarlet II Hybrid | Cantua Creek, CA | 385.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cutlass Solar II.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Braes Bayou Plant | Richmond, TX | 190.1 GWh | 11.5 mi |
| Brazoria County Solar Project (Danciger) | Damon, TX | 422.9 GWh | 14.7 mi |
| Brazoria West | Damon, TX | 422.6 GWh | 15.5 mi |
| Bronson | Beasley, TX | 9.6 GWh | 15.3 mi |
| Colorado Bend II | Wharton, TX | 6.1 TWh | 18.5 mi |
| Cutlass Solar 1 LLC | Richmond, TX | 169.0 GWh | 3.1 mi |
| Fighting Jays Solar Project | Needville, TX | 454.2 GWh | 3 mi |
| Fort Bend Solar LLC | East Bernard, TX | 527.2 GWh | 16.8 mi |
| FTBLID2 | Sugarland, TX | 130.0 MWh | 15.4 mi |
| HEB00110 | Missouri City, TX | 179.0 MWh | 17.8 mi |
| Jack Fusco Energy Center | Thompsons, TX | 3.6 TWh | 11 mi |
| Long Point Solar | Damon, TX | 429.0 MWh | 11.9 mi |
| Newgulf Cogen | NewGulf, TX | 12.7 GWh | 11.3 mi |
| Old 300 Solar Center, LLC | Needville, TX | 901.6 GWh | 4.8 mi |
| Petra Nova Carbon Capture Cogen | Thompsons, TX | 200.8 GWh | 10.6 mi |
| Second Division Solar | West Columbia, TX | 190.8 GWh | 15.3 mi |
| W A Parish | Thompsons, TX | 15.6 TWh | 11 mi |
| Wagyu | Damon, TX | 235.4 GWh | 12.6 mi |
| WAL2993 | Sugar Land, TX | 255.0 MWh | 17.5 mi |
| WAL546 | Richmond, TX | 178.0 MWh | 11.7 mi |