Wagyu
2114 County Rd 456, Damon, TX 77430Plant Summary Information
Wagyu is ranked #102 out of 215 solar farms in Texas in terms of total annual net electricity generation.
Wagyu generated 49.9 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Wagyu |
|---|---|
| Utility Name | Cubico USA, LLC |
| Location | Brazoria County, TX |
| Initial Operation Date | August 2020 |
| Last Update | Dec 2025 |
| Annual Generation | 235.4 GWh |
| Annual Consumption | 841.3 k MMBtu |
| Ranked #2,290 out of 12,613 Power Plants Nationwide | |
| Ranked #354 out of 6,463 Solar Power Plants Nationwide | |
| Ranked #419 out of 816 Texas Power Plants | |
| Ranked #102 out of 215 Texas Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operator |
Cypress Creek Renewables (2019 to 2020) Cubico USA, LLC (2021 to 2024) |
Map of Wagyu
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Wagyu.
Monthly Net Generation for Wagyu
Monthly Plant Fuel Consumption for Wagyu
Wagyu Details
| Summary Information | |
|---|---|
| Plant Name | Wagyu (63273) |
| Plant Address | 2114 County Rd 456, Damon, TX 77430 |
| Utility | Cubico USA, LLC (62161) |
| Latitude, Longitude | 29.2423, -95.65814 |
| Generation Dates on File | Jul 2020 to Dec 2025 |
| Initial Operation Date | August 2020 |
| Annual Generation | 235.4 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | EG20-158, EG20-159, EG20-160, EG20-161 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | CenterPoint Energy (8901) TX |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
Generator 1215 Details Operating August 2020
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 120 MW |
| Summer Capacity | 120 MW |
| Winter Capacity | 120 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | August 2020 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| East West Fixed Tilt | No |
| Other Solar Technology | Yes |
| DC Net Capacity | 162.4 MW |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Wagyu Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #344 | Liberty County Solar Project | Dayton, TX | 245.4 GWh |
| #345 | OCI Alamo 7 LLC | Haskell, TX | 245.3 GWh |
| #346 | Great Cove Solar II | Saint Thomas, PA | 244.8 GWh |
| #347 | West of the Pecos Solar | TBD, TX | 244.8 GWh |
| #348 | Lockhart Solar PV, LLC | Hinkley, CA | 243.4 GWh |
| #349 | Chesapeake Solar Project | Chesapeake, VA | 242.8 GWh |
| #350 | Ragsdale Solar LLC | Canton, MS | 238.9 GWh |
| #351 | Morris Solar | Kirksville, MO | 238.3 GWh |
| #352 | Kiowa County Solar Project, LLC | Snyder, OK | 235.9 GWh |
| #353 | Sandrini Solar 100 | Mettler, CA | 235.6 GWh |
| #355 | Oak Trail Solar, LLC | Moyock, NC | 234.7 GWh |
| #356 | SR Lumpkin | Lumpkin, GA | 234.5 GWh |
| #357 | RE Mustang LLC | Lemoore, CA | 220.6 GWh |
| #358 | Ivanpah 2 | Nipton, CA | 244.3 GWh |
| #359 | San Pablo Raceway | Lancaster, CA | 233.4 GWh |
| #360 | Dressor Plains Solar, LLC | Herrick, IL | 232.1 GWh |
| #361 | Prairie Mist Solar | Montrose, AR | 232.0 GWh |
| #362 | Desert Harvest, LLC | Desert Center, CA | 231.0 GWh |
| #363 | Bayou Galion Solar Project | Mer Rouge, LA | 230.3 GWh |
| #364 | Ivanpah 3 | Nipton, CA | 237.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Wagyu.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Braes Bayou Plant | Richmond, TX | 190.1 GWh | 16.6 mi |
| Brazoria County Solar Project (Danciger) | Damon, TX | 422.9 GWh | 7.6 mi |
| Brazoria West | Damon, TX | 422.6 GWh | 3.6 mi |
| Brotman Power Station | Rosharon, TX | 298.7 GWh | 15.9 mi |
| Cascade Solar (TX) | Wharton, TX | 17.3 GWh | 22.2 mi |
| Cutlass Solar 1 LLC | Richmond, TX | 169.0 GWh | 12.4 mi |
| Cutlass Solar II | Richmond, TX | 417.8 GWh | 12.6 mi |
| Fighting Jays Solar Project | Needville, TX | 454.2 GWh | 9.6 mi |
| HEB00110 | Missouri City, TX | 179.0 MWh | 21.6 mi |
| Jack Fusco Energy Center | Thompsons, TX | 3.6 TWh | 16.1 mi |
| Long Point Solar | Damon, TX | 429.0 MWh | 1.1 mi |
| Longbow Solar, LLC | Liverpool, TX | 141.0 GWh | 21.9 mi |
| Mark One Power Station | Angleton, TX | 352.7 GWh | 13.7 mi |
| Mckeever | Fresno, TX | 187.0 MWh | 21.3 mi |
| Newgulf Cogen | NewGulf, TX | 12.7 GWh | 14.6 mi |
| Old 300 Solar Center, LLC | Needville, TX | 901.6 GWh | 11.9 mi |
| Petra Nova Carbon Capture Cogen | Thompsons, TX | 200.8 GWh | 16.2 mi |
| Second Division Solar | West Columbia, TX | 190.8 GWh | 7.1 mi |
| Sweeny Cogen Facility | Old Ocean, TX | 3.3 TWh | 12.8 mi |
| W A Parish | Thompsons, TX | 15.6 TWh | 16.7 mi |