Swift Air Solar II
8995 FM 1601, Odessa, TX 79763Plant Summary Information
Swift Air Solar II is ranked #133 out of 251 solar farms in Texas in terms of total annual net electricity generation.
Swift Air Solar II generated 96.0 GWh during the 3-month period between March 2026 to June 2026.
| Plant Name | Swift Air Solar II |
|---|---|
| Utility Name | Origis Energy USA, Inc |
| Location | Ector County, TX |
| Initial Operation Date | November 2025 |
| Last Update | Jun 2026 |
| Annual Generation | 215.3 GWh |
| Annual Consumption | 734.6 k MMBtu |
| Ranked #2,448 out of 13,094 Power Plants Nationwide | |
| Ranked #444 out of 7,027 Solar Power Plants Nationwide | |
| Ranked #463 out of 858 Texas Power Plants | |
| Ranked #133 out of 251 Texas Solar Power Plants | |
| Fuel Types | Solar |
Map of Swift Air Solar II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Swift Air Solar II.
Monthly Net Generation for Swift Air Solar II
Monthly Plant Fuel Consumption for Swift Air Solar II
Swift Air Solar II Details
| Summary Information | |
|---|---|
| Plant Name | Swift Air Solar II (68587) |
| Plant Address | 8995 FM 1601, Odessa, TX 79763 |
| Utility | Origis Energy USA, Inc (58764) |
| Latitude, Longitude | 31.72309, -102.51965 |
| Generation Dates on File | Nov 2025 to Jun 2026 |
| Initial Operation Date | November 2025 |
| Annual Generation | 215.3 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | NA |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator OSAS2 Details Operating November 2025
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 173.6 MW |
| Summer Capacity | 150 MW |
| Winter Capacity | 150 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | November 2025 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 188.3 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Swift Air Solar II Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #434 | Axial Basin Solar | Meeker, CO | 220.2 GWh |
| #435 | Assembly Solar II LLC | Lennon, MI | 220.0 GWh |
| #436 | Willow Spring Solar, LLC | Rosamond, CA | 219.8 GWh |
| #437 | BPL Files Solar | Itasca, TX | 219.8 GWh |
| #438 | Fern Solar LLC | Battleboro, NC | 219.7 GWh |
| #439 | West of the Pecos Solar | TBD, TX | 218.9 GWh |
| #440 | Enterprise Solar, LLC | Newcastle, UT | 218.7 GWh |
| #441 | Escalante Solar I, LLC | Milford, UT | 217.6 GWh |
| #442 | Wagyu | Damon, TX | 217.4 GWh |
| #443 | Escalante Solar II, LLC | Milford, UT | 217.2 GWh |
| #445 | Cadence Solar Energy Center | Marysville, OH | 215.2 GWh |
| #446 | Pleasantville Solar Park | Ipava, IL | 214.9 GWh |
| #447 | Granite Mountain Solar East, LLC | Cedar City, UT | 214.7 GWh |
| #448 | Escalante Solar III, LLC | Milford, UT | 213.7 GWh |
| #449 | Riverstart Solar Park III | Modoc, IN | 213.1 GWh |
| #450 | SR Lumpkin | Lumpkin, GA | 213.1 GWh |
| #451 | Lockhart Solar PV II | Hinkley, CA | 207.2 GWh |
| #452 | Elektron Solar, LLC | Grantsville, UT | 212.7 GWh |
| #453 | Happy Solar 1 | Searcy, AR | 212.6 GWh |
| #454 | Badger Hollow II | Cobb, WI | 212.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Swift Air Solar II.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| 2W Permian Solar Project Hybrid | Andrews, TX | 1.0 TWh | 27.2 mi |
| Castle Gap Solar Hybrid | McCarney, TX | 350.0 GWh | 35.5 mi |
| Crane Solar Project | Crane, TX | 385.4 GWh | 34.6 mi |
| Ector County Energy Center | Goldsmith, TX | 934.6 GWh | 24.2 mi |
| Goldsmith | Goldsmith, TX | 101.0 MWh | 18.7 mi |
| N. Mary Francis | Odessa, TX | 116.0 MWh | 14.7 mi |
| Notrees Windpower Hybrid | Goldsmith, TX | 217.0 GWh | 26.1 mi |
| Oberon IA | Odessa, TX | 254.1 GWh | 10.8 mi |
| Oberon IB | Odessa, TX | 46.1 GWh | 10.7 mi |
| Odessa-Ector Power Plant | Odessa, TX | 8.4 TWh | 13.9 mi |
| Oxy Renewable Energy - Goldsmith | Goldsmith, TX | 38.8 GWh | 20.4 mi |
| Permian Basin | Monahans, TX | 669.5 GWh | 27.8 mi |
| Phoebe Solar | Kermit, TX | 507.5 GWh | 22.1 mi |
| Quail Run Energy Center | Odessa, TX | 3.1 TWh | 14.5 mi |
| Rockhound A | Odessa, TX | 57.9 GWh | 0 mi |
| Rockhound C | Odessa, TX | 12.3 GWh | 0 mi |
| Rockhound D | Odessa, TX | 4.7 GWh | 2.6 mi |
| Swift Air Solar I | Goldsmith, TX | 384.3 GWh | 10.8 mi |
| Swift Air Solar III | Odessa, TX | 146.9 GWh | 0 mi |
| Westover | Odessa, TX | 100.0 MWh | 8.9 mi |