Oberon IB
31600 W I-20, Odessa, TX 79760Plant Summary Information
Oberon IB is ranked #142 out of 215 solar farms in Texas in terms of total annual net electricity generation.
Oberon IB generated 11.9 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Oberon IB |
|---|---|
| Utility Name | Oberon Solar IB |
| Location | Ector County, TX |
| Initial Operation Date | July 2020 |
| Last Update | Dec 2025 |
| Annual Generation | 61.9 GWh |
| Annual Consumption | 223.0 k MMBtu |
| Ranked #3,891 out of 12,613 Power Plants Nationwide | |
| Ranked #948 out of 6,463 Solar Power Plants Nationwide | |
| Ranked #521 out of 816 Texas Power Plants | |
| Ranked #142 out of 215 Texas Solar Power Plants | |
| Fuel Types | Solar |
Map of Oberon IB
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Oberon IB.
Monthly Net Generation for Oberon IB
Monthly Plant Fuel Consumption for Oberon IB
Oberon IB Details
| Summary Information | |
|---|---|
| Plant Name | Oberon IB (62932) |
| Plant Address | 31600 W I-20, Odessa, TX 79760 |
| Utility | Oberon Solar IB (62789) |
| Latitude, Longitude | 31.69236, -102.69743 |
| Generation Dates on File | Jul 2020 to Dec 2025 |
| Initial Operation Date | July 2020 |
| Annual Generation | 61.9 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
Generator OBR1B Details Operating July 2020
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 30 MW |
| Summer Capacity | 30 MW |
| Winter Capacity | 30 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | July 2020 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Fixed Tilt | Yes |
| Azimuth Angle | 165 |
| Tilt Angle | 52 |
| DC Net Capacity | 37.3 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Oberon IB Plant Owners
| Owner Name | Address | Ownership |
|---|---|---|
| 174 Power Global Corp. | 400 Spectrum Center Dr. Ste 1400, Irvine, CA 92618 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #938 | Hayhurst New Mexico Solar | Malaga, NM | 63.5 GWh |
| #939 | Waiawa Solar Power Hybrid | Waipahu, HI | 58.0 GWh |
| #940 | AES Waikoloa Solar Hybrid | Waikoloa Village, HI | 61.0 GWh |
| #941 | Pawpaw Solar Plant | Butler, GA | 63.2 GWh |
| #942 | Cuyama Solar, LLC | Cuyama, CA | 63.2 GWh |
| #943 | Little Bear Solar 1, LLC | Mendota, CA | 63.0 GWh |
| #944 | Avra Valley Solar | Marana, AZ | 62.5 GWh |
| #945 | TAI Huntsville Solar Hybrid | Huntsville, AL | 62.4 GWh |
| #946 | Solar Borrego I | Borrego Springs, CA | 62.2 GWh |
| #947 | Hazlehurst II | Hazlehurst, GA | 62.1 GWh |
| #949 | Innovative Solar 67 | Willard, NC | 61.9 GWh |
| #950 | Gulf Coast Solar Center I | Valparaiso, FL | 61.2 GWh |
| #951 | Norton Solar Farm | Bronte, TX | 59.8 GWh |
| #952 | EE Waianae Solar Project | Waianae, HI | 59.4 GWh |
| #953 | Bison Solar LLC | Wellington, CO | 59.1 GWh |
| #954 | Rocking R Solar, LLC | Hosston, LA | 59.1 GWh |
| #955 | Crescent Dunes Solar Energy | Tonopah, NV | 59.0 GWh |
| #956 | Polaris Solar Park | Ashley, MI | 59.0 GWh |
| #957 | RE Garland A | Rosamond, CA | 58.2 GWh |
| #958 | Prairie Creek Solar | Jacksonville, IL | 58.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Oberon IB.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| 2W Permian Solar Project Hybrid | Andrews, TX | 1.0 TWh | 30.9 mi |
| Castle Gap Solar Hybrid | McCarney, TX | 384.2 GWh | 39.3 mi |
| Crane Solar Project | Crane, TX | 405.5 GWh | 37.9 mi |
| Ector County Energy Center | Goldsmith, TX | 648.7 GWh | 26.8 mi |
| Goldsmith | Goldsmith, TX | 184.0 MWh | 19.9 mi |
| Greasewood II LLC | Girvin, TX | 796.9 GWh | 41 mi |
| N. Mary Francis | Odessa, TX | 216.0 MWh | 22.3 mi |
| Notrees Windpower Hybrid | Goldsmith, TX | 237.1 GWh | 22.3 mi |
| Oberon IA | Odessa, TX | 302.7 GWh | 0.8 mi |
| Odessa-Ector Power Plant | Odessa, TX | 8.1 TWh | 24.1 mi |
| Oxy Renewable Energy - Goldsmith | Goldsmith, TX | 40.5 GWh | 21.7 mi |
| Permian Basin | Monahans, TX | 464.5 GWh | 17.3 mi |
| Phoebe Solar | Kermit, TX | 557.3 GWh | 14.5 mi |
| Quail Run Energy Center | Odessa, TX | 3.1 TWh | 24.7 mi |
| SPS1 Dollarhide | Jal, NM | 23.0 GWh | 39.6 mi |
| Swift Air Solar I | Goldsmith, TX | 311.5 GWh | 5.3 mi |
| Swift Air Solar II | Odessa, TX | 33.9 GWh | 10.7 mi |
| Swift Air Solar III | Odessa, TX | 21.3 GWh | 10.7 mi |
| Upton County Solar | McCamey, TX | 299.1 GWh | 39.3 mi |
| Westover | Odessa, TX | 185.0 MWh | 17.8 mi |