Odessa-Ector Power Plant
2200 I-20 East, Odessa, TX 79766Plant Summary Information
Odessa-Ector Power Plant is ranked #42 out of 2,284 natural gas power plants nationwide in terms of total annual net electricity generation.
Odessa-Ector Power Plant is comprised of 6 generators and generated 2.4 TWh during the 3-month period between November 2023 to February 2024.
Plant Name | Odessa-Ector Power Plant |
---|---|
Utility Name | LaFrontera Holdings LLC |
Location | Ector County, TX |
Initial Operation Date | July 2001 |
Last Update | Feb 2024 |
Annual Generation | 7.6 TWh |
Annual Consumption | 52.9 M MMBtu |
Ranked #121 out of 11,455 Power Plants Nationwide | |
Ranked #42 out of 2,284 Natural Gas Power Plants Nationwide | |
Ranked #12 out of 726 Texas Power Plants | |
Ranked #6 out of 291 Texas Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Previous Operator |
Odessa-Ector Power Partners LP (2013 to 2016) LaFrontera Holdings LLC (2017 to 2022) |
Map of Odessa-Ector Power Plant
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Odessa-Ector Power Plant.
Monthly Net Generation for Odessa-Ector Power Plant
Odessa-Ector Power Plant Details
Summary Information | |
---|---|
Plant Name | Odessa-Ector Power Plant (55215) |
Plant Address | 2200 I-20 East Odessa, TX 79766 |
Utility | LaFrontera Holdings LLC (60477) |
Latitude, Longitude | 31.8403, -102.3264 |
Generation Dates on File | Jul 2001 to Feb 2024 |
Initial Operation Date | July 2001 |
Annual Generation | 7.6 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 99-242-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | Wells |
Ash Impoundment | No |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name |
EL PASO NATURAL GAS COMPANY LLC ONEOK WES TEX TRANSMISSION LLC |
Natural Gas Storage | No |
Generator CTG1 Details Operating July 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | BLK1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | OECCS_1 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | OECCS_1 |
Nameplate Capacity | 176 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 166.7 MW |
Winter Capacity | 195.2 MW |
Minimum Load | 84.8 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2001 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CTG2 Details Operating July 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | BLK1 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | OECCS_1 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | OECCS_1 |
Nameplate Capacity | 176 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 158.2 MW |
Winter Capacity | 189.1 MW |
Minimum Load | 82.7 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2001 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator STG1 Details Operating July 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | BLK1 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | OECCS_1 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | OECCS_1 |
Nameplate Capacity | 224.4 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 206 MW |
Winter Capacity | 217 MW |
Minimum Load | 53.3 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | July 2001 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CTG3 Details Operating August 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | BLK2 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | OECCS_2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | OECCS_2 |
Nameplate Capacity | 176 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 166.7 MW |
Winter Capacity | 195.2 MW |
Minimum Load | 92.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | August 2001 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator CTG4 Details Operating August 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | BLK2 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | No |
RTO ISO LMP Node Designation | OECCS_2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | OECCS_2 |
Nameplate Capacity | 176 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 158.2 MW |
Winter Capacity | 189.1 MW |
Minimum Load | 95.2 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | August 2001 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator STG2 Details Operating August 2001
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | BLK2 |
Ownership | Single Owner |
Duct Burners | Yes |
RTO ISO LMP Node Designation | OECCS_2 |
RTO ISO Location Designation For Reporting Wholesale Sales Data | OECCS_2 |
Nameplate Capacity | 224.4 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 206 MW |
Winter Capacity | 217 MW |
Minimum Load | 55.6 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | August 2001 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 12H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Odessa-Ector Power Plant Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#32 | Sanford | DeBary, FL | 8.2 TWh |
#33 | Moxie Freedom Generation Plant | Salem Township, PA | 8.2 TWh |
#34 | Martin | Indiantown, FL | 8.2 TWh |
#35 | Freestone Energy Center | Fairfield, TX | 8.1 TWh |
#36 | Indeck Niles Energy Center | Niles, MI | 7.9 TWh |
#37 | CPV Fairview Energy Center | Johnstown, PA | 7.9 TWh |
#38 | Jackson Generation, LLC | Elwood, IL | 7.8 TWh |
#39 | Riviera | Riviera Beach, FL | 7.8 TWh |
#40 | Panda Temple Power Station | Temple, TX | 7.8 TWh |
#41 | Wolf Hollow II | Granbury, TX | 7.6 TWh |
#43 | Guadalupe Generating Station | Marion, TX | 7.6 TWh |
#44 | Cape Canaveral | Cocoa, FL | 7.6 TWh |
#45 | Chouteau | Pryor, OK | 7.6 TWh |
#46 | Deer Park Energy Center | Deer Park, TX | 7.6 TWh |
#47 | Chuck Lenzie Generating Station | Apex, NV | 7.5 TWh |
#48 | Paradise | Drakesboro, KY | 7.4 TWh |
#49 | Brunswick County Power Station | Freeman, VA | 7.3 TWh |
#50 | Tenaska Westmoreland Generating Station | Smithton, PA | 7.2 TWh |
#51 | Manatee | Parrish, FL | 7.2 TWh |
#52 | Seminole (FL) | Palatka, FL | 10.8 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Odessa-Ector Power Plant.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
2W Permian Solar Project Hybrid | Andrews, TX | 972.4 GWh | 22.4 mi |
Bakke | Andrews, TX | 491.0 MWh | 33.9 mi |
Castle Gap Solar Hybrid | McCarney, TX | 423.2 GWh | 40.6 mi |
CED Crane Solar | Crane, TX | 433.6 GWh | 40.5 mi |
Ector County Energy Center | Goldsmith, TX | 120.8 GWh | 21.9 mi |
Goldsmith | Goldsmith, TX | 424.3 MWh | 20.4 mi |
N. Mary Francis | Odessa, TX | 495.0 MWh | 8.3 mi |
Notrees Windpower Hybrid | Goldsmith, TX | 273.1 GWh | 31.3 mi |
Oberon IA | Odessa, TX | 345.4 GWh | 24 mi |
Oberon IB | Odessa, TX | 68.8 GWh | 24.1 mi |
Oxy Renewable Energy - Goldsmith | Goldsmith, TX | 45.5 GWh | 21.2 mi |
Permian Basin | Monahans, TX | 131.1 GWh | 41.4 mi |
Phoebe Solar | Kermit, TX | 559.5 GWh | 31.8 mi |
Pioneer Hutt Wind Energy | Midland, TX | 62.0 GWh | 25 mi |
Prospero Solar II | Andrews, TX | 721.2 GWh | 42.7 mi |
Quail Run Energy Center | Odessa, TX | 1.4 TWh | 0.7 mi |
Stanton Wind Energy LLC | Lenorah, TX | 281.1 GWh | 39.6 mi |
Tumbleweed | Andrews, TX | 511.0 MWh | 37.8 mi |
Upton County Solar | McCamey, TX | 302.1 GWh | 41.4 mi |
Westover | Odessa, TX | 367.0 MWh | 7 mi |