Springbok 3 Solar Farm Hybrid
31997 Cholla Rd, Cantil, CA 93519Plant Summary Information
Springbok 3 Solar Farm Hybrid is ranked #86 out of 854 solar farms in California in terms of total annual net electricity generation.
Springbok 3 Solar Farm Hybrid generated 32.5 GWh during the 3-month period between November 2025 to February 2026.
| Plant Name | Springbok 3 Solar Farm Hybrid |
|---|---|
| Utility Name | 64KT 8me LLC |
| Location | Kern County, CA |
| Initial Operation Date | July 2019 |
| Last Update | Feb 2026 |
| Annual Generation | 243.2 GWh |
| Annual Consumption | 883.2 k MMBtu |
| Ranked #2,275 out of 12,637 Power Plants Nationwide | |
| Ranked #353 out of 6,487 Solar Power Plants Nationwide | |
| Ranked #226 out of 1,603 California Power Plants | |
| Ranked #86 out of 854 California Solar Power Plants | |
| Fuel Types | Solar |
Map of Springbok 3 Solar Farm Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Springbok 3 Solar Farm Hybrid.
Monthly Net Generation for Springbok 3 Solar Farm Hybrid
Monthly Plant Fuel Consumption for Springbok 3 Solar Farm Hybrid
Springbok 3 Solar Farm Hybrid Details
| Summary Information | |
|---|---|
| Plant Name | Springbok 3 Solar Farm Hybrid (60491) |
| Plant Address | 31997 Cholla Rd, Cantil, CA 93519 |
| Utility | 64KT 8me LLC (60278) |
| Latitude, Longitude | 35.17115, -118.00165 |
| Generation Dates on File | Jul 2019 to Feb 2026 |
| Initial Operation Date | July 2019 |
| Annual Generation | 243.2 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Los Angeles Department of Water and Power (LDWP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Los Angeles Department of Water & Power (11208) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | Yes |
Generator SB3BS Details Operating July 2019
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 1.5 MW |
| Summer Capacity | 1.5 MW |
| Winter Capacity | 1.5 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | July 2019 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 1.5 |
|---|---|
| Maximum Charge Rate | 1.5 MW |
| Maximum Discharge Rate | 1.5 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 1.5 |
| Storage Enclosure Type | CT |
| Frequency Regulation | Yes |
| Voltage Or Reactive Power Support | Yes |
| Excess Wind And Solar Generation | P |
| DC Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 60491 |
| Direct Support Gen Id | SB3SF |
| Support T D Asset | No |
Generator SB3SF Details Operating July 2019
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 90 MW |
| Summer Capacity | 90 MW |
| Winter Capacity | 90 MW |
| Minimum Load | 1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 2019 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 119.6 MW |
| Crystalline Silicon | Yes |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Springbok 3 Solar Farm Hybrid Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #343 | East Line Solar | Coolidge, AZ | 251.3 GWh |
| #344 | Hickory Solar | Jerseyville, IL | 250.5 GWh |
| #345 | Great Cove Solar II | Saint Thomas, PA | 250.4 GWh |
| #346 | Elm Branch Solar 1 | Bardwell, TX | 250.1 GWh |
| #347 | SR Snipesville III | Denton, GA | 249.8 GWh |
| #348 | Rabbitbrush Solar, LLC | Rosamond, CA | 245.5 GWh |
| #349 | Taylor County Solar | Butler, GA | 245.4 GWh |
| #350 | OCI Alamo 7 LLC | Haskell, TX | 245.3 GWh |
| #351 | Galloway 2 Solar Farm | Paint Rock, TX | 244.4 GWh |
| #352 | Willow Spring Solar, LLC | Rosamond, CA | 244.1 GWh |
| #354 | Lockhart Solar PV, LLC | Hinkley, CA | 241.0 GWh |
| #355 | Fish Springs | Reno, NV | 239.9 GWh |
| #356 | Wagyu | Damon, TX | 241.4 GWh |
| #357 | Chesapeake Solar Project | Chesapeake, VA | 240.3 GWh |
| #358 | SR Snipesville II | Denton, GA | 240.2 GWh |
| #359 | Ragsdale Solar LLC | Canton, MS | 238.1 GWh |
| #360 | West of the Pecos Solar | TBD, TX | 237.8 GWh |
| #361 | San Pablo Raceway | Lancaster, CA | 237.0 GWh |
| #362 | Calhoun County Solar Project | Sheridan Township, MI | 235.5 GWh |
| #363 | RE Mustang LLC | Lemoore, CA | 220.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Springbok 3 Solar Farm Hybrid.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Beacon Solar Plant Site 2 | Cantil, CA | 111.7 GWh | 6.5 mi |
| Beacon Solar Plant Site 5 | Cantil, CA | 88.5 GWh | 5.7 mi |
| Bellefield Solar and Energy Storage Farm | Mojave, CA | 143.9 GWh | 8.9 mi |
| CalCity Solar 1 | California City, CA | 7.9 GWh | 2.9 mi |
| California City | California City, CA | 4.6 GWh | 1.5 mi |
| Difwind Farms Ltd VI | Mojave, CA | 14.9 GWh | 12.7 mi |
| Edwards Sanborn S1 | Mojave, CA | 100.4 GWh | 12.4 mi |
| Edwards Sanborn S3 | Mojave, CA | 83.1 GWh | 12.7 mi |
| Edwards Sanborn S4 | Mojave, CA | 89.8 GWh | 12.8 mi |
| Eland Solar & Storage Center, Phase 1 Hy | Mojave, CA | 665.8 GWh | 3.9 mi |
| Eland Solar & Storage Center, Phase 2 Hy | Mojave, CA | 329.0 GWh | 3.4 mi |
| Hecate Energy Beacon Solar 1 | Cantil, CA | 127.6 GWh | 6.8 mi |
| Hecate Energy Beacon Solar 3 | Cantil, CA | 120.7 GWh | 5.7 mi |
| Hecate Energy Beacon Solar 4 | Cantil, CA | 115.3 GWh | 5.9 mi |
| Pine Tree Solar Project | Owenyo, CA | 7.2 GWh | 11.7 mi |
| Pine Tree Wind Power Project | Cantil, CA | 115.4 GWh | 11.2 mi |
| RE Barren Ridge 1 | Mojave, CA | 175.0 GWh | 4.4 mi |
| Rising Tree Wind Farm II | Mojave, CA | 58.7 GWh | 12.9 mi |
| Springbok Solar Farm 1 | Cantil, CA | 297.7 GWh | 6 mi |
| Springbok Solar Farm 2 | Cantil, CA | 399.0 GWh | 5.6 mi |