Eland Solar & Storage Center, Phase 1 Hy
TBD, Mojave, CA 93280Plant Summary Information
Eland Solar & Storage Center, Phase 1 Hy is ranked #42 out of 6,397 solar farms nationwide in terms of total annual net electricity generation.
Eland Solar & Storage Center, Phase 1 Hy generated 123.0 GWh during the 3-month period between December 2025 to March 2026.
| Plant Name | Eland Solar & Storage Center, Phase 1 Hy |
|---|---|
| Utility Name | 68SF 8me LLC |
| Location | Kern County, CA |
| Initial Operation Date | November 2024 |
| Last Update | Mar 2026 |
| Annual Generation | 669.7 GWh |
| Annual Consumption | 2.5 M MMBtu |
| Ranked #1,048 out of 12,332 Power Plants Nationwide | |
| Ranked #42 out of 6,397 Solar Power Plants Nationwide | |
| Ranked #52 out of 1,530 California Power Plants | |
| Ranked #10 out of 834 California Solar Power Plants | |
| Fuel Types | Solar |
Map of Eland Solar & Storage Center, Phase 1 Hy
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Eland Solar & Storage Center, Phase 1 Hy.
Monthly Net Generation for Eland Solar & Storage Center, Phase 1 Hy
Monthly Plant Fuel Consumption for Eland Solar & Storage Center, Phase 1 Hy
Eland Solar & Storage Center, Phase 1 Hy Details
| Summary Information | |
|---|---|
| Plant Name | Eland Solar & Storage Center, Phase 1 Hy (61168) |
| Plant Address | TBD, Mojave, CA 93280 |
| Utility | 68SF 8me LLC (60797) |
| Latitude, Longitude | 35.2237, -117.977 |
| Generation Dates on File | Nov 2024 to Mar 2026 |
| Initial Operation Date | November 2024 |
| Annual Generation | 669.7 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Los Angeles Department of Water and Power (LDWP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Los Angeles Department of Water & Power (11208) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | Yes |
Generator 61168 Details Operating November 2024
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 150 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 150 MW |
| Winter Capacity | 150 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | November 2024 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Multiple Fuels | No |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 600 |
|---|---|
| Maximum Charge Rate | 150 MW |
| Maximum Discharge Rate | 150 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 100 |
| Storage Enclosure Type | CS |
| Frequency Regulation | Yes |
| Load Following | Yes |
| Voltage Or Reactive Power Support | Yes |
| Excess Wind And Solar Generation | P |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 60797 |
| Direct Support Gen Id | 61168 |
| Support T D Asset | Yes |
Generator 68SF8 Details Operating November 2024
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 309.6 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 200 MW |
| Winter Capacity | 200 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | November 2024 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| Tilt Angle | 60 |
| DC Net Capacity | 384 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Eland Solar & Storage Center, Phase 1 Hy Plant Owners
| Owner Name | Address | Generator | Ownership |
|---|---|---|---|
| Arevon Asset Management | 8800 N Gainey Center Dr, Suite 250, Scottsdale, AZ 85258 | Generator 61168 | 100.00% |
| Arevon Asset Management | 8800 N Gainey Center Dr, Suite 250, Scottsdale, AZ 85258 | Generator 68SF8 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #32 | Mammoth North Solar | Knox, IN | 746.6 GWh |
| #33 | Atrisco Solar LLC | Rio Rancho, NM | 732.6 GWh |
| #34 | Prospero Solar | Andrews, TX | 730.8 GWh |
| #35 | McFarland B Solar and Storage | Dateland, AZ | 710.1 GWh |
| #36 | Solar Star 2 | Rosamond, CA | 723.9 GWh |
| #37 | Peregrine Solar | Gollad, TX | 723.6 GWh |
| #38 | Athos Solar Project | Desert Center, CA | 712.8 GWh |
| #39 | Texas Solar Nova 1 | Spur, TX | 710.5 GWh |
| #40 | Arroyo Solar Energy Storage Hybrid | Pueblo Pintado, NM | 685.4 GWh |
| #41 | Lumina II Solar Project | Snyder, TX | 689.6 GWh |
| #43 | Box Canyon (AZ) | Florence, AZ | 691.4 GWh |
| #44 | Neptune Energy Center Hybrid | Boone, CO | 672.1 GWh |
| #45 | Copper Mountain Solar 5, LLC | Boulder City, NV | 689.4 GWh |
| #46 | Solar Blue | Lemoore, CA | 650.5 GWh |
| #47 | Lumina Solar Project | Snyder, TX | 665.1 GWh |
| #48 | Silver State Solar Power South | Primm Valley, NV | 672.1 GWh |
| #49 | Arlington Energy Center II | Blythe, CA | 643.9 GWh |
| #50 | Mount Signal Solar Farm V | Calexico, CA | 670.4 GWh |
| #51 | McCoy Solar Energy Project Hybrid | Blythe, CA | 646.7 GWh |
| #52 | Desert Sunlight 300, LLC | Desert Center, CA | 666.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Eland Solar & Storage Center, Phase 1 Hy.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Beacon Solar Plant Site 2 | Cantil, CA | 112.2 GWh | 3.2 mi |
| Beacon Solar Plant Site 5 | Cantil, CA | 89.9 GWh | 3.7 mi |
| Bellefield Solar and Energy Storage Farm | Mojave, CA | 270.9 GWh | 12.7 mi |
| CalCity Solar 1 | California City, CA | 7.9 GWh | 5.7 mi |
| California City | California City, CA | 4.6 GWh | 4.6 mi |
| Difwind Farms Ltd VI | Mojave, CA | 14.9 GWh | 16.2 mi |
| Edwards Sanborn S1 | Mojave, CA | 102.4 GWh | 16.2 mi |
| Eland Solar & Storage Center, Phase 2 Hy | Mojave, CA | 385.2 GWh | 0.5 mi |
| Hecate Energy Beacon Solar 1 | Cantil, CA | 128.9 GWh | 3.8 mi |
| Hecate Energy Beacon Solar 3 | Cantil, CA | 121.6 GWh | 2.9 mi |
| Hecate Energy Beacon Solar 4 | Cantil, CA | 116.8 GWh | 3.5 mi |
| North Sky River Energy LLC | Weldon, CA | 435.0 GWh | 14.6 mi |
| Pine Tree Solar Project | Owenyo, CA | 7.2 GWh | 12.4 mi |
| Pine Tree Wind Power Project | Cantil, CA | 115.4 GWh | 11.3 mi |
| RE Barren Ridge 1 | Mojave, CA | 175.0 GWh | 5.3 mi |
| Rising Tree Wind Farm II | Mojave, CA | 58.7 GWh | 16 mi |
| Sky River Wind Energy Center | Tehachapi, CA | 245.0 GWh | 15.4 mi |
| Springbok 3 Solar Farm Hybrid | Cantil, CA | 243.4 GWh | 3.9 mi |
| Springbok Solar Farm 1 | Cantil, CA | 297.7 GWh | 2.1 mi |
| Springbok Solar Farm 2 | Cantil, CA | 399.0 GWh | 1.8 mi |