Blythe Mesa Solar II
16489 Mesa Drive, Blythe, CA 92225Plant Summary Information
Blythe Mesa Solar II is ranked #48 out of 5,666 solar farms nationwide in terms of total annual net electricity generation.
Blythe Mesa Solar II generated 103.6 GWh during the 3-month period between December 2024 to March 2025.
Plant Name | Blythe Mesa Solar II |
---|---|
Utility Name | Blythe Mesa Solar II, LLC |
Location | Riverside County, CA |
Initial Operation Date | December 2022 |
Last Update | Mar 2025 |
Annual Generation | 571.8 GWh |
Annual Consumption | 2.1 M MMBtu |
Ranked #1,160 out of 11,623 Power Plants Nationwide | |
Ranked #48 out of 5,666 Solar Power Plants Nationwide | |
Ranked #67 out of 1,487 California Power Plants | |
Ranked #19 out of 761 California Solar Power Plants | |
Fuel Types | Solar |
Map of Blythe Mesa Solar II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Blythe Mesa Solar II.
Monthly Net Generation for Blythe Mesa Solar II
Blythe Mesa Solar II Details
Summary Information | |
---|---|
Plant Name | Blythe Mesa Solar II (65053) |
Plant Address | 16489 Mesa Drive, Blythe, CA 92225 |
Utility | Blythe Mesa Solar II, LLC (64459) |
Latitude, Longitude | 33.64081, -114.68026 |
Generation Dates on File | Dec 2022 to Mar 2025 |
Initial Operation Date | December 2022 |
Annual Generation | 571.8 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | Yes |
FERC Exempt Wholesale Generator Docket Number | 21-164-000 |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
Grid Voltage | 220.00 kV |
Energy Storage | Yes |
Generator BMSES Details Operating December 2022
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CENTPD_2_BMSX2-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | CENTPD_2_BMSX2 |
Nameplate Capacity | 112 MW |
Summer Capacity | 112 MW |
Winter Capacity | 112 MW |
Uprate/Derate Completed | No |
Status | Operating |
---|---|
First Operation Date | December 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 10M |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 448 |
---|---|
Maximum Charge Rate | 112 MW |
Maximum Discharge Rate | 112 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 36.8 |
Storage Enclosure Type | CS |
Arbitrage | Yes |
Co Located Renewable Firming | Yes |
Excess Wind And Solar Generation | P |
Ac Coupled | Yes |
Direct Support Of Another Unit | Yes |
Direct Support Plant Id | 65053 |
Direct Support Gen Id | IPBMS |
Support T D Asset | No |
Generator IPBMS Details Operating December 2022
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
RTO ISO LMP Node Designation | CENTPD_2_BMSSX2-APND |
RTO ISO Location Designation For Reporting Wholesale Sales Data | CENTPD_2_BMSSX2 |
Nameplate Capacity | 223.6 MW |
Summer Capacity | 223.6 MW |
Winter Capacity | 223.6 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2022 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 309.7 MW |
Thin Film CDTE | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Blythe Mesa Solar II Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#38 | Moapa Southern Paiute | Moapa, NV | 623.1 GWh |
#39 | Copper Mountain Solar 3 | Boulder City, NV | 621.3 GWh |
#40 | Stateline Solar | Nipton, CA | 618.5 GWh |
#41 | Oberon II Solar Project | Desert Center, CA | 593.0 GWh |
#42 | McCoy Solar Energy Project Hybrid | Blythe, CA | 524.7 GWh |
#43 | Titan Solar Project | Van Horn, TX | 601.7 GWh |
#44 | Mojave Solar Project | Hinkley, CA | 600.3 GWh |
#45 | Bighorn Solar 1 | Pueblo, CO | 594.3 GWh |
#46 | Blythe Solar 110, LLC | Blythe, CA | 584.2 GWh |
#47 | Agua Caliente Solar Project | Dateland, AZ | 591.7 GWh |
#49 | Victory Pass | Desert Center, CA | 575.1 GWh |
#50 | Eleven Mile Solar Center | Coolidge, AZ | 546.9 GWh |
#51 | Thunder Wolf Energy Center Hybrid | Avondale, CO | 556.8 GWh |
#52 | RE Maplewood | McCamey, TX | 570.5 GWh |
#53 | AV Solar Ranch One | Lancaster, CA | 569.0 GWh |
#54 | Texas Solar Nova 2 | Spur, TX | 565.9 GWh |
#55 | Oberon Solar Project | Desert Center, CA | 544.8 GWh |
#56 | Sparta Solar | Pawnee, TX | 562.7 GWh |
#57 | Eiffel Solar Project | Paris, TX | 562.4 GWh |
#58 | Dodge Flat | Reno, NV | 555.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Blythe Mesa Solar II.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arlington Energy Center II | Blythe, CA | 634.7 GWh | 6.5 mi |
Arlington Energy Center III | Blythe, CA | 293.2 GWh | 6.5 mi |
Blythe Energy Inc | Blythe, CA | 576.6 GWh | 1.8 mi |
Blythe Solar 110, LLC | Blythe, CA | 584.2 GWh | 4.5 mi |
Blythe Solar II, LLC | Blythe, CA | 337.6 GWh | 3.9 mi |
Blythe Solar III, LLC Hybrid | Blythe, CA | 353.1 GWh | 3.7 mi |
Blythe Solar IV, LLC | Blythe, CA | 318.4 GWh | 5.8 mi |
Chuckawalla Solar | Blythe, CA | 6.8 GWh | 14.6 mi |
Chuckawalla Valley State Prison | Blythe, CA | 1.2 GWh | 13.9 mi |
Desert Quartzite | Blythe, CA | 231.9 GWh | 6.7 mi |
Genesis Solar Energy Project | Blythe, CA | 642.6 GWh | 18.4 mi |
Ironwood Solar LLC | Blythe, CA | 8.2 GWh | 14.7 mi |
McCoy Solar Energy Project Hybrid | Blythe, CA | 524.7 GWh | 5.1 mi |
Palo Verde College | Blythe, CA | 2.0 GWh | 2.2 mi |
Solar Blythe 2 | Blythe, CA | 40.5 GWh | 1.8 mi |
Solar Blythe LLC | Blythe, CA | 40.5 GWh | 5 mi |
SunEdison Ironwood State Prison | Blythe, CA | 1.3 GWh | 14.6 mi |
Venable Solar 1 | Blythe, CA | 3.4 GWh | 6.9 mi |
Venable Solar 2 | Blythe, CA | 3.4 GWh | 6.9 mi |
Victory Pass | Desert Center, CA | 575.1 GWh | 36.8 mi |