Arlington Energy Center III
Dracker Drive, Blythe, CA 92225Plant Summary Information
Arlington Energy Center III is ranked #58 out of 854 solar farms in California in terms of total annual net electricity generation.
Arlington Energy Center III generated 56.8 GWh during the 3-month period between November 2025 to February 2026.
| Plant Name | Arlington Energy Center III |
|---|---|
| Utility Name | Arlington Energy Center III |
| Location | Riverside County, CA |
| Initial Operation Date | August 2022 |
| Last Update | Feb 2026 |
| Annual Generation | 323.9 GWh |
| Annual Consumption | 1.2 M MMBtu |
| Ranked #1,898 out of 12,637 Power Plants Nationwide | |
| Ranked #227 out of 6,487 Solar Power Plants Nationwide | |
| Ranked #161 out of 1,603 California Power Plants | |
| Ranked #58 out of 854 California Solar Power Plants | |
| Fuel Types | Solar |
Map of Arlington Energy Center III
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Arlington Energy Center III.
Monthly Net Generation for Arlington Energy Center III
Monthly Plant Fuel Consumption for Arlington Energy Center III
Arlington Energy Center III Details
| Summary Information | |
|---|---|
| Plant Name | Arlington Energy Center III (64564) |
| Plant Address | Dracker Drive, Blythe, CA 92225 |
| Utility | Arlington Energy Center III (64199) |
| Latitude, Longitude | 33.69088, -114.77494 |
| Generation Dates on File | Aug 2022 to Feb 2026 |
| Initial Operation Date | August 2022 |
| Annual Generation | 323.9 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
| Grid Voltage | 220.00 kV |
| Energy Storage | Yes |
Generator AEC3 Details Operating August 2022
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 131 MW |
| Summer Capacity | 131 MW |
| Winter Capacity | 131 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | August 2022 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| DC Net Capacity | 164 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator AEC3B Details Operating August 2022
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 110 MW |
| Summer Capacity | 110 MW |
| Winter Capacity | 110 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | August 2022 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 440 |
|---|---|
| Maximum Charge Rate | 110 MW |
| Maximum Discharge Rate | 110 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 36.2 |
| Storage Enclosure Type | CT |
| Frequency Regulation | P |
| Ramping Spinning Reserve | Yes |
| Excess Wind And Solar Generation | Yes |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | No |
| Direct Support Plant Id | 64564 |
| Direct Support Gen Id | AEC3 |
| Support T D Asset | No |
Arlington Energy Center III Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #217 | Copper Mountain Solar 2 | Boulder City, NV | 356.1 GWh |
| #218 | Camilla Solar Energy Project | Camilla, GA | 355.9 GWh |
| #219 | Darien Solar | Darien, WI | 355.5 GWh |
| #220 | Driver Solar | Osceola, AR | 355.3 GWh |
| #221 | Calhoun Solar | Battle Creek, MI | 354.9 GWh |
| #222 | Ganado Solar | Gail, TX | 347.1 GWh |
| #223 | Centinela Solar Energy | Calexico, CA | 352.7 GWh |
| #224 | Blythe Solar II, LLC | Blythe, CA | 336.8 GWh |
| #225 | Aragorn Solar Project | Van Horn, TX | 345.5 GWh |
| #226 | Edwards Sanborn E1A | Mojave, CA | 328.9 GWh |
| #228 | Buckthorn Westex | Ft. Stockton, TX | 341.4 GWh |
| #229 | West Memphis Solar Station | Crawfordsville, AR | 341.4 GWh |
| #230 | Arlington Valley Solar Energy II | Arlington, AZ | 341.2 GWh |
| #231 | Eland Solar & Storage Center, Phase 2 Hy | Mojave, CA | 329.0 GWh |
| #232 | Daybreak Solar | Maupin, OR | 337.2 GWh |
| #233 | Sun Streams 2 | Hassayampa, AZ | 336.2 GWh |
| #234 | Cass County Renewable Energy Center | Beardstown, IL | 335.0 GWh |
| #235 | Hardin Solar Energy II LLC | Belle Center, OH | 333.5 GWh |
| #236 | Vikings Energy Farm | Holtville, CA | 309.7 GWh |
| #237 | Twin Lakes Solar LLC | Monticello, IN | 328.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Arlington Energy Center III.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Arica Solar | Desert Center, CA | 779.1 GWh | 31.1 mi |
| Arlington Energy Center II | Blythe, CA | 636.7 GWh | 0 mi |
| Blythe Energy Inc | Blythe, CA | 315.2 GWh | 7.3 mi |
| Blythe Mesa Solar II | Blythe, CA | 585.9 GWh | 6.5 mi |
| Blythe Solar 110, LLC | Blythe, CA | 580.5 GWh | 2 mi |
| Blythe Solar II, LLC | Blythe, CA | 336.8 GWh | 2.7 mi |
| Blythe Solar III, LLC Hybrid | Blythe, CA | 357.8 GWh | 3.1 mi |
| Blythe Solar IV, LLC | Blythe, CA | 356.4 GWh | 0.7 mi |
| Chuckawalla Solar | Blythe, CA | 7.1 GWh | 11.8 mi |
| Chuckawalla Valley State Prison | Blythe, CA | 1.4 GWh | 11.4 mi |
| Desert Quartzite | Blythe, CA | 830.4 GWh | 8.8 mi |
| Genesis Solar Energy Project | Blythe, CA | 599.2 GWh | 13 mi |
| Ironwood Solar LLC | Blythe, CA | 7.5 GWh | 12 mi |
| McCoy Solar Energy Project Hybrid | Blythe, CA | 646.7 GWh | 2 mi |
| Palo Verde College | Blythe, CA | 2.0 GWh | 7.4 mi |
| Solar Blythe 2 | Blythe, CA | 38.1 GWh | 6.7 mi |
| Solar Blythe LLC | Blythe, CA | 41.8 GWh | 7.1 mi |
| SunEdison Ironwood State Prison | Blythe, CA | 996.0 MWh | 11.9 mi |
| Venable Solar 1 | Blythe, CA | 3.4 GWh | 13.3 mi |
| Venable Solar 2 | Blythe, CA | 3.4 GWh | 13.4 mi |