| GKS Solar | Cypress Creek Renewables | Belvidere, NC | 9 GWh | Jul 2015 | Dec 2024 |
Solar
|
| Hardison Farm Solar, LLC | Cypress Creek Renewables | Williamston, NC | 10 GWh | Aug 2016 | Dec 2024 |
Solar
|
| Modlin Solar Farm | Cypress Creek Renewables | Williamston, NC | 9 GWh | Jul 2016 | Dec 2024 |
Solar
|
| Sullivan Solar, LLC | Cypress Creek Renewables | Sullivan, IN | 8 GWh | Aug 2016 | Dec 2024 |
Solar
|
| White Farm Solar, LLC | Cypress Creek Renewables | Woodland, NC | 10 GWh | Jul 2016 | Dec 2024 |
Solar
|
| Dakota | Cypress Creek Renewables | Rock City, IL | 82 MWh | Nov 2024 | Dec 2024 |
Solar
|
| Galt | Cypress Creek Renewables | Sterling, IL | 2 GWh | Aug 2024 | Dec 2024 |
Solar
|
| Walldog | Cypress Creek Renewables | Pontiac, IL | 210 MWh | Oct 2024 | Dec 2024 |
Solar
|
| Baker Point | Cypress Creek Renewables | Thurmont, MD | 13 GWh | Sep 2016 | Dec 2024 |
Solar
|
| Barnhill Road Solar, LLC | Cypress Creek Renewables | Elizabeth City, NC | 5 GWh | Nov 2016 | Dec 2024 |
Solar
|
| Leggett Solar, LLC | Cypress Creek Renewables | Leggett, NC | 8 GWh | Nov 2016 | Dec 2024 |
Solar
|
| Silvi Gibraltar Rock | CVI CleanCapital Solar 5 LLC | Belle Mead, NJ | 3 GWh | Sep 2016 | Dec 2024 |
Solar
|
| Seabrook Village | CVI CleanCapital Solar 5 LLC | Tinton Falls, NJ | 4 GWh | Aug 2016 | Dec 2024 |
Solar
|
| Pfizer Peapack Solar | CVI CleanCapital Solar 5 LLC | Peapack, NJ | 7 GWh | Sep 2016 | Dec 2024 |
Solar
|
| Imclone Solar Electric Facility | CVI CleanCapital Solar 5 LLC | Branchburg, NJ | 10 GWh | Apr 2014 | Dec 2024 |
Solar
|
| Delilah Road Landfill | CVI CleanCapital Solar 5 LLC | Egg Harbor, NJ | 13 GWh | Sep 2016 | Dec 2024 |
Solar
|
| The Lawrenceville School Solar Facility | CVI CleanCapital Solar 4 LLC | Lawrenceville, NJ | 7 GWh | Apr 2012 | Dec 2024 |
Solar
|
| Amazon | CVI CleanCapital Solar 4 LLC | Carteret, NJ | 4 GWh | Nov 2011 | Dec 2024 |
Solar
|
| North Jersey Media Group Solar Facility | CVI CleanCapital Solar 4 LLC | Rockaway Township, NJ | 4 GWh | Feb 2013 | Dec 2024 |
Solar
|
| United Stationers Supply Solar Electric | CVI CleanCapital Solar 4 LLC | Cranbury, NJ | 3 GWh | Nov 2011 | Dec 2024 |
Solar
|
| Corning Pharmaceutical Glass | CVI CleanCapital Solar 4 LLC | Vineland, NJ | 3 GWh | Aug 2012 | Dec 2024 |
Solar
|
| Atlantic Coast Freezers Solar Facility | CVI CleanCapital Solar 4 LLC | Vineland, NJ | 2 GWh | Mar 2012 | Dec 2024 |
Solar
|
| Williams-Sonoma Solar Facility | CVI CleanCapital Solar 4 LLC | Jamesburg, NJ | 4 GWh | Nov 2011 | Dec 2024 |
Solar
|
| Middlesex Apple Orchard Solar | CVI CleanCapital Solar 4 LLC | North Brunswick, NJ | 6 GWh | Mar 2013 | Dec 2024 |
Solar
|
| CentraState Medical Center PV Facility | CVI CleanCapital Solar 1 LLC | Freehold, NJ | 4 GWh | Sep 2014 | Dec 2024 |
Solar
|
| BBB Corporate Headquarters | Cushman Wakefield | Union, NJ | 426 MWh | May 2010 | Nov 2024 |
Solar
|
| CU Solar Plant | CU Solar LLC | Cedarville, OH | 2 GWh | Mar 2013 | Dec 2024 |
Solar
|
| CSL Behring LLC | CSL Behring LLC | Bradley, IL | 9 GWh | Apr 1993 | Dec 2024 |
Natural Gas
|
| CSG Mt. Morris 2, LLC | CSG Mt. Morris 2, LLC | Mt. Morries, IL | 4 GWh | Mar 2021 | Dec 2024 |
Solar
|
| Croda Atlas Point CHP | Croda Inc. | New Castle, DE | 15 GWh | Jul 2013 | Dec 2024 |
Landfill Gas
|
| Criterion | Criterion Power Partners LLC | Oakland, MD | 238 GWh | Nov 2010 | Sep 2025 |
Wind
|
| Crete Energy Venture LLC | Crete Energy Venture LLC | Crete, IL | 57 GWh | Apr 2002 | Nov 2024 |
Natural Gas
|
| CPV Three Rivers Energy Center | CPV Three Rivers, LLC | Morris, IL | 6 TWh | May 2023 | Sep 2025 |
Natural Gas
|
| CPV St Charles Energy Center | CPV Maryland LLC | Waldorf, MD | 4 TWh | Jan 2017 | Sep 2025 |
Natural Gas
|
| CPV Maple Hill Solar | CPV Maple Hill Solar, LLC | Portage, PA | 159 GWh | Oct 2023 | Sep 2025 |
Solar
|
| CPV Fairview Energy Center | CPV Fairview, LLC | Johnstown, PA | 8 TWh | Nov 2019 | Sep 2025 |
Natural Gas
|
| New River Clean Energy | Cox Enterprises | Beckley, WV | 8 GWh | Jan 2017 | Dec 2024 |
Landfill Gas
|
| Manheim New Jersey | Cox Enterprises | Bordentown, NJ | 4 GWh | May 2009 | Dec 2024 |
Solar
|
| Cox Waste to Energy | Cox Companies, LLC | Campbellsville, KY | 10 GWh | Dec 1994 | Dec 2024 |
Wood/Wood Waste Solids
|
| Montgomery County Resource Recovery | Covanta Montgomery, Inc. | Dickerson, MD | 289 GWh | Apr 1995 | Sep 2025 |
Non-biogenic Municipal Solid Waste : 54.6%
Biogenic Municipal Solid Waste : 44.6%
Natural Gas : 0.8%
|
| Lancaster County Resource Recovery | Covanta Lancaster Inc | Brainbridge, PA | 183 GWh | Nov 1990 | Sep 2025 |
Non-biogenic Municipal Solid Waste : 54.9%
Biogenic Municipal Solid Waste : 44.9%
|
| Covanta Fairfax Energy | Covanta Fairfax Inc | Lorton, VA | 647 GWh | Feb 1990 | Sep 2025 |
Non-biogenic Municipal Solid Waste : 54.3%
Biogenic Municipal Solid Waste : 44.4%
Natural Gas : 1.3%
|
| Covanta Essex Company | Covanta Essex Company | Newark, NJ | 484 GWh | Oct 1990 | Sep 2025 |
Non-biogenic Municipal Solid Waste : 55.0%
Biogenic Municipal Solid Waste : 45.0%
|
| Covanta Delaware Valley | Covanta Delaware Valley LP | Chester, PA | 532 GWh | Mar 1991 | Sep 2025 |
Non-biogenic Municipal Solid Waste : 54.9%
Biogenic Municipal Solid Waste : 45.0%
|
| Camden Resource Recovery Facility | Covanta Camden Energy Recovery Center | Camden, NJ | 161 GWh | Feb 1991 | Sep 2025 |
Non-biogenic Municipal Solid Waste : 54.6%
Biogenic Municipal Solid Waste : 44.7%
Natural Gas : 0.7%
|
| Covanta Alexandria/Arlington Energy | Covanta Alexandria/Arlington | Alexandria, VA | 146 GWh | Sep 1987 | Sep 2025 |
Non-biogenic Municipal Solid Waste : 55.0%
Biogenic Municipal Solid Waste : 45.0%
|
| Bay View Backup Power Facility | COT/Division of Water Reclamation | Toledo, OH | 629 MWh | Dec 2006 | Dec 2024 |
Distillate Fuel Oil : 99.1%
Natural Gas : 0.9%
|
| Cortland | Cortland Solar 2 LLC | Cortland, IL | 4 GWh | Apr 2021 | Dec 2024 |
Solar
|
| Cork Oak Solar | Cork Oak Solar, LLC | Halifax, NC | 38 GWh | Nov 2017 | Dec 2024 |
Solar
|
| Cleveland Thermal | Corix Cleveland Thermal Generating LP | Cleveland, OH | 2 GWh | Jan 2017 | Dec 2024 |
Natural Gas
|
| Cordova Energy | Cordova Energy Co LLC | Cordova, IL | 1 TWh | May 2001 | Dec 2024 |
Natural Gas
|
| Cooper Farms VW Project | Cooper Hatchery Inc. | Van Wert, OH | 13 GWh | Feb 2012 | Dec 2024 |
Wind
|
| Federalsburg Energy Storage 1 LLC | Convergent Energy and Power LP | Federaslburg, MD | 1 GWh | Oct 2021 | Dec 2024 |
Solar
|
| New Covert Generating Facility | Consumers Energy Co - (MI) | Covert, MI | 7 TWh | Feb 2004 | Sep 2025 |
Natural Gas
|
| Mount Saint Mary's | Constellation Solar Horizons LLC | Emmitsburg, MD | 17 GWh | Jun 2012 | Sep 2025 |
Solar
|
| Delaware Generating Station | Constellation Power, Inc | Philadelphia, PA | 169 MWh | Mar 1969 | Dec 2024 |
Distillate Fuel Oil
|
| Eddystone Generating Station | Constellation Power, Inc | Eddystone, PA | 61 GWh | Apr 1967 | Dec 2024 |
Natural Gas : 81.6%
Distillate Fuel Oil : 18.4%
|
| Southwark | Constellation Power, Inc | Philadelphia, PA | 119 MWh | May 1967 | Dec 2024 |
Distillate Fuel Oil
|
| Schuylkill Generating Station | Constellation Power, Inc | Phila., PA | 119 MWh | Apr 1969 | Dec 2024 |
Distillate Fuel Oil
|
| Chester Generating Station | Constellation Power, Inc | Chester, PA | 128 MWh | Jan 1969 | Dec 2024 |
Distillate Fuel Oil
|
| Richmond Generating Station | Constellation Power, Inc | Phila., PA | 259 MWh | May 1973 | Jul 2024 |
Distillate Fuel Oil
|
| Falls | Constellation Power, Inc | Morrisville, PA | 187 MWh | Apr 1970 | Dec 2024 |
Distillate Fuel Oil
|
| Moser Generating Station | Constellation Power, Inc | Pottstown, PA | 187 MWh | Apr 1970 | Dec 2024 |
Distillate Fuel Oil
|
| Croydon CT Generating Station | Constellation Power, Inc | Bristol Twp., PA | 2 GWh | May 1974 | Oct 2024 |
Distillate Fuel Oil
|
| Conowingo | Constellation Power, Inc | Darlington, MD | 2 TWh | Feb 1928 | Sep 2025 |
Water
|
| Philadelphia | Constellation Power Source Generation, LLC | Baltimore, MD | 5 GWh | Jul 1970 | Dec 2024 |
Distillate Fuel Oil
|
| Perryman | Constellation Power Source Generation, LLC | Harford County, MD | 195 GWh | Dec 1971 | Sep 2025 |
Natural Gas : 79.7%
Distillate Fuel Oil : 20.3%
|
| LaSalle Generating Station | Constellation Nuclear | Marseilles, IL | 20 TWh | Dec 1983 | Sep 2025 |
Nuclear
|
| Limerick | Constellation Nuclear | Sanatoga, PA | 19 TWh | Jan 1986 | Sep 2025 |
Nuclear
|
| Byron Generating Station | Constellation Nuclear | Byron, IL | 20 TWh | Aug 1985 | Sep 2025 |
Nuclear
|
| Braidwood Generation Station | Constellation Nuclear | Braceville, IL | 20 TWh | Jun 1988 | Sep 2025 |
Nuclear
|
| Dresden Generating Station | Constellation Nuclear | Morris, IL | 15 TWh | Jul 1970 | Sep 2025 |
Nuclear
|
| Calvert Cliffs Nuclear Power Plant | Constellation Nuclear | Lusby, MD | 15 TWh | Apr 1975 | Sep 2025 |
Nuclear
|
| Quad Cities Generating Station | Constellation Nuclear | Cordova, IL | 15 TWh | Nov 1972 | Sep 2025 |
Nuclear
|
| Peach Bottom | Constellation Nuclear | Delta, PA | 22 TWh | Jun 1974 | Sep 2025 |
Nuclear
|
| CES Cherry Hill Solar | Consolidated Edison Solutions Inc. | Cherry Hill, NJ | 2 GWh | Jan 2016 | Dec 2024 |
Solar
|
| CES VMT Solar | Consolidated Edison Solutions Inc. | Hagerstown, MD | 1 GWh | Jun 2015 | Dec 2024 |
Solar
|
| RP Wind | Consolidated Edison Solutions Inc. | Russells Point, OH | 8 GWh | Nov 2013 | Dec 2024 |
Wind
|
| Frenchtown II Solar | Consolidated Edison Development Inc. | Frenchtown, NJ | 5 GWh | Nov 2011 | Dec 2024 |
Solar
|
| PA Solar Park | Consolidated Edison Development Inc. | Nesquehoning, PA | 13 GWh | Sep 2012 | Sep 2025 |
Solar
|
| Frenchtown III Solar | Consolidated Edison Development Inc. | Frenchtown, NJ | 12 GWh | Nov 2013 | Dec 2024 |
Solar
|
| Lebanon Solar | Consolidated Edison Development Inc. | Glen Gardner, NJ | 3 GWh | Nov 2011 | Dec 2024 |
Solar
|
| Frenchtown I Solar | Consolidated Edison Development Inc. | Frenchtown, NJ | 5 GWh | Dec 2011 | Dec 2024 |
Solar
|
| Flemington Solar | Consolidated Edison Development Inc. | Flemington, NJ | 14 GWh | Nov 2011 | Dec 2024 |
Solar
|
| Pilesgrove | Consolidated Edison Development Inc. | Pilesgrove, NJ | 25 GWh | Jul 2011 | Dec 2024 |
Solar
|
| Murray Hill Solar | Consolidated Edison Development Inc. | New Providence, NJ | 2 GWh | Apr 2011 | Dec 2024 |
Solar
|
| Watlington Solar | Consolidated Edison Development Inc. | Halifax, VA | 40 GWh | Feb 2023 | Dec 2024 |
Solar
|
| Lakehurst Solar | Consolidated Edison Development Inc. | Lakehurst, NJ | 18 GWh | Feb 2020 | Dec 2024 |
Solar
|
| PA Solar Park II | Consolidated Edison Development Inc. | Nesquehoning, PA | 15 GWh | Dec 2019 | Dec 2024 |
Solar
|
| Water Strider Solar | Consolidated Edison Development Inc. | Nathalie, VA | 165 GWh | Feb 2021 | Sep 2025 |
Solar
|
| Wythe County Solar | Consolidated Edison Development Inc. | Wythe County, VA | 93 GWh | - | Sep 2025 |
Solar
|
| Pleasant Hill Solar | Consolidated Edison Development Inc. | Suffolk, VA | 40 GWh | May 2023 | Oct 2024 |
Solar
|
| Connell East LLC | Connell East LLC. | Berkeley Heights, NJ | 1 GWh | Dec 2012 | Dec 2024 |
Solar
|
| Conetoe Solar | Conetoe Solar, LLC | Tarboro, NC | 8 GWh | Nov 2015 | Dec 2024 |
Solar
|
| Community Foodbank of NJ | Community Foodbank of NJ | Hillside, NJ | 884 MWh | Jul 2012 | Dec 2024 |
Solar
|
| Commonwealth Chesapeake | Commonwealth Chesapeake Co LLC | New Church, VA | 34 GWh | Jul 2000 | Sep 2025 |
Distillate Fuel Oil
|
| Collinwood BioEnergy Facility | Collinwood BioEnergy | Cleveland, OH | 3 GWh | Apr 2011 | Dec 2024 |
Other Biomass Gas
|
| Colice Hall Solar | Colice Hall Solar LLC | Ahoskie, NC | 33 GWh | Jun 2023 | Dec 2024 |
Solar
|
| CIP II/AR Bridgewater Holdings - NJCOE | COE Bridgewater LLC c/o Thor Equities, LLC | Bridgewater, NJ | 26 GWh | Oct 2002 | Sep 2025 |
Natural Gas : 99.6%
|
| Clevelandcliffs Warren | Clevelandcliffs Warren | Warren, OH | 53 GWh | Sep 1934 | Sep 2024 |
Other Gas : 62.9%
Natural Gas : 37.1%
|