Woodsdale
2100 Woodsdale Rd, Trenton, OH 45067Plant Summary Information
Woodsdale is ranked #36 out of 199 power plants in Ohio in terms of total annual net electricity generation.
Woodsdale is comprised of 6 generators and generated 85.5 GWh during the 3-month period between November 2025 to February 2026.
| Plant Name | Woodsdale |
|---|---|
| Utility Name | Duke Energy Kentucky Inc |
| Location | Butler County, OH |
| Initial Operation Date | May 1992 |
| Last Update | Feb 2026 |
| Annual Generation | 372.7 GWh |
| Annual Consumption | 6.6 M MMBtu |
| Ranked #1,691 out of 12,637 Power Plants Nationwide | |
| Ranked #618 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #36 out of 199 Ohio Power Plants | |
| Ranked #19 out of 55 Ohio Natural Gas Power Plants | |
| Fuel Types | Natural Gas : 96.8% Distillate Fuel Oil : 3.2% |
Map of Woodsdale
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Woodsdale.
Monthly Net Generation for Woodsdale
Monthly Plant Fuel Consumption for Woodsdale
Woodsdale Details
| Summary Information | |
|---|---|
| Plant Name | Woodsdale (7158) |
| Plant Address | 2100 Woodsdale Rd, Trenton, OH 45067 |
| Utility | Duke Energy Kentucky Inc (55729) |
| Latitude, Longitude | 39.4492, -84.4611 |
| Generation Dates on File | Jan 2001 to Feb 2026 |
| Initial Operation Date | May 1992 |
| Annual Generation | 372.7 GWh |
| Fuel Types | Natural Gas : 96.8% Distillate Fuel Oil : 3.2% |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | RFC |
| Balancing Authority | PJM Interconnection, LLC (PJM) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Duke Energy Ohio Inc (3542) OH |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Pipeline Name | TEXAS EASTERN TRANSMISSION LP |
| Natural Gas Storage | No |
| Liquefied Natural Gas Storage | No |
Generator GT3 Details Operating May 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 95.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 80 MW |
| Winter Capacity | 94 MW |
| Minimum Load | 5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 1992 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT5 Details Operating May 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 95.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 80 MW |
| Winter Capacity | 94 MW |
| Minimum Load | 5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 1992 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT6 Details Operating May 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 95.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 80 MW |
| Winter Capacity | 94 MW |
| Minimum Load | 5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 1992 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT2 Details Operating July 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 95.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 80 MW |
| Winter Capacity | 94 MW |
| Minimum Load | 5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1992 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT4 Details Operating July 1992
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 95.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 78 MW |
| Winter Capacity | 94 MW |
| Minimum Load | 5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 1992 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT1 Details Operating May 1993
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 95.3 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 78 MW |
| Winter Capacity | 94 MW |
| Minimum Load | 5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 1993 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Natural Gas / Distillate Fuel Oil |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | Yes |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Woodsdale Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #608 | Trinidad (TX) | Trinidad, TX | 376.4 GWh |
| #609 | F.D. Kuester Generating Station | Negaunee, MI | 374.8 GWh |
| #610 | West Valley Generation Project | West Valley City, UT | 374.8 GWh |
| #611 | Desert Star Energy Center | Boulder City, NV | 371.1 GWh |
| #612 | Western 102 Power Plant | McCarran, NV | 369.4 GWh |
| #613 | Kimberly Clark Mobile - CHP Plant | Mobile, AL | 367.8 GWh |
| #614 | Bellingham Cogeneration Facility | Bellingham, MA | 367.8 GWh |
| #615 | Valley (WI) | Milwaukee, WI | 365.4 GWh |
| #616 | Zion Energy Center | Zion, IL | 363.6 GWh |
| #617 | Hal C Weaver Power Plant | Austin, TX | 361.2 GWh |
| #619 | Arapahoe Combustion Turbine Project | Denver, CO | 360.3 GWh |
| #620 | Turtle Creek | Springfield, NE | 387.2 GWh |
| #621 | Saranac Facility | Plattsburgh, NY | 354.9 GWh |
| #622 | Red Gate Power Plant | Edinburg, TX | 354.2 GWh |
| #623 | Pawnee | Brush, CO | 1.3 TWh |
| #624 | Mark One Power Station | Angleton, TX | 353.8 GWh |
| #625 | RED-Rochester, LLC | Rochester, NY | 345.8 GWh |
| #626 | Henry County | New Castle, IN | 344.7 GWh |
| #627 | Humboldt Bay | Eureka, CA | 343.0 GWh |
| #628 | HO Clarke Generating | Houston, TX | 336.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Woodsdale.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Aero Solar Facility | Burlington, KY | 2.9 GWh | 30.8 mi |
| Central Utility Plant Cincinnati | Cincinnati, OH | 216.3 GWh | 21.9 mi |
| Dick's Creek | Monroe, OH | 8.7 GWh | 4.6 mi |
| East Campus Utility Plant | Cincinnati, OH | 519.4 MWh | 21.6 mi |
| Hamilton (OH) | Hamilton, OH | 1.1 GWh | 5.7 mi |
| Hamilton Hydro | HAMILTON, OH | 7.8 GWh | 5.6 mi |
| Hamilton Peaking | Hamilton, OH | 2.5 GWh | 7.3 mi |
| L'Oreal Solar - Florence | Florence, KY | 1.6 GWh | 32.8 mi |
| Madison | Trenton, OH | 1.0 TWh | 0.3 mi |
| Miami Fort | North Bend, OH | 6.6 TWh | 29.6 mi |
| Middletown Coke Company, LLC | Middletown, OH | 349.5 GWh | 3.6 mi |
| Middletown Energy Center | Middletown, OH | 3.1 TWh | 6.1 mi |
| Monument | Dayton, OH | 114.0 MWh | 26.7 mi |
| O H Hutchings | Miamisburg, OH | 397.0 MWh | 14.2 mi |
| Parking Lot Array | Cincinnati, OH | 1.7 GWh | 21.4 mi |
| Procter & Gamble Cincinnati Plant | Cincinnati, OH | 9.4 GWh | 19.1 mi |
| RA Jones Roof Mounted Solar System | Covington, KY | 1.2 GWh | 28.7 mi |
| Richmond Solar Site 2 | Richmond, IN | 13.8 GWh | 32.6 mi |
| Tait Electric Generating Station | Moraine, OH | 1.3 TWh | 23.4 mi |
| Yankee Street | Centerville, OH | 23.2 GWh | 17.3 mi |