Victory Pass
37949 DC379, Desert Center, CA 92239Plant Summary Information
Victory Pass is ranked #20 out of 816 solar farms in California in terms of total annual net electricity generation.
Victory Pass generated 126.7 GWh during the 3-month period between December 2024 to March 2025.
Plant Name | Victory Pass |
---|---|
Utility Name | Victory Pass I, LLC |
Location | Riverside County, CA |
Initial Operation Date | March 2024 |
Last Update | Mar 2025 |
Annual Generation | 575.1 GWh |
Annual Consumption | 2.1 M MMBtu |
Ranked #1,174 out of 12,288 Power Plants Nationwide | |
Ranked #52 out of 6,174 Solar Power Plants Nationwide | |
Ranked #66 out of 1,564 California Power Plants | |
Ranked #20 out of 816 California Solar Power Plants | |
Fuel Types | Solar |
Map of Victory Pass
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Victory Pass.
Monthly Net Generation for Victory Pass
Victory Pass Details
Summary Information | |
---|---|
Plant Name | Victory Pass (65743) |
Plant Address | 37949 DC379, Desert Center, CA 92239 |
Utility | Victory Pass I, LLC (64995) |
Latitude, Longitude | 33.701, -115.31629 |
Generation Dates on File | Mar 2024 to Mar 2025 |
Initial Operation Date | March 2024 |
Annual Generation | 575.1 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | NA |
Ash Impoundment | |
Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
Grid Voltage | 220.00 kV |
Energy Storage | Yes |
Generator VCTBA Details Operating March 2024
Technology | Batteries |
---|---|
Prime Mover | Battery |
Ownership | Single Owner |
Nameplate Capacity | 50 MW |
Summer Capacity | 50 MW |
Winter Capacity | 50 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2024 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Electricity used for energy storage |
Energy Storage Details | |
Nameplate Energy Capacity MWH | 200 |
---|---|
Maximum Charge Rate | 50 MW |
Maximum Discharge Rate | 50 MW |
Storage Technology | LIB |
Nameplate Reactive Power Rating | 16 |
Storage Enclosure Type | CT |
Arbitrage | P |
Frequency Regulation | Yes |
Excess Wind And Solar Generation | Yes |
Ac Coupled | Yes |
Direct Support Of Another Unit | No |
Direct Support Plant Id | 65743 |
Direct Support Gen Id | VCTPV |
Support T D Asset | No |
Generator VCTPV Details Operating March 2024
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 200 MW |
Summer Capacity | 200 MW |
Winter Capacity | 200 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | March 2024 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
Bifacial | Yes |
DC Net Capacity | 272 MW |
Crystalline Silicon | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Victory Pass Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#42 | Stateline Solar | Nipton, CA | 619.9 GWh |
#43 | Oberon II Solar Project | Desert Center, CA | 593.0 GWh |
#44 | Eleven Mile Solar Center | Coolidge, AZ | 576.8 GWh |
#45 | Titan Solar Project | Van Horn, TX | 601.7 GWh |
#46 | Mojave Solar Project | Hinkley, CA | 600.3 GWh |
#47 | California Valley Solar Ranch | California Valley, CA | 597.7 GWh |
#48 | Bighorn Solar 1 | Pueblo, CO | 594.3 GWh |
#49 | Agua Caliente Solar Project | Dateland, AZ | 591.7 GWh |
#50 | Blythe Solar 110, LLC | Blythe, CA | 571.4 GWh |
#51 | Blythe Mesa Solar II | Blythe, CA | 571.8 GWh |
#53 | Thunder Wolf Energy Center Hybrid | Avondale, CO | 556.8 GWh |
#54 | RE Maplewood | McCamey, TX | 570.5 GWh |
#55 | AV Solar Ranch One | Lancaster, CA | 569.0 GWh |
#56 | Texas Solar Nova 2 | Spur, TX | 565.9 GWh |
#57 | Oberon Solar Project | Desert Center, CA | 544.8 GWh |
#58 | Sparta Solar | Pawnee, TX | 562.7 GWh |
#59 | Eiffel Solar Project | Paris, TX | 562.4 GWh |
#60 | Dodge Flat | Reno, NV | 555.2 GWh |
#61 | Daggett 2 | Daggett, CA | 537.9 GWh |
#62 | Desert Sunlight 250, LLC | Desert Center, CA | 555.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Victory Pass.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arica Solar | Desert Center, CA | 659.1 GWh | 0 mi |
Arlington Energy Center II | Blythe, CA | 634.7 GWh | 31.1 mi |
Arlington Energy Center III | Blythe, CA | 293.2 GWh | 31.1 mi |
Athos Solar Project | Desert Center, CA | 645.4 GWh | 4.1 mi |
Chuckawalla Solar | Blythe, CA | 7.1 GWh | 24.7 mi |
Chuckawalla Valley State Prison | Blythe, CA | 1.4 GWh | 25.5 mi |
Desert Harvest II LLC | Desert Center, CA | 166.4 GWh | 7.8 mi |
Desert Harvest, LLC | Desert Center, CA | 207.8 GWh | 7.8 mi |
Desert Sunlight 250, LLC | Desert Center, CA | 555.7 GWh | 8.5 mi |
Desert Sunlight 300, LLC | Desert Center, CA | 666.9 GWh | 9.5 mi |
Genesis Solar Energy Project | Blythe, CA | 642.6 GWh | 18.5 mi |
Ironwood Solar LLC | Blythe, CA | 7.5 GWh | 24.8 mi |
Maverick Solar 4, LLC | Desert Center, CA | 240.9 GWh | 3.7 mi |
Maverick Solar 6, LLC | Desert Center, CA | 238.7 GWh | 3.7 mi |
Maverick Solar 7, LLC | Desert Center, CA | 302.4 GWh | 3.7 mi |
Maverick Solar, LLC | Desert Center, CA | 375.5 GWh | 3.7 mi |
Oberon II Solar Project | Desert Center, CA | 593.0 GWh | 4.3 mi |
Oberon Solar Project | Desert Center, CA | 544.8 GWh | 4.3 mi |
SE Athos II, LLC | Desert Center, CA | 516.0 GWh | 4.1 mi |
SunEdison Ironwood State Prison | Blythe, CA | 996.0 MWh | 24.7 mi |