Atascadero State Hospital is ranked #571 out of 818 solar farms in California in terms of total annual net electricity generation.

Atascadero State Hospital generated 478.0 MWh during the 3-month period between September 2024 to December 2024.

Plant NameAtascadero State Hospital
Utility NameEcoplexus, Inc
LocationSan Luis Obispo County, CA
Initial Operation DateAugust 2020
Last Update Dec 2024
Annual Generation 2.8 GWh
Annual Consumption 10.0 k MMBtu
Ranked #9,541 out of 12,327 Power Plants Nationwide
Ranked #4,437 out of 6,200 Solar Power Plants Nationwide
Ranked #1,280 out of 1,567 California Power Plants
Ranked #571 out of 818 California Solar Power Plants
Fuel Types Solar

Map of Atascadero State Hospital

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Atascadero State Hospital.

Create Your Account Today

Monthly Net Generation for Atascadero State Hospital

36036027027018018090900020212021Jul '21Jul '2120222022Jul '22Jul '2220232023Jul '23Jul '2320242024Jul '24Jul '24
Download SVG
Download PNG
Download CSV

Atascadero State Hospital Details

Summary Information
Plant NameAtascadero State Hospital (64523)
Plant Address10333 El Camino Real, Atascadero, CA 93422
UtilityEcoplexus, Inc (58970)
Latitude, Longitude35.46333, -120.63401
Generation Dates on FileJan 2021 to Dec 2024
Initial Operation DateAugust 2020
Annual Generation 2.8 GWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusYes
FERC Small Power Producer Docket NumberQF20-139-000
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator (CISO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment
Transmission / Distribution OwnerPacific Gas & Electric Co. (14328) CA
Grid Voltage 12.47 kV
Energy StorageNo

Generator ATASC Details Operating August 2020

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity1.1 MW
Summer Capacity1.1 MW
Winter Capacity1.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateAugust 2020
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Solar Details
Single Axis TrackingYes
East West Fixed TiltYes
Azimuth Angle180
Tilt Angle52
DC Net Capacity1.4 MW
Crystalline SiliconYes
Net Metering AgreementNo
Virtual Net Metering AgreementNo

Atascadero State Hospital Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#4427ASA Gouverneur NY Solar II LLCGouverneur, NY2.8 GWh
#4428CDCR (CA) - Pleasant Valley State PrisonCoalinga, CA2.8 GWh
#4429Curtis Hill Solar CSGCharlton, MA2.8 GWh
#4430Plote SomonaukSomonauk, IL2.8 GWh
#4431Krumkill Road Solar South, LLCGuilderland, NY2.8 GWh
#4432Carver MA 1 Community SolarCarver, MA2.8 GWh
#4433Limerick Road Solar FarmShelburne, VT2.8 GWh
#4434Germantown Solar, LLCRural Hall, NC2.8 GWh
#4435Panda Solar NC 7, LLCFaison, NC2.8 GWh
#4436Caelum Community SolarFoley, MN2.8 GWh
#4438CED Champaign Solar LLCChampaign, IL2.8 GWh
#4439Clif Bar Bakery of Twin FallsTwin Falls, ID2.8 GWh
#4440Dudley Solar CSGDudley, MA2.8 GWh
#4441Spruce - WCMD - Resh IHagerstown, MD2.8 GWh
#4442DG AMP Solar Jackson CenterJackson Center, OH2.8 GWh
#4443Finger Lakes Solar IGeneva, NY2.8 GWh
#4444BEMS East Solar (CSG)Southhampton, NJ2.8 GWh
#4445Zonneveld Oak GroveLaton, CA2.8 GWh
#4446Blydenburgh Solar ProjectHaupaugge, NY2.8 GWh
#4447WestminsterWestminster, VT2.8 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Atascadero State Hospital.

Plant NamePlant LocationAnnual GenerationDistance
Aera San Ardo Cogen FacilitySan Ardo, CA17.2 GWh36.1 mi
CA Flats Solar 130, LLCShandon, CA244.1 GWh16.7 mi
CA Flats Solar 150, LLCShandon, CA293.9 GWh16.7 mi
CA-DGS-California Men's ColonySan Luis Obispo, CA4.6 GWh10.1 mi
California Valley Solar RanchCalifornia Valley, CA597.7 GWh41.5 mi
Camp San Luis ObispoSan Luis Obispo, CA158.0 MWh11.2 mi
Cold Canyon 1San Luis Obispo, CA10.0 GWh19.2 mi
Coronal Lost HillsLost Hills, CA37.4 GWh44.8 mi
Diablo CanyonAvila Beach, CA18.5 TWh21.4 mi
Firestone Walker Brewery - Phase 1Paso Robles, CA3.3 GWh9.8 mi
Lost Hills/BlackwellLost Hills, CA80.6 GWh45.4 mi
Meridian VineyardsPaso Robles, CA1.4 GWh14.8 mi
Nacimiento Hydro ProjectBradley, CA18.2 GWh27.1 mi
Roll Lost HillsLost Hills, CA5.5 GWh43.8 mi
Salinas River CogenerationSan Ardo, CA261.2 GWh36.2 mi
Stenner Creek SolarSan Luis Obispo, CA9.5 GWh10.4 mi
Sutter Home Winery TCCPaso Robles, CA1.1 GWh19 mi
Topaz Solar FarmSanta Margarita, CA1.0 TWh32.1 mi
Vintner SolarTempleton, CA4.2 GWh7.1 mi
Wonderful Lost HillsLost Hills, CA48.2 GWh44.9 mi