Firestone Walker Brewery - Phase 1
1400 Ramada Drive, Paso Robles, CA 93446Plant Summary Information
Firestone Walker Brewery - Phase 1 is ranked #535 out of 849 solar farms in California in terms of total annual net electricity generation.
Firestone Walker Brewery - Phase 1 generated 637.0 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Firestone Walker Brewery - Phase 1 |
|---|---|
| Utility Name | SkyHigh 2 Solar |
| Location | San Luis Obispo County, CA |
| Initial Operation Date | November 2020 |
| Last Update | Dec 2024 |
| Annual Generation | 3.3 GWh |
| Annual Consumption | 12.0 k MMBtu |
| Ranked #9,189 out of 12,539 Power Plants Nationwide | |
| Ranked #4,132 out of 6,400 Solar Power Plants Nationwide | |
| Ranked #1,233 out of 1,600 California Power Plants | |
| Ranked #535 out of 849 California Solar Power Plants | |
| Fuel Types | Solar |
Map of Firestone Walker Brewery - Phase 1
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Firestone Walker Brewery - Phase 1.
Monthly Net Generation for Firestone Walker Brewery - Phase 1
Firestone Walker Brewery - Phase 1 Details
| Summary Information | |
|---|---|
| Plant Name | Firestone Walker Brewery - Phase 1 (64391) |
| Plant Address | 1400 Ramada Drive, Paso Robles, CA 93446 |
| Utility | SkyHigh 2 Solar (63432) |
| Latitude, Longitude | 35.59588, -120.69431 |
| Generation Dates on File | Nov 2020 to Dec 2024 |
| Initial Operation Date | November 2020 |
| Annual Generation | 3.3 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | Yes |
| FERC Small Power Producer Docket Number | QF20-1249-000 |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Pacific Gas & Electric Co. (14328) CA |
| Grid Voltage | 12.47 kV |
| Energy Storage | No |
Generator FWBP1 Details Operating November 2020
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 1.6 MW |
| Summer Capacity | 1.6 MW |
| Winter Capacity | 1.6 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | November 2020 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 2.4 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | Yes |
| Net Metering DC Capacity | 2.4 MW |
| Virtual Net Metering Agreement | No |
Firestone Walker Brewery - Phase 1 Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #4122 | Town of Needham VNEM CSG | Needham, MA | 3.3 GWh |
| #4123 | Wappinger 9D Solar | Wappinger, NY | 3.3 GWh |
| #4124 | Lister Avenue Solar | Newark, NJ | 3.3 GWh |
| #4125 | Expressway Solar C2 | Victorville, CA | 3.3 GWh |
| #4126 | Ellerbe | Ellerbe, NC | 3.3 GWh |
| #4127 | Salt Point Solar (Hybrid) | Poughkeepsie, NY | 3.3 GWh |
| #4128 | Nashville Farms, LLC | Nashville, NC | 3.3 GWh |
| #4129 | Monson Solar, LLC | Monson, MA | 3.3 GWh |
| #4130 | PowerFin Kingsbery | Austin, TX | 3.3 GWh |
| #4131 | Oak Hill Solar Array | Evansville, IN | 3.3 GWh |
| #4133 | Lafayette Solar I, LLC | Shelby, NC | 3.3 GWh |
| #4134 | Mesa CSG 2 Massicotte | Palisade, CO | 3.3 GWh |
| #4135 | Chester CSG | Chester, NY | 3.3 GWh |
| #4136 | BlackRock-Matrix | South Brunswick, NJ | 3.3 GWh |
| #4137 | SR Jackson II | Jackson, TN | 3.3 GWh |
| #4138 | Cairo Solar Farm, LLC | Cairo, GA | 3.3 GWh |
| #4139 | Landau Solar | Kingston, NY | 3.3 GWh |
| #4140 | Westmont 400A | Los Angeles, CA | 3.3 GWh |
| #4141 | CDCR (CA) - Wasco State Prison | Wasco, CA | 3.3 GWh |
| #4142 | Limelight Solar I, LLC | Spartanburg, SC | 3.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Firestone Walker Brewery - Phase 1.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Aera San Ardo Cogen Facility | San Ardo, CA | 17.2 GWh | 26.4 mi |
| Atascadero State Hospital | Atascadero, CA | 2.8 GWh | 9.8 mi |
| CA Flats Solar 130, LLC | Shandon, CA | 262.5 GWh | 16.3 mi |
| CA Flats Solar 150, LLC | Shandon, CA | 299.6 GWh | 16.3 mi |
| CA-DGS-California Men's Colony | San Luis Obispo, CA | 4.6 GWh | 18.7 mi |
| Camp San Luis Obispo | San Luis Obispo, CA | 158.0 MWh | 19 mi |
| CED Avenal | Avenal, CA | 9.7 GWh | 41.1 mi |
| Coalinga 25D Cogen | Coalinga, CA | 42.3 GWh | 42.1 mi |
| Cold Canyon 1 | San Luis Obispo, CA | 3.8 GWh | 28.8 mi |
| Diablo Canyon | Avila Beach, CA | 18.5 TWh | 28.1 mi |
| Meridian Vineyards | Paso Robles, CA | 1.0 GWh | 8.8 mi |
| Nacimiento Hydro Project | Bradley, CA | 18.2 GWh | 17.6 mi |
| Paso Robles - Municipal Airport | Paso Robles, CA | 6.0 GWh | 6.6 mi |
| Salinas River Cogeneration | San Ardo, CA | 258.0 GWh | 26.4 mi |
| Sand Drag LLC | Avenal, CA | 28.2 GWh | 42.3 mi |
| Stenner Creek Solar | San Luis Obispo, CA | 9.5 GWh | 19.1 mi |
| Sutter Home Winery TCC | Paso Robles, CA | 1.1 GWh | 9.7 mi |
| Topaz Solar Farm | Santa Margarita, CA | 1.0 TWh | 37.6 mi |
| Vintner Solar | Templeton, CA | 4.2 GWh | 2.7 mi |
| Wonderful Orchards - West Valley | Blackwells Corner, CA | 1.4 GWh | 40.7 mi |