Stampede Solar Hybrid
282 Country Road 3538, Saltillo, TX 75478Plant Summary Information
Stampede Solar Hybrid is ranked #27 out of 201 solar farms in Texas in terms of total annual net electricity generation.
Stampede Solar Hybrid generated 183.4 GWh during the 3-month period between June 2025 to September 2025.
| Plant Name | Stampede Solar Hybrid |
|---|---|
| Utility Name | Stampede Solar Project LLC |
| Location | Hopkins County, TX |
| Initial Operation Date | October 2024 |
| Last Update | Sep 2025 |
| Annual Generation | 549.1 GWh |
| Annual Consumption | 1.9 M MMBtu |
| Ranked #1,243 out of 12,539 Power Plants Nationwide | |
| Ranked #78 out of 6,400 Solar Power Plants Nationwide | |
| Ranked #241 out of 799 Texas Power Plants | |
| Ranked #27 out of 201 Texas Solar Power Plants | |
| Fuel Types | Solar |
Map of Stampede Solar Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Stampede Solar Hybrid.
Monthly Net Generation for Stampede Solar Hybrid
Stampede Solar Hybrid Details
| Summary Information | |
|---|---|
| Plant Name | Stampede Solar Hybrid (67762) |
| Plant Address | 282 Country Road 3538, Saltillo, TX 75478 |
| Utility | Stampede Solar Project LLC (66361) |
| Latitude, Longitude | 33.20132, -95.31923 |
| Generation Dates on File | Oct 2024 to Sep 2025 |
| Initial Operation Date | October 2024 |
| Annual Generation | 549.1 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 345.00 kV |
| Energy Storage | Yes |
Generator STMPB Details Operating October 2024
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 72.2 MW |
| Summer Capacity | 72.2 MW |
| Winter Capacity | 72.2 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | October 2024 |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 115 |
|---|---|
| Maximum Charge Rate | 70 MW |
| Maximum Discharge Rate | 70 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 124.9 |
| Storage Enclosure Type | CS |
| Arbitrage | P |
| Frequency Regulation | Yes |
| Voltage Or Reactive Power Support | Yes |
| Direct Support Of Another Unit | No |
| Support T D Asset | No |
Stampede Solar Hybrid Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #68 | AV Solar Ranch One | Lancaster, CA | 569.7 GWh |
| #69 | Eiffel Solar Project | Paris, TX | 567.6 GWh |
| #70 | Hopkins Energy LLC | Dike, TX | 566.1 GWh |
| #71 | Sun Valley Solar Project | Abbott, TX | 565.5 GWh |
| #72 | SE Athos II, LLC | Desert Center, CA | 565.4 GWh |
| #73 | Thunder Wolf Energy Center Hybrid | Avondale, CO | 545.4 GWh |
| #74 | Texas Solar Nova 2 | Spur, TX | 562.0 GWh |
| #75 | Orion III Solar Project | Buckholts, TX | 558.6 GWh |
| #76 | Orion II Solar Project | Rosebud, TX | 556.1 GWh |
| #77 | Desert Sunlight 250, LLC | Desert Center, CA | 555.7 GWh |
| #79 | Phoebe Solar | Kermit, TX | 554.5 GWh |
| #80 | Dodge Flat | Reno, NV | 547.3 GWh |
| #81 | Golden Field Solar III, LLC | Rosamond, CA | 529.7 GWh |
| #82 | Daggett 2 | Daggett, CA | 527.1 GWh |
| #83 | Agua Caliente Solar Project | Dateland, AZ | 548.2 GWh |
| #84 | Sun Streams 4 | Tonopah, AZ | 513.7 GWh |
| #85 | Porter Solar, LLC (TX) | Krum, TX | 541.9 GWh |
| #86 | Noble Solar | Krum, TX | 540.2 GWh |
| #87 | Azure Sky Solar | Haskell, TX | 533.2 GWh |
| #88 | Galloway 1 Solar Farm | Paint Rock, TX | 539.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Stampede Solar Hybrid.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bright Arrow Solar, LLC | Sulphur Springs, TX | 226.3 GWh | 23.8 mi |
| BT Signal Ranch | Quinlan, TX | 81.3 GWh | 46.8 mi |
| Chisum | Blossom, TX | 20.7 GWh | 30.1 mi |
| Coniglio Solar | Wolfe City, TX | 204.6 GWh | 46.3 mi |
| Delilah Solar Energy II LLC | Bogota, TX | 67.3 GWh | 19.6 mi |
| Delilah Solar Energy LLC | Bogota, TX | 470.4 GWh | 10.7 mi |
| Eiffel Solar Project | Paris, TX | 567.6 GWh | 29.9 mi |
| Estonian Solar Project, LLC | Cooper, TX | 339.2 GWh | 26.8 mi |
| Hecate Energy Upshur Rural LLC | Ore City, TX | 4.1 GWh | 42.1 mi |
| Hopkins Energy LLC | Dike, TX | 566.1 GWh | 8.3 mi |
| Impact Solar 1 | Deport, TX | 348.0 GWh | 18.7 mi |
| Lamar Power Project | Paris, TX | 6.7 TWh | 33.5 mi |
| Mockingbird Solar Center | Brookston, TX | 936.0 GWh | 14.5 mi |
| Paris Energy Center | Paris, TX | 648.0 GWh | 36.9 mi |
| Powerlane Plant | Greenville, TX | 48.9 GWh | 46.7 mi |
| Samson Solar Energy | Cunningham, TX | 367.7 GWh | 8 mi |
| Samson Solar Energy II LLC | Cunningham, TX | 218.5 GWh | 17.8 mi |
| Samson Solar Energy III LLC | Cunningham, TX | 245.3 GWh | 15.7 mi |
| Sterling Solar (TX) | Greenville, TX | 10.5 GWh | 49.4 mi |
| Welsh | Pittsburg, TX | 4.1 TWh | 29.5 mi |