Orion III Solar Project
664 County Road 116A, Buckholts, TX 76569Plant Summary Information
Orion III Solar Project is ranked #45 out of 190 solar farms in Texas in terms of total annual net electricity generation.
Orion III Solar Project generated 131.0 GWh during the 3-month period between January 2025 to April 2025.
Plant Name | Orion III Solar Project |
---|---|
Utility Name | Ben Milam Solar 3 LLC |
Location | Milam County, TX |
Initial Operation Date | August 2024 |
Last Update | Apr 2025 |
Annual Generation | 396.7 GWh |
Annual Consumption | 1.4 M MMBtu |
Ranked #1,561 out of 12,299 Power Plants Nationwide | |
Ranked #124 out of 6,182 Solar Power Plants Nationwide | |
Ranked #302 out of 792 Texas Power Plants | |
Ranked #45 out of 190 Texas Solar Power Plants | |
Fuel Types | Solar |
Map of Orion III Solar Project
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Orion III Solar Project.
Monthly Net Generation for Orion III Solar Project
Orion III Solar Project Details
Summary Information | |
---|---|
Plant Name | Orion III Solar Project (66821) |
Plant Address | 664 County Road 116A, Buckholts, TX 76569 |
Utility | Ben Milam Solar 3 LLC (65782) |
Latitude, Longitude | 30.96022, -97.12452 |
Generation Dates on File | Aug 2024 to Apr 2025 |
Initial Operation Date | August 2024 |
Annual Generation | 396.7 GWh |
Fuel Types | Solar |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | TRE |
Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
Grid Voltage | 345.00 kV |
Energy Storage | No |
Generator ORN3 Details Operating August 2024
Technology | Solar Photovoltaic |
---|---|
Prime Mover | Photovoltaic |
Ownership | Single Owner |
Nameplate Capacity | 250 MW |
Summer Capacity | 250 MW |
Winter Capacity | 250 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | August 2024 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Solar |
Solar Details | |
Single Axis Tracking | Yes |
---|---|
DC Net Capacity | 325 MW |
Thin Film CDTE | Yes |
Net Metering Agreement | No |
Virtual Net Metering Agreement | No |
Orion III Solar Project Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#114 | Scarlet Solar (CA) | Fresno, CA | 401.4 GWh |
#115 | Sun Streams, LLC | Arlington, AZ | 407.2 GWh |
#116 | Castle Gap Solar Hybrid | McCarney, TX | 405.7 GWh |
#117 | Big Plain Solar, LLC | London, OH | 405.8 GWh |
#118 | Tres Bahias | Port Lavaca, TX | 404.3 GWh |
#119 | Brazoria County Solar Project (Danciger) | Damon, TX | 402.8 GWh |
#120 | Mesquite Solar 1 | Tonopah, AZ | 401.4 GWh |
#121 | Springbok Solar Farm 2 | Cantil, CA | 399.0 GWh |
#122 | Samson Solar Energy | Cunningham, TX | 399.0 GWh |
#123 | North Rosamond Solar LLC | Rosamond, CA | 398.4 GWh |
#125 | Dry Lake Solar Energy Center | Moapa, NV | 380.5 GWh |
#126 | Buena Vista Energy Center | Chaparral, NM | 391.1 GWh |
#127 | Mustang Two | Lemoore, CA | 391.9 GWh |
#128 | Chestnut | Lemoore, CA | 387.2 GWh |
#129 | Shakes Solar | Carrizo Springs, TX | 389.8 GWh |
#130 | Greasewood II LLC | Girvin, TX | 386.7 GWh |
#131 | Buckthorn Westex | Ft. Stockton, TX | 382.7 GWh |
#132 | Crooked Lake Solar, LLC | Blytheville, AR | 382.2 GWh |
#133 | Holstein 1 Solar Farm | Wingate, TX | 381.4 GWh |
#134 | Madison Fields Solar Project, LLC | Irwin, OH | 381.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Orion III Solar Project.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
AbbVie Waco | Waco, TX | 811.0 MWh | 36.8 mi |
Big Elm Solar | Troy, TX | 138.0 GWh | 13.6 mi |
BPL Crown Solar LLC | Chilton, TX | 199.9 GWh | 26.8 mi |
BPL Sol Solar LLC | Chilton, TX | 195.5 GWh | 26.8 mi |
BT Jungmann | Buckholts, TX | 22.1 GWh | 5.6 mi |
Eddy II | Eddy, TX | 16.6 GWh | 24.2 mi |
Five Wells Solar Center - Hybrid | Rogers, TX | 734.3 GWh | 8.4 mi |
Gransolar Texas One, LLC | Thorndale, TX | 24.0 GWh | 25 mi |
Griffin Solar | Robinson, TX | 9.2 GWh | 35.5 mi |
HEB00182 | Temple, TX | 217.0 MWh | 16.5 mi |
HEBTEMDistCenter | Temple, TX | 618.0 MWh | 19.3 mi |
HEBTEMDistCenter1B | Temple, TX | 309.0 MWh | 19.3 mi |
HEBTEMDistCenter2A | Temple, TX | 309.0 MWh | 19.3 mi |
Major Oak Power | Bremond, TX | 2.3 TWh | 27 mi |
Marlin Solar | Marlin, TX | 9.9 GWh | 26.9 mi |
Orion I Solar Project | Burlington, TX | 323.5 GWh | 7.7 mi |
Orion II Solar Project | Rosebud, TX | 277.5 GWh | 12.2 mi |
Temple Power Station | Temple, TX | 7.0 TWh | 13.2 mi |
WAL1232 | Belton, TX | 237.0 MWh | 21.4 mi |
WAL6929 | Temple, TX | 271.0 MWh | 20.2 mi |