| Lake Elsinore Canopies - Lakeside HS | Standard Solar | Lake Elsinore, CA | 2 GWh | Feb 2022 | Dec 2024 |
Solar
|
| Stage Gulch Solar | Stage Gulch Solar, LLC | Petaluma, CA | 1 GWh | Mar 2018 | Dec 2024 |
Solar
|
| Vallecitos Water District | SSA Solar of CA 5, LLC | San Marcos, CA | 3 GWh | Aug 2021 | Dec 2024 |
Solar
|
| San Antonio West Solar Rooftop | SS San Antonio West LLC | Chino, CA | 2 GWh | Jul 2012 | Dec 2024 |
Solar
|
| Santa Rita Jail Fuel Cell | SRJFC, LLC | Dublin, CA | 9 GWh | Nov 2016 | Dec 2024 |
Natural Gas
|
| Atwell Island | SPS Atwell Island LLC | Alpaugh, CA | 33 GWh | Feb 2013 | Dec 2024 |
Solar
|
| RE Tranquillity | Southern Power Co | Cantua Creek, CA | 491 GWh | Jun 2016 | Dec 2024 |
Solar
|
| Henrietta Solar Project | Southern Power Co | Lemoore, CA | 218 GWh | Jul 2016 | Dec 2024 |
Solar
|
| North Star Solar | Southern Power Co | Mendota, CA | 132 GWh | May 2015 | Dec 2024 |
Solar
|
| Lost Hills/Blackwell | Southern Power Co | Lost Hills, CA | 81 GWh | Mar 2015 | Dec 2024 |
Solar
|
| Stateline Solar | Southern Power Co | Nipton, CA | 620 GWh | Nov 2015 | Dec 2024 |
Solar
|
| Solar Gen 2 Solar Facility | Southern Power Co | Calipatria, CA | 364 GWh | Oct 2014 | Dec 2024 |
Solar
|
| Campo Verde Solar | Southern Power Co | El Centro, CA | 295 GWh | Sep 2013 | Dec 2024 |
Solar
|
| Adobe Solar | Southern Power Co | Arvin, CA | 40 GWh | Apr 2014 | Dec 2024 |
Solar
|
| Morelos del Sol | Southern Power Co | Lost Hills, CA | 30 GWh | Oct 2015 | Dec 2024 |
Solar
|
| RE Garland A | Southern Power Co | Rosamond, CA | 58 GWh | Aug 2016 | Dec 2024 |
Solar
|
| RE Garland | Southern Power Co | Rosamond, CA | 483 GWh | Oct 2016 | Dec 2024 |
Solar
|
| Gaskell West 1 Solar Facility | Southern Power Co | Lancaster, CA | 53 GWh | Feb 2018 | Dec 2024 |
Solar
|
| Rush Creek | Southern California Edison Co | June lake, CA | 43 GWh | Sep 1916 | Dec 2024 |
Water
|
| Mill Creek 3 | Southern California Edison Co | Mill Creek, CA | 11 GWh | Feb 1903 | Dec 2024 |
Water
|
| Bishop Creek 4 | Southern California Edison Co | Bishop, CA | 40 GWh | Aug 1905 | Dec 2024 |
Water
|
| J S Eastwood | Southern California Edison Co | Shaver Lake, CA | 84 GWh | Nov 1987 | Sep 2025 |
Water
|
| Bishop Creek 5 | Southern California Edison Co | Bishop, CA | 17 GWh | May 1919 | Sep 2024 |
Water
|
| Bishop Creek 6 | Southern California Edison Co | Bishop, CA | 10 GWh | Feb 1913 | Dec 2024 |
Water
|
| Fontana | Southern California Edison Co | Rialto, CA | 9 GWh | Nov 1917 | Dec 2024 |
Water
|
| Portal | Southern California Edison Co | Lakeshore, CA | 19 GWh | Nov 1956 | Dec 2024 |
Water
|
| Poole | Southern California Edison Co | Lee Vining, CA | 23 GWh | Apr 1924 | Dec 2024 |
Water
|
| Big Creek 8 | Southern California Edison Co | Auberry, CA | 174 GWh | Jul 1921 | Dec 2024 |
Water
|
| Pebbly Beach Generating Station Hybrid | Southern California Edison Co | Avalon, CA | 29 GWh | Jun 1958 | Sep 2025 |
Distillate Fuel Oil : 94.5%
Gaseous Propane : 5.5%
|
| Bishop Creek 3 | Southern California Edison Co | Bishop, CA | 20 GWh | May 1913 | Dec 2024 |
Water
|
| Bishop Creek 2 | Southern California Edison Co | Bishop, CA | 16 GWh | Oct 1908 | Dec 2024 |
Water
|
| Big Creek 2A | Southern California Edison Co | Auberry, CA | 211 GWh | Jul 1928 | Sep 2025 |
Water
|
| Mountainview Generating Station | Southern California Edison Co | Redlands, CA | 2 TWh | Nov 2005 | Sep 2025 |
Natural Gas
|
| Kaweah 2 | Southern California Edison Co | Three Rivers, CA | 1 GWh | Aug 1929 | Dec 2024 |
Water
|
| Big Creek 1 | Southern California Edison Co | Big Creek, CA | 405 GWh | Oct 1913 | Dec 2024 |
Water
|
| Big Creek 2 | Southern California Edison Co | Auberry, CA | 355 GWh | Nov 1913 | Dec 2024 |
Water
|
| Big Creek 3 | Southern California Edison Co | Auberry, CA | 598 GWh | Aug 1923 | Sep 2025 |
Water
|
| Big Creek 4 | Southern California Edison Co | North Fork, CA | 322 GWh | May 1951 | Sep 2025 |
Water
|
| Grapeland Hybrid | Southern California Edison Co | Rancho Cucamonga, CA | 4 GWh | Aug 2007 | Dec 2024 |
Natural Gas
|
| McGrath Peaker | Southern California Edison Co | Oxnard, CA | 7 GWh | Oct 2012 | Dec 2024 |
Natural Gas
|
| Mira Loma Peaker | Southern California Edison Co | Ontario, CA | 11 GWh | Aug 2007 | Dec 2024 |
Natural Gas
|
| Kern River 3 | Southern California Edison Co | Kernville, CA | 143 GWh | Feb 1921 | Dec 2024 |
Water
|
| Barre Peaker | Southern California Edison Co | Stanton, CA | 13 GWh | Aug 2007 | Nov 2024 |
Natural Gas
|
| Center Hybrid | Southern California Edison Co | Norwalk, CA | 7 GWh | Aug 2007 | Dec 2024 |
Natural Gas
|
| Mammoth Pool | Southern California Edison Co | North Fork, CA | 383 GWh | Feb 1960 | Sep 2025 |
Water
|
| Lundy | Southern California Edison Co | Lee Vining, CA | 7 GWh | Nov 1911 | Dec 2024 |
Water
|
| Solar Photovoltaic Project #42 | Southern California Edison Co | Tulare, CA | 8 GWh | Oct 2012 | Dec 2024 |
Solar
|
| Kern River 1 | Southern California Edison Co | Bakersfield, CA | 192 GWh | Apr 1907 | Dec 2024 |
Water
|
| Sacramento Municipal Util Dist | South Sutter Water District | Sacramento, CA | 16 GWh | Jan 1985 | Mar 2024 |
Water
|
| Robert O Schulz Solar Farm | South San Joaquin Irr District | Oakdale, CA | 2 GWh | Apr 2008 | Dec 2024 |
Solar
|
| Woodleaf | South Feather Water and Power Agency | Forbestown, CA | 194 GWh | Oct 1963 | Dec 2024 |
Water
|
| Forbestown | South Feather Water and Power Agency | Forbestown, CA | 129 GWh | Sep 1963 | Dec 2024 |
Water
|
| Kelly Ridge | South Feather Water and Power Agency | Oroville, CA | 67 GWh | Aug 1963 | Dec 2024 |
Water
|
| Sly Creek | South Feather Water and Power Agency | Forbestown, CA | 31 GWh | Jun 1983 | Dec 2024 |
Water
|
| Blackjack Solar | South County Packing | King City, CA | 9 GWh | Nov 2020 | Dec 2024 |
Solar
|
| Soscol Ferry Solar | Soscol Ferry Solar | Napa, CA | 5 GWh | Nov 2020 | Dec 2024 |
Solar
|
| Santa Rosa Junior College Petaluma Solar | Sonoma County Junior College District | Petaluma, CA | 2 GWh | Jun 2018 | Dec 2023 |
Solar
|
| 2097 Helton Solar Project | Solarenewal LLC | Merced, CA | 2 GWh | Mar 2014 | Dec 2024 |
Solar
|
| 2127 Harris Solar Project | Solarenewal LLC | Live Oak, CA | 1 GWh | Mar 2014 | Dec 2024 |
Solar
|
| 2081 Terzian Solar Project | Solarenewal LLC | Reedley, CA | 2 GWh | Jan 2014 | Dec 2024 |
Solar
|
| Amazon SAN3 Solar Project | Solar Star Prime 4 LLC | San Diego, CA | 6 GWh | Apr 2024 | Dec 2024 |
Solar
|
| Amazon Bakersfield 1 Solar Project | Solar Star Prime 3, LLC | Bakersfiled, CA | 8 GWh | Dec 2023 | Dec 2024 |
Solar
|
| Orange Coast College PH2 Solar Project | Solar Star Coastal Pirate, LLC | Costa Mesa, CA | 4 GWh | Apr 2022 | Dec 2024 |
Solar
|
| UC Davis South Campus | Solar Star California XXXII, LLC | Davis, CA | 17 GWh | Feb 2015 | Dec 2024 |
Solar
|
| Tequesquite Landfill Solar PV Project | Solar Star California XXXI, LLC | Riverside, CA | 13 GWh | Sep 2015 | Dec 2024 |
Solar
|
| Solar Star 2 | Solar Star California XX, LLC | Rosamond, CA | 714 GWh | Feb 2014 | Sep 2025 |
Solar
|
| Solar Star 1 | Solar Star California XIX, LLC | Rosamond, CA | 898 GWh | Feb 2014 | Sep 2025 |
Solar
|
| County of San Diego COC Hybrid | Solar Star California LXXVIII, LLC | San Diego, CA | 3 GWh | Jun 2020 | Dec 2024 |
Solar
|
| Solar Oasis LLC | Solar Oasis, LLC | Palmdale, CA | 51 GWh | Dec 2015 | Dec 2024 |
Solar
|
| Monticello Dam | Solano Irrigation District | Winters, CA | 36 GWh | May 1983 | Dec 2024 |
Water
|
| Solano County Cogen Plant | Solano County | Fairfield, CA | 8 GWh | May 1989 | Dec 2024 |
Natural Gas
|
| Bob Wiley Detention Center | SoCore Energy LLC | Visalia, CA | 3 GWh | Aug 2020 | Dec 2024 |
Solar
|
| Civic Center East | SoCore Energy LLC | Visalia, CA | 3 GWh | Nov 2020 | Dec 2024 |
Solar
|
| Tulare Akers Professional Center | SoCore Energy LLC | Visalia, CA | 2 GWh | Oct 2019 | Dec 2024 |
Solar
|
| Government Plaza Solar | SoCore Energy LLC | Visalia, CA | 2 GWh | Oct 2020 | Dec 2024 |
Solar
|
| North Juvenile Detention Center Solar | SoCore Energy LLC | Visalia, CA | 2 GWh | Oct 2019 | Dec 2024 |
Solar
|
| South County Detention Center Solar | SoCore Energy LLC | Porterville, CA | 2 GWh | Oct 2019 | Dec 2024 |
Solar
|
| Soboba Community Solar Project | Soboba Band of Luiseno Indians | San Jacinto, CA | 3 GWh | Jul 2016 | Dec 2024 |
Solar
|
| Ponderosa Bailey Creek | Snow Mountain Hydro LLC | Manton, CA | 3 GWh | Feb 1990 | Dec 2024 |
Water
|
| Lost Creek I | Snow Mountain Hydro LLC | Burney, CA | 5 GWh | Nov 1989 | Dec 2024 |
Water
|
| Cove Hydroelectric | Snow Mountain Hydro LLC | Burney, CA | 18 GWh | Jan 1990 | Dec 2024 |
Water
|
| Burney Creek | Snow Mountain Hydro LLC | Burney, CA | 9 GWh | Feb 1990 | Dec 2024 |
Water
|
| Niagara Bottling - Rialto | SkyHigh 2 Solar | Rialto, CA | 8 GWh | Nov 2021 | Dec 2024 |
Solar
|
| EMWD - San Jacinto RWRF NEM | SkyHigh 2 Solar | San Jacinto, CA | 10 GWh | Jun 2021 | Dec 2024 |
Solar
|
| El Dorado County | SkyHigh 2 Solar | Placerville, CA | 3 GWh | Feb 2021 | Dec 2024 |
Solar
|
| EMWD - Sun City RWRF | SkyHigh 2 Solar | Menifee, CA | 4 GWh | Jun 2021 | Dec 2024 |
Solar
|
| EMWD - San Jacinto RES BCT | SkyHigh 2 Solar | San Jacinto, CA | 3 GWh | Apr 2022 | Dec 2024 |
Solar
|
| CSU San Jose State University | SkyHigh 2 Solar | San Jose, CA | 2 GWh | Nov 2021 | Dec 2024 |
Solar
|
| EMWD - Moreno Valley RWRF | SkyHigh 2 Solar | Moreno Valley, CA | 6 GWh | Jun 2021 | Dec 2024 |
Solar
|
| California State Univ at Channel Islands | SkyHigh 2 Solar | Camarillo, CA | 8 GWh | Nov 2021 | Dec 2024 |
Solar
|
| Firestone Walker Brewery - Phase 1 | SkyHigh 2 Solar | Paso Robles, CA | 3 GWh | Oct 2020 | Dec 2024 |
Solar
|
| EMWD - Perris Valley RWRF | SkyHigh 2 Solar | Perris, CA | 6 GWh | Jun 2021 | Dec 2024 |
Solar
|
| Sky River Wind Energy Center | Sky River Wind LLC | Tehachapi, CA | 245 GWh | Jan 1991 | Dec 2024 |
Wind
|
| Silver State Solar Power South | Silver State Solar Power South, LLC | Primm Valley, NV | 673 GWh | Oct 2015 | Sep 2025 |
Solar
|
| Silveira Ranch Road Solar | Silveira Ranch Road Solar | Novato, CA | 4 GWh | Feb 2021 | Dec 2024 |
Solar
|
| Silicon Valley Clean Water | Silicon Valley Clean Water | Redwood City, CA | 7 GWh | Feb 2015 | Dec 2024 |
Other Biomass Gas : 71.4%
Natural Gas : 28.6%
|
| Signal Hill West Unit | Signal Hill Petroleum, Inc | Signal Hill, CA | 40 GWh | Jun 2004 | Sep 2025 |
Other Gas
|
| Sierra Pacific Burney Facility | Sierra Pacific Industries | Burney, CA | 96 GWh | Sep 1986 | Dec 2024 |
Wood/Wood Waste Solids
|
| Sierra Pacific Lincoln Facility | Sierra Pacific Industries | Lincoln, CA | 94 GWh | Feb 2004 | Dec 2024 |
Wood/Wood Waste Solids
|
| SPI Anderson 2 | Sierra Pacific Industries | Anderson, CA | 138 GWh | Jul 2015 | Oct 2024 |
Wood/Wood Waste Solids : 99.0%
Natural Gas : 1.0%
|