Big Creek 3
47369 Lower Redinger Road, Auberry, CA 93602Plant Summary Information
Big Creek 3 is ranked #6 out of 206 hydroelectric power plants in California in terms of total annual net electricity generation.
Big Creek 3 is comprised of 5 generators and generated 172.4 GWh during the 3-month period between January 2025 to April 2025.
Plant Name | Big Creek 3 |
---|---|
Utility Name | Southern California Edison Co |
Location | Fresno County, CA |
Initial Operation Date | September 1923 |
Last Update | Apr 2025 |
Annual Generation | 593.2 GWh |
Annual Consumption | 2.3 M MMBtu |
Ranked #1,141 out of 12,299 Power Plants Nationwide | |
Ranked #64 out of 1,323 Water Power Plants Nationwide | |
Ranked #63 out of 1,566 California Power Plants | |
Ranked #6 out of 206 California Water Power Plants | |
Fuel Types | Water |
Map of Big Creek 3
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Big Creek 3.
Monthly Net Generation for Big Creek 3
Big Creek 3 Details
Summary Information | |
---|---|
Plant Name | Big Creek 3 (319) |
Plant Address | 47369 Lower Redinger Road, Auberry, CA 93602 |
Utility | Southern California Edison Co (17609) |
Latitude, Longitude | 37.14852, -119.38662 |
Generation Dates on File | Jan 2001 to Apr 2025 |
Initial Operation Date | September 1923 |
Annual Generation | 593.2 GWh |
Fuel Types | Water |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | California Independent System Operator (CISO) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | San Joaquin River |
Ash Impoundment | |
Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
Grid Voltage | 220.00 kV |
Energy Storage | No |
Generator 1 Details Operating October 1923
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 34 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 34 MW |
Winter Capacity | 34 MW |
Minimum Load | 3.4 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | October 1923 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Generator 3 Details Operating October 1923
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 34 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 33 MW |
Winter Capacity | 33 MW |
Minimum Load | 3.4 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | October 1923 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Generator 2 Details Operating September 1923
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 34 MW |
Nameplate Power Factor | 1 |
Summer Capacity | 34 MW |
Winter Capacity | 34 MW |
Minimum Load | 3.4 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | September 1923 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Time From Cold Shutdown To Full Load | 10M |
Generator 4 Details Operating April 1948
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 36 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 36 MW |
Winter Capacity | 36 MW |
Minimum Load | 3.6 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | April 1948 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Generator 5 Details Operating February 1980
Technology | Conventional Hydroelectric |
---|---|
Prime Mover | Hydroelectric Turbine |
Ownership | Single Owner |
Nameplate Capacity | 36.5 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 36.5 MW |
Winter Capacity | 36.5 MW |
Minimum Load | 3.6 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | February 1980 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Water |
Solid Fuel Gasification | No |
Time From Cold Shutdown To Full Load | 10M |
Big Creek 3 Plant Owners
Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#54 | Palisades Dam | Palisades, ID | 744.4 GWh |
#55 | Fort Loudoun | Lenoir City, TN | 732.1 GWh |
#56 | Hungry Horse | Columbia Falls, MT | 730.3 GWh |
#57 | Wolf Creek | Jamestown, KY | 723.8 GWh |
#58 | Gavins Point | Crofton, NE | 712.6 GWh |
#59 | Gorge | Rockport, WA | 700.0 GWh |
#60 | Chickamauga | Chattanooga, TN | 688.9 GWh |
#61 | J Strom Thurmond | Clarks Hill, SC | 650.7 GWh |
#62 | Bull Shoals | Mountain Home, AR | 647.3 GWh |
#63 | Rock Creek | Storrie, CA | 604.5 GWh |
#65 | Barkley | Kuttawa, KY | 590.6 GWh |
#66 | Mayfield | Silver Creek, WA | 576.4 GWh |
#67 | Great Lakes Hydro America - ME | Millinocket, ME | 570.9 GWh |
#68 | Swift 1 | Cougar, WA | 553.9 GWh |
#69 | Trinity | Weaverville, CA | 552.7 GWh |
#70 | Calderwood | Tallassee, TN | 549.2 GWh |
#71 | Folsom | Folsom, CA | 546.4 GWh |
#72 | Pit 5 | Big Bend, CA | 527.8 GWh |
#73 | Dardanelle | Dardanelle, AR | 517.3 GWh |
#74 | Fairfield Pumped Storage | Jenkinsville, SC | 497.5 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Big Creek 3.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
A G Wishon | North Fork, CA | 21.6 GWh | 6.5 mi |
Balch 1 | Balch Camp, CA | 138.8 GWh | 23.4 mi |
Balch 2 | Balch Camp, CA | 443.4 GWh | 23.4 mi |
Big Creek 1 | Big Creek, CA | 405.3 GWh | 9 mi |
Big Creek 2 | Auberry, CA | 355.2 GWh | 5.6 mi |
Big Creek 2A | Auberry, CA | 283.1 GWh | 5.7 mi |
Big Creek 4 | North Fork, CA | 353.2 GWh | 5.7 mi |
Big Creek 8 | Auberry, CA | 173.8 GWh | 5.3 mi |
Clovis East High School | Clovis, CA | 1.5 GWh | 27.9 mi |
Clovis North High School | Fresno, CA | 1.5 GWh | 26.3 mi |
Friant Hydro Facility | Friant, CA | 59.8 GWh | 20.3 mi |
Haas | Balch Camp, CA | 427.9 GWh | 25.3 mi |
J S Eastwood | Shaver Lake, CA | 1.3 GWh | 7.2 mi |
Kerckhoff 2 | Auberry, CA | 407.9 GWh | 10.8 mi |
Kings River PH | Balch Camp, CA | 106.9 GWh | 21.9 mi |
Kings River Syphon | Sanger, CA | 325.0 MWh | 26.7 mi |
Mammoth Pool | North Fork, CA | 421.5 GWh | 5.6 mi |
Pine Flat | Piedra, CA | 448.8 GWh | 22.1 mi |
Portal | Lakeshore, CA | 18.7 GWh | 14.6 mi |
SCCCD - Clovis Community College | Fresno, CA | 2.0 GWh | 26.3 mi |