2127 Harris Solar Project

11160 Hampton Road, Live Oak, CA 95953

Plant Summary Information

2127 Harris Solar Project is ranked #866 out of 917 solar farms in California in terms of total annual net electricity generation.

2127 Harris Solar Project generated 140.0 MWh during the 3-month period between September 2025 to December 2025.

Plant Name2127 Harris Solar Project
Utility NameSolarenewal LLC
LocationButte County, CA
Initial Operation DateApril 2014
Last Update Dec 2025
Annual Generation 885.0 MWh
Annual Consumption 3.1 k MMBtu
Ranked #12,211 out of 13,301 Power Plants Nationwide
Ranked #6,895 out of 7,209 Solar Power Plants Nationwide
Ranked #1,569 out of 1,641 California Power Plants
Ranked #866 out of 917 California Solar Power Plants
Fuel Types Solar
Previous Operator Pristine Sun LLC (2013 to 2016)
Solarenewal LLC (2017 to 2025)

Map of 2127 Harris Solar Project

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for 2127 Harris Solar Project.

Create Your Account Today

Monthly Net Generation for 2127 Harris Solar Project

Monthly Plant Fuel Consumption for 2127 Harris Solar Project

2127 Harris Solar Project Details

Summary Information
Plant Name2127 Harris Solar Project (58919)
Plant Address11160 Hampton Road, Live Oak, CA 95953
UtilitySolarenewal LLC (61315)
Latitude, Longitude39.29167, -121.66972
Generation Dates on FileApr 2014 to Dec 2025
Initial Operation DateApril 2014
Annual Generation 885.0 MWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator (CISO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment No
Transmission / Distribution OwnerPacific Gas & Electric Co (14328) CA
Grid Voltage 12.00 kV
Energy StorageNo

Generator 2127 Details Operating April 2014

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipSingle Owner
Nameplate Capacity1.3 MW
Summer Capacity1.3 MW
Winter Capacity1.3 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateApril 2014
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Solid Fuel Gasification No
Carbon Capture TechnologyNo
Time From Cold Shutdown To Full Load1H
Solar Details
Single Axis TrackingYes
Azimuth Angle90
DC Net Capacity1.4 MW
Crystalline SiliconYes
Net Metering AgreementNo
Virtual Net Metering AgreementNo

2127 Harris Solar Project Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#6885Foster Clean Power BArcata, CA901.0 MWh
#6886Kelso Community Solar IIEssex, MD901.0 MWh
#6887PCIP SolarTimberlake, NC898.0 MWh
#6888Atlanta Falcons SolarAtlanta, GA896.0 MWh
#6889StockbridgeMunnsville, NY892.0 MWh
#6890Delano Land 1Delano, CA892.0 MWh
#6891Oneida EastHolland Patent, NY891.0 MWh
#6892HCE Moore IAberdeen, NC886.0 MWh
#6893Hamlet Solar Energy StorageHamlet, NC867.0 MWh
#6894Manchester Community College NorthGreat Path, CT885.0 MWh
#6896IMPA Richmond Solar ParkRichmond, IN884.0 MWh
#6897Tioga Solar Morris County 1 LLCMorristown, NJ876.0 MWh
#6898Bishop Ranch - BR 8-QSan Ramon, CA871.0 MWh
#6899Wilson Solar (MA)Spencer, MA870.0 MWh
#6900State Route 64N Community Solar FarmEast Bloomfield, NY870.0 MWh
#6901East WindsorEast Windsor, CT869.0 MWh
#6902NL IL - Maples RoadDixon, IL867.0 MWh
#6903DIVOCSG 14 LLCWabasha, MN862.0 MWh
#6904SCV Water - Gladbach Water Treatment Plant Phases I and IISanta Clara, CA858.0 MWh
#6905Sonora 1Jamestown, CA858.0 MWh

Nearby Power Plants

Below are closest 20 power plants surrounding 2127 Harris Solar Project.

Plant NamePlant LocationAnnual GenerationDistance
Abel Road BioenergyWilliams, CA22.7 GWh26.1 mi
Butte College Main Campus SolarOroville, CA6.6 GWh24.7 mi
ColgateDobbins, CA1.3 TWh25.7 mi
Edward C HyattOroville, CA2.2 TWh19.8 mi
Feather River Energy CenterYuba City, CA35.4 GWh13 mi
G2 Energy Ostrom Road LLCWheatland, CA27.7 GWh20.9 mi
Greenleaf 1Yuba City, CA2.6 GWh16.6 mi
Greenleaf 2 Power PlantYuba City, CA63.8 GWh10.8 mi
Gridley MainGridley, CA1.4 GWh5.7 mi
Gridley Main TwoGridley, CA3.6 GWh5.7 mi
Kelly RidgeOroville, CA69.1 GWh19.1 mi
Narrows 2Browns Valley, CA181.2 GWh21.7 mi
Narrows PHGrass Valley, CA73.4 GWh21.6 mi
Oroville Cogeneration, LLCOroville, CA115.6 MWh15 mi
Sacramento Municipal Util DistSacramento, CA14.2 GWh25.3 mi
Sutter Energy CenterYuba City, CA1.7 TWh16.5 mi
ThermalitoOroville, CA318.3 GWh15.6 mi
Thermalito Diverson DamOroville, CA10.3 GWh17.7 mi
Yuba City Cogen PartnersYuba City, CA14.7 GWh10.8 mi
Yuba City Energy CenterYuba City, CA23.4 GWh10.7 mi