Rush Creek
June Lake Loop Sierra Ntnl For, June lake, CA 93529Plant Summary Information
Rush Creek is ranked #101 out of 207 hydroelectric power plants in California in terms of total annual net electricity generation.
Rush Creek is comprised of 2 generators and generated 2.2 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Rush Creek |
|---|---|
| Utility Name | Southern California Edison Co |
| Location | Mono County, CA |
| Initial Operation Date | October 1916 |
| Last Update | Dec 2025 |
| Annual Generation | 30.0 GWh |
| Annual Consumption | 105.3 k MMBtu |
| Ranked #4,866 out of 13,081 Power Plants Nationwide | |
| Ranked #599 out of 1,311 Water Power Plants Nationwide | |
| Ranked #604 out of 1,606 California Power Plants | |
| Ranked #101 out of 207 California Water Power Plants | |
| Fuel Types | Water |
Map of Rush Creek
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Rush Creek.
Monthly Net Generation for Rush Creek
Monthly Plant Fuel Consumption for Rush Creek
Rush Creek Details
| Summary Information | |
|---|---|
| Plant Name | Rush Creek (357) |
| Plant Address | June Lake Loop Sierra Ntnl For, June lake, CA 93529 |
| Utility | Southern California Edison Co (17609) |
| Latitude, Longitude | 37.76695, -119.12328 |
| Generation Dates on File | Jan 2001 to Dec 2025 |
| Initial Operation Date | October 1916 |
| Annual Generation | 30.0 GWh |
| Fuel Types | Water |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | Rush Creek |
| Ash Impoundment | |
| Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
| Grid Voltage | 115.00 kV |
| Energy Storage | No |
Generator 1 Details Operating October 1916
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 5.9 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 5.9 MW |
| Winter Capacity | 5.9 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | October 1916 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
Generator 2 Details Operating December 1917
| Technology | Conventional Hydroelectric |
|---|---|
| Prime Mover | Hydroelectric Turbine |
| Ownership | Single Owner |
| Nameplate Capacity | 7.2 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 5.5 MW |
| Winter Capacity | 5.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 1917 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Water |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 10M |
Rush Creek Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Water.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #589 | Tiber Dam Hydroelectric Plant | Chester, MT | 31.2 GWh |
| #590 | Cedar Falls (WI) | Menomonie, WI | 30.9 GWh |
| #591 | Salmon Creek 1 | Juneau, AK | 30.9 GWh |
| #592 | Coleman PH | Anderson, CA | 30.9 GWh |
| #593 | Minetto | Minetto, NY | 30.8 GWh |
| #594 | Chandler | Benton City, WA | 30.6 GWh |
| #595 | Higley | Colton, NY | 30.5 GWh |
| #596 | Clearwater 2 | Idleyld Park, OR | 30.5 GWh |
| #597 | Sartell Dam | Sartell, MN | 30.4 GWh |
| #598 | SAF Hydroelectric LLC | Minneapolis, MN | 30.2 GWh |
| #600 | Wise | Auburn, CA | 29.9 GWh |
| #601 | Aziscohos Hydroelectric Project | Wilson Mills, ME | 29.8 GWh |
| #602 | Biron | Biron, WI | 29.6 GWh |
| #603 | Norway (MI) | Norway, MI | 29.5 GWh |
| #604 | Croton | Newaygo, MI | 29.5 GWh |
| #605 | Deerfield 2 | Conway, MA | 29.4 GWh |
| #606 | Michigamme Falls | Crystal Falls, MI | 29.4 GWh |
| #607 | Buchanan Dam (TX) | Buchanan Dam, TX | 29.2 GWh |
| #608 | Green Mountain | Kremmling, CO | 28.5 GWh |
| #609 | Eagle | Croghan, NY | 28.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Rush Creek.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Big Creek 1 | Big Creek, CA | 409.1 GWh | 39.4 mi |
| Big Creek 2 | Auberry, CA | 376.6 GWh | 40.4 mi |
| Big Creek 2A | Auberry, CA | 273.7 GWh | 40.4 mi |
| Big Creek 3 | Auberry, CA | 747.3 GWh | 45.1 mi |
| Big Creek 8 | Auberry, CA | 151.8 GWh | 40.1 mi |
| Bishop Creek 2 | Bishop, CA | 13.2 GWh | 45.5 mi |
| Bishop Creek 3 | Bishop, CA | 23.9 GWh | 45.6 mi |
| CD4 | Mammoth Lakes, CA | 236.3 GWh | 14.1 mi |
| Control Gorge | Bishop, CA | 46.4 GWh | 38.4 mi |
| J S Eastwood | Shaver Lake, CA | 130.6 GWh | 43.4 mi |
| Lundy | Lee Vining, CA | 6.7 GWh | 19.2 mi |
| Mammoth G1 | Mammoth lakes, CA | 43.6 GWh | 14.2 mi |
| Mammoth G2 | Mammoth Lakes, CA | 83.8 GWh | 14.4 mi |
| Mammoth G3 | Mammoth Lakes, CA | 75.3 GWh | 14.4 mi |
| Mammoth Pool | North Fork, CA | 568.6 GWh | 39.6 mi |
| Middle Gorge | Bishop, CA | 48.0 GWh | 35.1 mi |
| Pleasant Valley Hydro | Bishop, CA | 6.3 GWh | 40.9 mi |
| Poole | Lee Vining, CA | 22.3 GWh | 13.3 mi |
| Portal | Lakeshore, CA | 26.2 GWh | 35.3 mi |
| Upper Gorge | Bishop, CA | 51.9 GWh | 32.9 mi |