High Lonesome Wind Power, LLC Hybrid
2731 W US Hwy 67, Rankin, TX 79778Plant Summary Information
High Lonesome Wind Power, LLC Hybrid is ranked #27 out of 1,366 wind farms nationwide in terms of total annual net electricity generation.
High Lonesome Wind Power, LLC Hybrid generated 308.4 GWh during the 3-month period between July 2025 to October 2025.
| Plant Name | High Lonesome Wind Power, LLC Hybrid |
|---|---|
| Utility Name | High Lonesome Wind Power, LLC |
| Location | Upton County, TX |
| Initial Operation Date | July 2021 |
| Last Update | Oct 2025 |
| Annual Generation | 1.2 TWh |
| Annual Consumption | 4.5 M MMBtu |
| Ranked #655 out of 12,553 Power Plants Nationwide | |
| Ranked #27 out of 1,366 Wind Power Plants Nationwide | |
| Ranked #99 out of 804 Texas Power Plants | |
| Ranked #11 out of 226 Texas Wind Power Plants | |
| Fuel Types | Wind |
Map of High Lonesome Wind Power, LLC Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for High Lonesome Wind Power, LLC Hybrid.
Monthly Net Generation for High Lonesome Wind Power, LLC Hybrid
High Lonesome Wind Power, LLC Hybrid Details
| Summary Information | |
|---|---|
| Plant Name | High Lonesome Wind Power, LLC Hybrid (62562) |
| Plant Address | 2731 W US Hwy 67, Rankin, TX 79778 |
| Utility | High Lonesome Wind Power, LLC (62046) |
| Latitude, Longitude | 31.17165, -101.88115 |
| Generation Dates on File | Sep 2020 to Oct 2025 |
| Initial Operation Date | July 2021 |
| Annual Generation | 1.2 TWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | 22-147-000 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Lower Colorado River Authority (11269) |
| Grid Voltage | 345.00 kV |
| Energy Storage | Yes |
Generator BA Details Operating June 2023
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 63.3 MW |
| Summer Capacity | 51 MW |
| Winter Capacity | 51 MW |
| Minimum Load | 1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | June 2023 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 81 |
|---|---|
| Maximum Charge Rate | 51.1 MW |
| Maximum Discharge Rate | 51.1 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 81.3 |
| Storage Enclosure Type | CS |
| Arbitrage | P |
| Frequency Regulation | Yes |
| Voltage Or Reactive Power Support | Yes |
| Direct Support Of Another Unit | No |
| Support T D Asset | No |
Generator HILO Details Operating July 2023
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 449.5 MW |
| Summer Capacity | 449.5 MW |
| Winter Capacity | 449.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | July 2023 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 140 |
| Time From Cold Shutdown To Full Load | 1H |
| Turbine Details | |
| Number Of Turbines | 140 |
|---|---|
| Predominant Turbine Manufacturer | Acciona |
| Predominant Turbine Model Number | AW132/3000 |
| Design Wind Speed | 18 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 398 |
Generator HILO2 Details Operating July 2023
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 50 MW |
| Summer Capacity | 50 MW |
| Winter Capacity | 50 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | July 2023 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 22 |
| Time From Cold Shutdown To Full Load | 1H |
| Turbine Details | |
| Number Of Turbines | 22 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.3-116 |
| Design Wind Speed | 18 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 295 |
High Lonesome Wind Power, LLC Hybrid Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #17 | Grande Prairie Wind Farm | O'Neill, NE | 1.5 TWh |
| #18 | Fowler Ridge Wind Farm LLC | Fowler, IN | 1.5 TWh |
| #19 | Palo Alto Wind Farm | Emmetsburg, IA | 1.4 TWh |
| #20 | TB Flats | Medicine Bow, WY | 1.3 TWh |
| #21 | Clearwater Wind I | Miles City, MT | 1.3 TWh |
| #22 | Beaver Creek Wind | Ogden, IA | 1.3 TWh |
| #23 | North English | Montezuma, IA | 1.3 TWh |
| #24 | Iron Star Wind Project | Dodge City, KS | 1.2 TWh |
| #25 | Santa Rita East | Barnhart, TX | 1.2 TWh |
| #26 | Inertia Wind Project | Haskell, TX | 1.2 TWh |
| #28 | Jordan Creek Wind Farm, LLC | Judyville, IN | 1.2 TWh |
| #29 | Azure Sky Wind Project, LLC Hybrid | Throckmorton, TX | 1.2 TWh |
| #30 | Lacy Creek Wind Energy Center | Sterling City, TX | 1.2 TWh |
| #31 | Santa Rita Wind Energy | Big Lake, TX | 1.2 TWh |
| #32 | Red Cloud Wind LLC | Corona, NM | 1.2 TWh |
| #33 | Ranchero Wind Farm LLC | Iraan, TX | 1.2 TWh |
| #34 | Seven Cowboy Wind Project, LLC | Gage, OK | 1.1 TWh |
| #35 | Tahoka Wind | Tahoka, TX | 1.1 TWh |
| #36 | Sage Draw Wind | Wilson, TX | 1.1 TWh |
| #37 | Torrecillas Wind Energy, LLC | Bruni, TX | 1.1 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding High Lonesome Wind Power, LLC Hybrid.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Alamo 6 | Fort Stockton, TX | 226.6 GWh | 26.2 mi |
| Appaloosa Run Wind | Rankin, TX | 707.5 GWh | 3.1 mi |
| Castle Gap Solar Hybrid | McCarney, TX | 385.5 GWh | 23.8 mi |
| Crane Solar Project | Crane, TX | 407.9 GWh | 26.1 mi |
| Desert Sky | Iraan, TX | 496.7 GWh | 21.3 mi |
| East Pecos Solar | McCamey, TX | 214.7 GWh | 26.5 mi |
| Emerald Grove | Crane, TX | 256.8 GWh | 28.8 mi |
| Greasewood Solar | Fort Stockton, TX | 378.8 GWh | 37.2 mi |
| King Mountain Wind Ranch 1 | McCamey, TX | 555.4 GWh | 21.5 mi |
| Midway Solar - TX | Fort Stockton, TX | 336.0 GWh | 23.6 mi |
| NWP Indian Mesa Wind Farm | Iraan, TX | 205.6 GWh | 25.2 mi |
| Pearl Solar | Fort Stockton, TX | 99.4 GWh | 26.2 mi |
| RE Maplewood | McCamey, TX | 522.5 GWh | 26 mi |
| Roadrunner, LLC Hybrid | McCamey, TX | 1.1 TWh | 18.7 mi |
| Santa Rita Wind Energy | Big Lake, TX | 1.2 TWh | 33.3 mi |
| Shamrock Wind | TBD, TX | 887.3 GWh | 23 mi |
| Upton County Solar | McCamey, TX | 299.6 GWh | 24.7 mi |
| White Mesa Wind | Ozona, TX | 1.8 TWh | 40.8 mi |
| Woodward Mountain I | Girvin, TX | 168.0 GWh | 35 mi |
| Woodward Mountain II | Girvin, TX | 168.0 GWh | 35 mi |