Clearwater Wind I
622 Rock Springs Rd W, Miles City, MT 59301Plant Summary Information
Clearwater Wind I is ranked #25 out of 1,362 wind farms nationwide in terms of total annual net electricity generation.
Clearwater Wind I generated 246.2 GWh during the 3-month period between June 2025 to September 2025.
| Plant Name | Clearwater Wind I |
|---|---|
| Utility Name | Clearwater Energy Resources LLC |
| Location | Rosebud County, MT |
| Initial Operation Date | November 2022 |
| Last Update | Sep 2025 |
| Annual Generation | 1.2 TWh |
| Annual Consumption | 4.6 M MMBtu |
| Ranked #652 out of 12,539 Power Plants Nationwide | |
| Ranked #25 out of 1,362 Wind Power Plants Nationwide | |
| Ranked #4 out of 71 Montana Power Plants | |
| Ranked #1 out of 23 Montana Wind Power Plants | |
| Fuel Types | Wind |
Map of Clearwater Wind I
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Clearwater Wind I.
Monthly Net Generation for Clearwater Wind I
Clearwater Wind I Details
| Summary Information | |
|---|---|
| Plant Name | Clearwater Wind I (65577) |
| Plant Address | 622 Rock Springs Rd W, Miles City, MT 59301 |
| Utility | Clearwater Energy Resources LLC (64896) |
| Latitude, Longitude | 46.81771, -106.37885 |
| Generation Dates on File | Nov 2022 to Sep 2025 |
| Initial Operation Date | November 2022 |
| Annual Generation | 1.2 TWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | Puget Sound Energy (PSEI) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | NorthWestern Energy LLC - (MT) (12825) MT |
| Grid Voltage | 500.00 kV |
| Energy Storage | No |
Generator CW1 Details Operating November 2022
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 365.5 MW |
| Nameplate Power Factor | 0.9 |
| Summer Capacity | 365.5 MW |
| Winter Capacity | 365.5 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | November 2022 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Turbines/Hydrokinetic Buoys | 131 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 131 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.82-127 |
| Design Wind Speed | 20.7 MPH |
| Wind Quality Class | 1 - High Wind |
| Turbine Hub Height Feet | 374 |
Clearwater Wind I Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #15 | Young Wind | Graham, TX | 1.5 TWh |
| #16 | Maverick Creek Wind | Eden, TX | 1.5 TWh |
| #17 | Fowler Ridge Wind Farm LLC | Fowler, IN | 1.5 TWh |
| #18 | Grande Prairie Wind Farm | O'Neill, NE | 1.5 TWh |
| #19 | Palo Alto Wind Farm | Emmetsburg, IA | 1.4 TWh |
| #20 | Beaver Creek Wind | Ogden, IA | 1.3 TWh |
| #21 | TB Flats | Medicine Bow, WY | 1.3 TWh |
| #22 | North English | Montezuma, IA | 1.3 TWh |
| #23 | Iron Star Wind Project | Dodge City, KS | 1.3 TWh |
| #24 | Inertia Wind Project | Haskell, TX | 1.2 TWh |
| #26 | Santa Rita East | Barnhart, TX | 1.2 TWh |
| #27 | Jordan Creek Wind Farm, LLC | Judyville, IN | 1.2 TWh |
| #28 | Azure Sky Wind Project, LLC Hybrid | Throckmorton, TX | 1.2 TWh |
| #29 | High Lonesome Wind Power, LLC Hybrid | Rankin, TX | 1.2 TWh |
| #30 | Santa Rita Wind Energy | Big Lake, TX | 1.2 TWh |
| #31 | Lacy Creek Wind Energy Center | Sterling City, TX | 1.2 TWh |
| #32 | Ranchero Wind Farm LLC | Iraan, TX | 1.2 TWh |
| #33 | Sage Draw Wind | Wilson, TX | 1.2 TWh |
| #34 | Red Cloud Wind LLC | Corona, NM | 1.2 TWh |
| #35 | Tahoka Wind | Tahoka, TX | 1.2 TWh |
Nearby Power Plants
Below are closest 14 power plants surrounding Clearwater Wind I.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Clearwater Wind East | Miles City, MT | 827.6 GWh | 17.9 mi |
| Clearwater Wind II | Miles City, MT | 395.2 GWh | 8.7 mi |
| Clearwater Wind III | Miles City, MT | 371.0 GWh | 8.7 mi |
| Colstrip | Colstrip, MT | 9.4 TWh | 65.5 mi |
| Colstrip Energy LP | Colstrip, MT | 287.5 GWh | 59.7 mi |
| Culbertson Generation Station | Culbertson, MT | 251.2 GWh | 133.6 mi |
| Fort Peck | Fort Peck, MT | 751.6 GWh | 82.5 mi |
| Glendive GT | Glendive, MT | 2.6 GWh | 79 mi |
| Hardin Generator Project | Hardin, MT | 481.0 GWh | 93.6 mi |
| Miles City GT | Miles City, MT | 331.0 MWh | 39.4 mi |
| OREG 1 Inc | Culbertson, MT | 143.8 GWh | 133.6 mi |
| OREG 2 Inc | Culbertson, MT | 118.7 GWh | 133.6 mi |
| South Mills Solar, LLC | Hardin, MT | 5.1 GWh | 96.1 mi |
| Yellowtail | Hardin, MT | 798.4 GWh | 128.9 mi |