Edwards Sanborn E1A
9900 Lone Butte Road, Mojave, CA 93501Plant Summary Information
Edwards Sanborn E1A is ranked #55 out of 849 solar farms in California in terms of total annual net electricity generation.
Edwards Sanborn E1A generated 106.4 GWh during the 3-month period between June 2025 to September 2025.
| Plant Name | Edwards Sanborn E1A |
|---|---|
| Utility Name | Terra-Gen Operating Co-Hybrid |
| Location | Kern County, CA |
| Initial Operation Date | August 2022 |
| Last Update | Sep 2025 |
| Annual Generation | 333.4 GWh |
| Annual Consumption | 1.3 M MMBtu |
| Ranked #1,833 out of 12,539 Power Plants Nationwide | |
| Ranked #205 out of 6,400 Solar Power Plants Nationwide | |
| Ranked #151 out of 1,600 California Power Plants | |
| Ranked #55 out of 849 California Solar Power Plants | |
| Fuel Types | Solar |
Map of Edwards Sanborn E1A
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Edwards Sanborn E1A.
Monthly Net Generation for Edwards Sanborn E1A
Edwards Sanborn E1A Details
| Summary Information | |
|---|---|
| Plant Name | Edwards Sanborn E1A (64878) |
| Plant Address | 9900 Lone Butte Road, Mojave, CA 93501 |
| Utility | Terra-Gen Operating Co-Hybrid (64366) |
| Latitude, Longitude | 34.96192, -118.12421 |
| Generation Dates on File | Aug 2022 to Sep 2025 |
| Initial Operation Date | August 2022 |
| Annual Generation | 333.4 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | Yes |
Generator BESS Details Operating August 2022
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | PHSP15 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | PHSP15 |
| Nameplate Capacity | 144 MW |
| Summer Capacity | 144 MW |
| Winter Capacity | 144 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | August 2022 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 272 |
|---|---|
| Maximum Charge Rate | 130 MW |
| Maximum Discharge Rate | 130 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 133.4 |
| Storage Enclosure Type | CS |
| Arbitrage | Yes |
| Frequency Regulation | Yes |
| Ramping Spinning Reserve | Yes |
| Excess Wind And Solar Generation | P |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 64878 |
| Direct Support Gen Id | PV |
| Support T D Asset | No |
Generator PV Details Operating August 2022
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | PHSP15 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | PHSP15 |
| Nameplate Capacity | 149.3 MW |
| Summer Capacity | 149.3 MW |
| Winter Capacity | 149.3 MW |
|---|---|
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | August 2022 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 157 MW |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Edwards Sanborn E1A Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #195 | Camilla Solar Energy Project | Camilla, GA | 359.2 GWh |
| #196 | Scarlet II Hybrid | Cantua Creek, CA | 342.2 GWh |
| #197 | Huck Finn Renewable Energy Center | Vandalia, MO | 357.9 GWh |
| #198 | Copper Mountain Solar 2 | Boulder City, NV | 356.1 GWh |
| #199 | Buckthorn Westex | Ft. Stockton, TX | 355.9 GWh |
| #200 | Aragorn Solar Project | Van Horn, TX | 353.9 GWh |
| #201 | Centinela Solar Energy | Calexico, CA | 352.7 GWh |
| #202 | Newport Solar Project | Newport, AR | 352.7 GWh |
| #203 | Blythe Solar II, LLC | Blythe, CA | 337.2 GWh |
| #204 | Ganado Solar | Gail, TX | 343.8 GWh |
| #206 | Impact Solar 1 | Deport, TX | 348.0 GWh |
| #207 | Blythe Solar IV, LLC | Blythe, CA | 339.0 GWh |
| #208 | Estonian Solar Project, LLC | Cooper, TX | 339.2 GWh |
| #209 | Box Canyon (AZ) | Florence, AZ | 344.8 GWh |
| #210 | Midway Solar - TX | Fort Stockton, TX | 343.6 GWh |
| #211 | Fifth Standard Solar PV, LLC (Hybrid) | Huron, CA | 317.9 GWh |
| #212 | Arlington Energy Center III | Blythe, CA | 321.0 GWh |
| #213 | Arlington Valley Solar Energy II | Arlington, AZ | 341.2 GWh |
| #214 | Calhoun Solar | Battle Creek, MI | 337.3 GWh |
| #215 | Maverick Solar 7, LLC | Desert Center, CA | 336.8 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Edwards Sanborn E1A.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Alta Wind Energy Center IV | Mojave, CA | 193.4 GWh | 7.4 mi |
| Alta Wind Energy Center V | Mojave, CA | 288.4 GWh | 7.4 mi |
| Alta Wind VIII | Mojave, CA | 222.0 GWh | 7.7 mi |
| Brookfield Tehachapi 1 | Mojave, CA | 276.9 GWh | 7.4 mi |
| Difwind Farms Ltd VI | Mojave, CA | 14.9 GWh | 6.7 mi |
| Edwards Sanborn E1B | Mojave, CA | 355.4 GWh | 1.7 mi |
| Edwards Sanborn E2 | Mojave, CA | 299.6 GWh | 1.4 mi |
| Edwards Sanborn E3 | Mojave, CA | 55.8 GWh | 1.1 mi |
| Edwards Sanborn E4 | Mojave, CA | 316.3 GWh | 2.4 mi |
| Edwards Sanborn E5 | Mojave, CA | 155.2 GWh | 2.7 mi |
| Edwards Sanborn S1 | Mojave, CA | 99.6 GWh | 4.6 mi |
| Edwards Sanborn S3 | Mojave, CA | 83.4 GWh | 3.8 mi |
| Edwards Sanborn S4 | Mojave, CA | 88.2 GWh | 3.5 mi |
| Pinyon Pine I | Mojave, CA | 306.6 GWh | 7.5 mi |
| Pinyon Pine II | Mojave, CA | 233.1 GWh | 7.2 mi |
| RE Camelot LLC | Mojave, CA | 125.1 GWh | 5.7 mi |
| RE Columbia 3 LLC | Mojave, CA | 23.9 GWh | 4.9 mi |
| RE Columbia Two, LLC | Mojave, CA | 40.4 GWh | 5.7 mi |
| RE Rio Grande Solar LLC | Mojave, CA | 11.0 GWh | 3.9 mi |
| RE Rosamond Two LLC | Rosamond, CA | 48.3 GWh | 7.7 mi |