HEB00182
3002 S. 31st St., Temple, TX 76502Plant Summary Information
HEB00182 is ranked #262 out of 314 natural gas power plants in Texas in terms of total annual net electricity generation.
HEB00182 is comprised of 3 generators and generated 48.6 MWh during the 3-month period between September 2024 to December 2024.
| Plant Name | HEB00182 |
|---|---|
| Utility Name | Texas Microgrid, LLC |
| Location | Bell County, TX |
| Initial Operation Date | October 2018 |
| Last Update | Dec 2024 |
| Annual Generation | 217.0 MWh |
| Annual Consumption | 3.4 k MMBtu |
| Ranked #11,920 out of 12,539 Power Plants Nationwide | |
| Ranked #2,064 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #729 out of 799 Texas Power Plants | |
| Ranked #262 out of 314 Texas Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
Map of HEB00182
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for HEB00182.
Monthly Net Generation for HEB00182
HEB00182 Details
| Summary Information | |
|---|---|
| Plant Name | HEB00182 (65274) |
| Plant Address | 3002 S. 31st St., Temple, TX 76502 |
| Utility | Texas Microgrid, LLC (64449) |
| Latitude, Longitude | 31.07212, -97.3709 |
| Generation Dates on File | Jan 2021 to Dec 2024 |
| Initial Operation Date | October 2018 |
| Annual Generation | 217.0 MWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | ATMOS ENERGY CORPORATION |
| Natural Gas Storage | No |
Generator H1821 Details Operating October 2018
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.4 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.4 MW |
| Winter Capacity | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | October 2018 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator H1822 Details Operating October 2018
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.4 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.4 MW |
| Winter Capacity | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | October 2018 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator H1823 Details Operating October 2018
| Technology | Natural Gas Internal Combustion Engine |
|---|---|
| Prime Mover | Internal Combustion Engine |
| Ownership | Single Owner |
| Nameplate Capacity | 0.4 MW |
| Nameplate Power Factor | 0.8 |
| Summer Capacity | 0.4 MW |
| Winter Capacity | 0.4 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | October 2018 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Switch Between Oil And Natural Gas | No |
HEB00182 Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #2054 | Albany Green Energy | Albany, GA | 188.9 GWh |
| #2055 | WAL4509 | Tarrant, TX | 225.0 MWh |
| #2056 | WAL3827 | Richmond, TX | 224.0 MWh |
| #2057 | WAL602 | Spring, TX | 223.0 MWh |
| #2058 | WAL5080 | Hurst, TX | 223.0 MWh |
| #2059 | HEB00028 | League City, TX | 223.0 MWh |
| #2060 | Pratt 2 | Pratt, KS | 372.0 MWh |
| #2061 | Triton East and West Cogen | River Grove, IL | 218.0 MWh |
| #2062 | WAL3510 | Pearland, TX | 218.0 MWh |
| #2063 | WAL284 | Mansfield, TX | 217.0 MWh |
| #2065 | WAL872 | Pearland, TX | 214.0 MWh |
| #2066 | HEB00789 | Frisco, TX | 212.0 MWh |
| #2067 | HEB00055 | Southlake, TX | 211.0 MWh |
| #2068 | Missouri River Wastewater Treatment | Omaha, NE | 10.8 GWh |
| #2069 | WAL194 | Baytown, TX | 209.0 MWh |
| #2070 | WAL972 | Fort Worth, TX | 209.0 MWh |
| #2071 | WAL3298 | Kemah, TX | 209.0 MWh |
| #2072 | Oxnard Wastewater Treatment Plant | Oxnard, CA | 4.2 GWh |
| #2073 | Water Street Station | Bay City, MI | 239.0 MWh |
| #2074 | OTHERTraditionClearfork | Fort Worth, TX | 205.0 MWh |
Nearby Power Plants
Below are closest 20 power plants surrounding HEB00182.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| AbbVie Waco | Waco, TX | 811.0 MWh | 30.5 mi |
| Big Elm Solar | Troy, TX | 380.7 GWh | 10.3 mi |
| BPL Crown Solar LLC | Chilton, TX | 215.3 GWh | 25.5 mi |
| BPL Sol Solar LLC | Chilton, TX | 208.9 GWh | 25.5 mi |
| BT Jungmann | Buckholts, TX | 68.1 GWh | 21.9 mi |
| Eddy II | Eddy, TX | 16.6 GWh | 16.5 mi |
| Five Wells Solar Center - Hybrid | Rogers, TX | 726.7 GWh | 8.3 mi |
| Griffin Solar | Robinson, TX | 9.2 GWh | 30.9 mi |
| HEBTEMDistCenter | Temple, TX | 618.0 MWh | 5.6 mi |
| HEBTEMDistCenter1B | Temple, TX | 309.0 MWh | 5.6 mi |
| HEBTEMDistCenter2A | Temple, TX | 309.0 MWh | 5.6 mi |
| Marlin Solar | Marlin, TX | 9.9 GWh | 32.7 mi |
| Orion I Solar Project | Burlington, TX | 452.7 GWh | 22.5 mi |
| Orion II Solar Project | Rosebud, TX | 556.1 GWh | 26 mi |
| Orion III Solar Project | Buckholts, TX | 558.6 GWh | 16.5 mi |
| Phantom Solar | Fort Hood, TX | 16.9 GWh | 28.2 mi |
| Temple Power Station | Temple, TX | 7.0 TWh | 3.4 mi |
| WAL1232 | Belton, TX | 237.0 MWh | 5.2 mi |
| WAL407 | Killeen, TX | 251.0 MWh | 21.2 mi |
| WAL6929 | Temple, TX | 271.0 MWh | 3.9 mi |