Temple Power Station
2892 Panda Drive, Temple, TX 76501Plant Summary Information
Temple Power Station is ranked #43 out of 2,243 natural gas power plants nationwide in terms of total annual net electricity generation.
Temple Power Station is comprised of 6 generators and generated 2.0 TWh during the 3-month period between July 2025 to October 2025.
| Plant Name | Temple Power Station |
|---|---|
| Utility Name | Temple Generation Holdings LLC |
| Location | Bell County, TX |
| Initial Operation Date | July 2014 |
| Last Update | Oct 2025 |
| Annual Generation | 6.9 TWh |
| Annual Consumption | 53.1 M MMBtu |
| Ranked #133 out of 12,553 Power Plants Nationwide | |
| Ranked #43 out of 2,243 Natural Gas Power Plants Nationwide | |
| Ranked #11 out of 804 Texas Power Plants | |
| Ranked #4 out of 314 Texas Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
| Previous Operator |
PPG - O&M Panda Temple Power LLC (2013 to 2023) Temple Generation Holdings LLC (2024 to 2024) |
Map of Temple Power Station
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Temple Power Station.
Monthly Net Generation for Temple Power Station
Temple Power Station Details
| Summary Information | |
|---|---|
| Plant Name | Temple Power Station (58001) |
| Plant Address | 2892 Panda Drive, Temple, TX 76501 |
| Utility | Temple Generation Holdings LLC (57377) |
| Latitude, Longitude | 31.05583, -97.31722 |
| Generation Dates on File | Jul 2014 to Oct 2025 |
| Initial Operation Date | July 2014 |
| Annual Generation | 6.9 TWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | EG22-158, EG14-48, EG14-49 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | City of Temple |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | ATMOS ENERGY CORPORATION |
| Natural Gas Storage | No |
Generator CTG-1 Details Operating July 2014
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | TMP1 |
| Ownership | Wholly Owned by Other Entity |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 232 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 232 MW |
| Winter Capacity | 232 MW |
| Minimum Load | 140 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 2014 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator CTG-2 Details Operating July 2014
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | TMP1 |
| Ownership | Wholly Owned by Other Entity |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 232 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 232 MW |
| Winter Capacity | 232 MW |
| Minimum Load | 140 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | July 2014 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator STG-1 Details Operating July 2014
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | TMP1 |
| Ownership | Wholly Owned by Other Entity |
| Duct Burners | Yes |
| Nameplate Capacity | 339.2 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 326 MW |
| Winter Capacity | 326 MW |
| Minimum Load | 70 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | July 2014 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator CTG-3 Details Operating May 2015
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | TMP2 |
| Ownership | Wholly Owned by Other Entity |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 232 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 232 MW |
| Winter Capacity | 232 MW |
| Minimum Load | 140 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 2015 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator CTG-4 Details Operating May 2015
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Combustion Turbine Part |
| Unit Code | TMP2 |
| Ownership | Wholly Owned by Other Entity |
| Can Bypass Heat Recovery Steam Generator | No |
| Nameplate Capacity | 232 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 232 MW |
| Winter Capacity | 232 MW |
| Minimum Load | 140 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
| First Operation Date | May 2015 |
|---|---|
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Startup Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 1H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator STG-2 Details Operating May 2015
| Technology | Natural Gas Fired Combined Cycle |
|---|---|
| Prime Mover | Combined Cycle Steam Part |
| Unit Code | TMP2 |
| Ownership | Wholly Owned by Other Entity |
| Duct Burners | Yes |
| Nameplate Capacity | 339.2 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 326 MW |
| Winter Capacity | 326 MW |
| Minimum Load | 70 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | May 2015 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Time From Cold Shutdown To Full Load | 12H |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Temple Power Station Plant Owners
| Owner Name | Address | Generator | Ownership |
|---|---|---|---|
| Temple Generation I, LLC | 2892 Panda Drive, Temple, TX 76501 | Generator CTG-1 | 100.00% |
| Temple Generation I, LLC | 2892 Panda Drive, Temple, TX 76501 | Generator CTG-2 | 100.00% |
| Temple Generation II, LLC | 2892 Panda Drive, Temple, TX 76501 | Generator CTG-3 | 100.00% |
| Temple Generation II, LLC | 2892 Panda Drive, Temple, TX 76501 | Generator CTG-4 | 100.00% |
| Temple Generation I, LLC | 2892 Panda Drive, Temple, TX 76501 | Generator STG-1 | 100.00% |
| Temple Generation II, LLC | 2892 Panda Drive, Temple, TX 76501 | Generator STG-2 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #33 | Paradise | Drakesboro, KY | 7.7 TWh |
| #34 | Jackson Generation, LLC | Elwood, IL | 7.7 TWh |
| #35 | Wansley Combined Cycle | Franklin, GA | 7.6 TWh |
| #36 | Seminole (FL) | Palatka, FL | 10.1 TWh |
| #37 | South Field Energy | Wellsville, OH | 7.5 TWh |
| #38 | Big Bend | Apollo Beach, FL | 7.5 TWh |
| #39 | New Covert Generating Facility | Covert, MI | 7.3 TWh |
| #40 | Port Washington Generating Station | Port Washington, WI | 7.2 TWh |
| #41 | Moxie Freedom Generation Plant | Salem Township, PA | 7.2 TWh |
| #42 | Cape Canaveral | Cocoa, FL | 6.9 TWh |
| #44 | Lamar Power Project | Paris, TX | 6.8 TWh |
| #45 | Hickory Run Energy Station | New Castle, PA | 6.8 TWh |
| #46 | Riviera | Riviera Beach, FL | 6.8 TWh |
| #47 | Magnolia Power Plant | Ashland, MS | 6.7 TWh |
| #48 | Jack County | Bridgeport, TX | 6.7 TWh |
| #49 | Manatee | Parrish, FL | 6.6 TWh |
| #50 | Midlothian Energy Facility | Midlothian, TX | 6.6 TWh |
| #51 | Clean Energy Future-Lordstown, LLC | Lordstown, OH | 6.5 TWh |
| #52 | Tenaska Westmoreland Generating Station | Smithton, PA | 6.4 TWh |
| #53 | Turkey Point | Homestead, FL | 20.1 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Temple Power Station.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| AbbVie Waco | Waco, TX | 811.0 MWh | 30.7 mi |
| Big Elm Solar | Troy, TX | 424.2 GWh | 8.4 mi |
| BPL Crown Solar LLC | Chilton, TX | 213.9 GWh | 24.4 mi |
| BPL Sol Solar LLC | Chilton, TX | 208.5 GWh | 24.4 mi |
| BT Jungmann | Buckholts, TX | 75.0 GWh | 18.6 mi |
| Eddy II | Eddy, TX | 16.6 GWh | 16.6 mi |
| Five Wells Solar Center - Hybrid | Rogers, TX | 724.6 GWh | 5.2 mi |
| Griffin Solar | Robinson, TX | 9.2 GWh | 30.7 mi |
| HEB00182 | Temple, TX | 217.0 MWh | 3.4 mi |
| HEBTEMDistCenter | Temple, TX | 618.0 MWh | 7.2 mi |
| HEBTEMDistCenter1B | Temple, TX | 309.0 MWh | 7.2 mi |
| HEBTEMDistCenter2A | Temple, TX | 309.0 MWh | 7.2 mi |
| Marlin Solar | Marlin, TX | 9.9 GWh | 30.5 mi |
| Orion I Solar Project | Burlington, TX | 450.0 GWh | 19.1 mi |
| Orion II Solar Project | Rosebud, TX | 553.6 GWh | 22.7 mi |
| Orion III Solar Project | Buckholts, TX | 555.5 GWh | 13.2 mi |
| Phantom Solar | Fort Hood, TX | 16.9 GWh | 31.5 mi |
| WAL1232 | Belton, TX | 237.0 MWh | 8.5 mi |
| WAL407 | Killeen, TX | 251.0 MWh | 24.5 mi |
| WAL6929 | Temple, TX | 271.0 MWh | 7.1 mi |