Grant County
6006 Stage Rd, Town of Potosi, WI 53820Plant Summary Information
Grant County is ranked #17 out of 239 power plants in Wisconsin in terms of total annual net electricity generation.
Grant County generated 121.1 GWh during the 3-month period between June 2025 to September 2025.
| Plant Name | Grant County |
|---|---|
| Utility Name | Wisconsin Power & Light Co |
| Location | Grant County, WI |
| Initial Operation Date | May 2024 |
| Last Update | Sep 2025 |
| Annual Generation | 374.6 GWh |
| Annual Consumption | 1.4 M MMBtu |
| Ranked #1,666 out of 12,539 Power Plants Nationwide | |
| Ranked #181 out of 6,400 Solar Power Plants Nationwide | |
| Ranked #17 out of 239 Wisconsin Power Plants | |
| Ranked #1 out of 91 Wisconsin Solar Power Plants | |
| Fuel Types | Solar |
Map of Grant County
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Grant County.
Monthly Net Generation for Grant County
Grant County Details
| Summary Information | |
|---|---|
| Plant Name | Grant County (65007) |
| Plant Address | 6006 Stage Rd, Town of Potosi, WI 53820 |
| Utility | Wisconsin Power & Light Co (20856) |
| Latitude, Longitude | 42.71898, -90.70104 |
| Generation Dates on File | Jun 2024 to Sep 2025 |
| Initial Operation Date | May 2024 |
| Annual Generation | 374.6 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | MRO |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | American Transmission Co (659) |
| Grid Voltage | 138.00 kV |
| Energy Storage | Yes |
Generator PV1 Details Operating May 2024
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | ALTE.GRANTCTY |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | ALTE.GRANTCTY |
| Nameplate Capacity | 200 MW |
| Nameplate Power Factor | 0.95 |
| Summer Capacity | 200 MW |
| Winter Capacity | 200 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | May 2024 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Other Planned Modifications | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| DC Net Capacity | 256 MW |
| Crystalline Silicon | Yes |
| Thin Film CDTE | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Grant County Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #171 | Montague Solar | Arlington, OR | 381.9 GWh |
| #172 | Cavalry Solar Hybrid | Monon, IN | 371.6 GWh |
| #173 | Madison Fields Solar Project, LLC | Irwin, OH | 381.5 GWh |
| #174 | Big Elm Solar | Troy, TX | 380.7 GWh |
| #175 | RE Roserock | Fort Stockton, TX | 378.3 GWh |
| #176 | Corazon Energy LLC | Rachito Las Lomas, TX | 378.2 GWh |
| #177 | Raceway Solar & Storage | Lancaster, CA | 370.1 GWh |
| #178 | Indiana Crossroads Solar Park | Reynolds, IN | 375.7 GWh |
| #179 | Twiggs Solar | Dry Branch, GA | 375.3 GWh |
| #180 | Zier Solar | Brackettville, TX | 369.2 GWh |
| #182 | Hillcrest Solar | Mt. Orab, OH | 374.6 GWh |
| #183 | Dry Lake Solar Energy Center | Moapa, NV | 356.8 GWh |
| #184 | Imperial Solar Energy Center West | Seeley, CA | 373.6 GWh |
| #185 | Shakes Solar | Carrizo Springs, TX | 373.3 GWh |
| #186 | Edwards Sanborn E1B | Mojave, CA | 355.4 GWh |
| #187 | Maverick Solar, LLC | Desert Center, CA | 371.6 GWh |
| #188 | Greasewood Solar | Fort Stockton, TX | 371.1 GWh |
| #189 | Blythe Solar III, LLC Hybrid | Blythe, CA | 353.7 GWh |
| #190 | Samson Solar Energy | Cunningham, TX | 367.7 GWh |
| #191 | Lund Hill Solar | Bickleton, WA | 367.4 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Grant County.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Alliant SBD 9205 A Y McDonald | Dubuque, IA | 8.8 MWh | 15.9 mi |
| Alliant SBD 9301 Prairie Farms | Dubuque, IA | 86.2 MWh | 13.1 mi |
| Apple Canyon Lake Solar | Apple River, IL | 3.5 GWh | 32.9 mi |
| Badger Hollow I | Montfort, WI | 194.5 GWh | 23.7 mi |
| Badger Hollow II | Cobb, WI | 200.2 GWh | 23.7 mi |
| Bellevue | Bellevue, IA | 61.0 MWh | 35.5 mi |
| Cascade | Cascade, IA | 73.0 MWh | 33.1 mi |
| Cassville Solar | Cassville, WI | 97.6 GWh | 11.7 mi |
| Earlville | Earlville, IA | 7.0 MWh | 33 mi |
| Elk Wind Farm | Greeley, IA | 178.3 GWh | 35.3 mi |
| Fennimore | Fennimore, WI | 27.0 MWh | 18.4 mi |
| Fennimore Solar | Fennimore, WI | 3.6 GWh | 17.5 mi |
| Hopkinton | Hopkinton, IA | 11.0 MWh | 38 mi |
| John Deere Dubuque Works | Dubuque, IA | 47.0 MWh | 10.1 mi |
| McGregor | McGregor, IA | 7.0 MWh | 31.9 mi |
| Montfort Wind Energy Center | Montfort, WI | 55.8 GWh | 23.2 mi |
| Mt. Hope DPC Solar | Mt. Hope, WI | 2.1 GWh | 18.9 mi |
| Quilt Block Wind Farm LLC | Darlington, WI | 387.4 GWh | 22.4 mi |
| Red Barn Energy | Montfort, WI | 251.6 GWh | 20.8 mi |
| West Dubuque Solar | Dubuque, IA | 6.5 GWh | 16.4 mi |