Antelope Expansion 2
9611 West Avenue G, Lancaster, CA 93536Plant Summary Information
Antelope Expansion 2 is ranked #86 out of 834 solar farms in California in terms of total annual net electricity generation.
Antelope Expansion 2 generated 40.3 GWh during the 3-month period between December 2025 to March 2026.
| Plant Name | Antelope Expansion 2 |
|---|---|
| Utility Name | AES Distributed Energy |
| Location | Los Angeles County, CA |
| Initial Operation Date | December 2018 |
| Last Update | Mar 2026 |
| Annual Generation | 250.5 GWh |
| Annual Consumption | 927.7 k MMBtu |
| Ranked #2,226 out of 12,332 Power Plants Nationwide | |
| Ranked #348 out of 6,397 Solar Power Plants Nationwide | |
| Ranked #216 out of 1,530 California Power Plants | |
| Ranked #86 out of 834 California Solar Power Plants | |
| Fuel Types | Solar |
| Previous Operators |
Antelope Expansion 2, LLC (2016 to 2017) Sustainable Power Group, LLC (2018 to 2020) AES Distributed Energy (2021 to 2024) |
Map of Antelope Expansion 2
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Antelope Expansion 2.
Monthly Net Generation for Antelope Expansion 2
Monthly Plant Fuel Consumption for Antelope Expansion 2
Antelope Expansion 2 Details
| Summary Information | |
|---|---|
| Plant Name | Antelope Expansion 2 (61264) |
| Plant Address | 9611 West Avenue G, Lancaster, CA 93536 |
| Utility | AES Distributed Energy (61012) |
| Latitude, Longitude | 34.74498, -118.30915 |
| Generation Dates on File | Dec 2018 to Mar 2026 |
| Initial Operation Date | December 2018 |
| Annual Generation | 250.5 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
| Grid Voltage | 220.00 kV |
| Energy Storage | No |
Generator ANTX2 Details Operating December 2018
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 105 MW |
| Summer Capacity | 105 MW |
| Winter Capacity | 105 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2018 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Solar |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 130 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Antelope Expansion 2 Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #338 | Oak Solar | Gaston, NC | 255.1 GWh |
| #339 | Bluebell Solar II | Sterling, TX | 255.0 GWh |
| #340 | Onion River | Sheboygan Cedar Grove, WI | 254.5 GWh |
| #341 | Rabbitbrush Solar, LLC | Rosamond, CA | 250.2 GWh |
| #342 | Bellflower Solar 1 | Lewisville, IN | 253.2 GWh |
| #343 | Playa Solar 2 | North Las Vegas, NV | 253.0 GWh |
| #344 | Liberty County Solar Project | Dayton, TX | 252.7 GWh |
| #345 | Elm Branch Solar 1 | Bardwell, TX | 251.7 GWh |
| #346 | West Line Solar, LLC | City of Eloy, AZ | 251.1 GWh |
| #347 | SR Snipesville III | Denton, GA | 250.8 GWh |
| #349 | Emerald Grove | Crane, TX | 250.1 GWh |
| #350 | Hickory Solar | Jerseyville, IL | 249.5 GWh |
| #351 | Great Cove Solar II | Saint Thomas, PA | 249.5 GWh |
| #352 | Flat Fork Solar | Wheatley, AR | 248.5 GWh |
| #353 | Calhoun County Solar Project | Sheridan Township, MI | 247.0 GWh |
| #354 | East Line Solar | Coolidge, AZ | 246.4 GWh |
| #355 | Lockhart Solar PV, LLC | Hinkley, CA | 242.5 GWh |
| #356 | Taylor County Solar | Butler, GA | 245.4 GWh |
| #357 | OCI Alamo 7 LLC | Haskell, TX | 245.3 GWh |
| #358 | Orange Grove | Jim Wells, TX | 244.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Antelope Expansion 2.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Antelope DSR 3 | Lancaster, CA | 57.7 GWh | 0.6 mi |
| Antelope Expansion 3A | Lancaster, CA | 31.7 GWh | 1.3 mi |
| Antelope Expansion 3B | Lancaster, CA | 11.0 GWh | 1.9 mi |
| Central Antelope Dry Ranch B LLC | Lancaster, CA | 6.7 GWh | 2.8 mi |
| Central Antelope Dry Ranch C | Lancaster, CA | 33.3 GWh | 1.8 mi |
| Elevation Solar C | Lancaster, CA | 105.3 GWh | 1.1 mi |
| Lancaster Dry Farm Ranch B | Lancaster, CA | 7.8 GWh | 2.2 mi |
| North Lancaster Ranch | Lancaster, CA | 37.2 GWh | 1.8 mi |
| Portal Ridge Solar B, LLC | Lancaster, CA | 46.9 GWh | 2.5 mi |
| Rodeo Solar C2 | Lancaster, CA | 2.9 GWh | 2.5 mi |
| Rodeo Solar D2 | Lancaster, CA | 2.6 GWh | 2.5 mi |
| San Pablo Raceway | Lancaster, CA | 239.5 GWh | 2.2 mi |
| Summer North Solar | Lancaster, CA | 10.0 GWh | 1.9 mi |
| Summer Solar A2 | Lancaster, CA | 3.2 GWh | 1.9 mi |
| Summer Solar B2 | Lancaster, CA | 3.0 GWh | 1.9 mi |
| Summer Solar C2 | Lancaster, CA | 2.5 GWh | 1.9 mi |
| Summer Solar D2 | Lancaster, CA | 1.8 GWh | 1.9 mi |
| Summer Solar LLC | Lancaster, CA | 49.1 GWh | 2.1 mi |
| TA-High Desert LLC | Lancaster, CA | 56.8 GWh | 2.5 mi |
| Western Antelope Blue Sky B | Lancaster, CA | 50.2 GWh | 0.9 mi |