Los Vientos Wind 1A
4545 FM 507, Sebastian, TX 78594Plant Summary Information
Los Vientos Wind 1A is ranked #138 out of 224 wind farms in Texas in terms of total annual net electricity generation.
Los Vientos Wind 1A generated 83.0 GWh during the 3-month period between June 2025 to September 2025.
| Plant Name | Los Vientos Wind 1A |
|---|---|
| Utility Name | Duke Energy Renewables Services |
| Location | Cameron County, TX |
| Initial Operation Date | December 2012 |
| Last Update | Sep 2025 |
| Annual Generation | 408.3 GWh |
| Annual Consumption | 1.5 M MMBtu |
| Ranked #1,547 out of 12,539 Power Plants Nationwide | |
| Ranked #442 out of 1,362 Wind Power Plants Nationwide | |
| Ranked #310 out of 799 Texas Power Plants | |
| Ranked #138 out of 224 Texas Wind Power Plants | |
| Fuel Types | Wind |
| Previous Operator |
Los Vientos Wind 1A, LLC (2013 to 2021) Duke Energy Renewables Services (2022 to 2024) |
Map of Los Vientos Wind 1A
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Los Vientos Wind 1A.
Monthly Net Generation for Los Vientos Wind 1A
Los Vientos Wind 1A Details
| Summary Information | |
|---|---|
| Plant Name | Los Vientos Wind 1A (57751) |
| Plant Address | 4545 FM 507, Sebastian, TX 78594 |
| Utility | Duke Energy Renewables Services (65411) |
| Latitude, Longitude | 26.33072, -97.5857 |
| Generation Dates on File | Jan 2013 to Sep 2025 |
| Initial Operation Date | December 2012 |
| Annual Generation | 408.3 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | AEP Texas Central Company (3278) TX |
| Grid Voltage | 138.00 kV |
| Energy Storage | No |
Generator 1 Details Operating December 2012
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 200 MW |
| Summer Capacity | 200 MW |
| Winter Capacity | 200 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2012 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Solid Fuel Gasification | No |
| Turbines/Hydrokinetic Buoys | 87 |
| Multiple Fuels | No |
| Turbine Details | |
| Number Of Turbines | 87 |
|---|---|
| Predominant Turbine Manufacturer | Siemens |
| Predominant Turbine Model Number | SWT-2.3-108 |
| Design Wind Speed | 13.9 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 272 |
Los Vientos Wind 1A Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #432 | Midway Wind, LLC | Taft, TX | 418.5 GWh |
| #433 | Glass Sands Wind Facility | Sulphur, OK | 418.4 GWh |
| #434 | Los Vientos Windpower IV | Rio Grande City, TX | 418.3 GWh |
| #435 | Leaning Juniper Wind Power II | Arlington, OR | 416.6 GWh |
| #436 | Prairie Rose Wind Farm | Hardwick, MN | 414.4 GWh |
| #437 | Callahan Divide Wind Energy Center | Tusocola, TX | 414.3 GWh |
| #438 | Smoky Hills Wind Project Phase II | Lincoln, KS | 414.3 GWh |
| #439 | Senate Wind LLC | Bryson, TX | 413.7 GWh |
| #440 | Voyager Wind I | Mojave, CA | 413.4 GWh |
| #441 | Morning Light Wind Farm | Adair, IA | 413.3 GWh |
| #443 | Camp Grove Wind Farm | Wyoming, IL | 406.4 GWh |
| #444 | Rock Falls Wind Farm LLC | Braman, OK | 406.2 GWh |
| #445 | Post Oak Wind LLC | Abilene, TX | 405.9 GWh |
| #446 | Post Rock Wind Power Project, LLC | Ellsworth, KS | 405.7 GWh |
| #447 | Judith Gap Wind Energy Center | Harlowton, MT | 403.0 GWh |
| #448 | Panther Creek Wind Farm II | Big Spring, TX | 402.1 GWh |
| #449 | Glenrock | Glenrock, WY | 401.0 GWh |
| #450 | Seven Mile Hill | Medicine Bow, WY | 399.8 GWh |
| #451 | Tuolumne Wind Project | Goldendale, WA | 399.7 GWh |
| #452 | Milford Wind Corridor I LLC | Milford, UT | 399.7 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Los Vientos Wind 1A.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Bruennings Breeze Wind Farm | Raymondville, TX | 534.0 GWh | 14.8 mi |
| Cameron Wind 1 LLC | Rio Hondo, TX | 337.6 GWh | 11.9 mi |
| E. Porte Ct. | Harlingen, TX | 233.0 MWh | 10.7 mi |
| El Sauz Ranch Wind, LLC | San Perlita, TX | 636.3 GWh | 11.8 mi |
| La Chalupa, LLC | Rio Hondo, TX | 485.8 GWh | 7.2 mi |
| Las Majadas Wind Farm | Santa Monica, TX | 859.5 GWh | 3.4 mi |
| Los Vientos Wind 1B | Sebastian, TX | 353.9 GWh | 5.2 mi |
| Magic Valley Wind Farm I LLC | San Perlita, TX | 480.2 GWh | 11.9 mi |
| Nebula Solar | La Feria, TX | 280.7 GWh | 21.2 mi |
| Palmas Wind, LLC | Rio Hondo, TX | 358.7 GWh | 6.2 mi |
| Raymond Wind Farm, LLC | Lyford, TX | 676.2 GWh | 12.3 mi |
| Ridge Rd | Alamo, TX | 249.0 MWh | 33.7 mi |
| San Roman Wind I, LLC | Los Fresnos, TX | 250.7 GWh | 19.1 mi |
| Santa Rosa | Santa Rosa, TX | 275.0 MWh | 16.3 mi |
| Silas Ray | Brownsville, TX | 103.4 GWh | 29.1 mi |
| Vancourt Solar Interconnections | La Feria, TX | 90.5 GWh | 21.2 mi |
| Vaquero | Harlingen, TX | 270.0 MWh | 12 mi |
| Villa Cavasos | Brownsville, TX | 269.0 MWh | 21.4 mi |
| WAL456 | Brownsville, TX | 272.0 MWh | 24.8 mi |
| West Raymond Wind Farm LLC | Lyford, TX | 759.5 GWh | 25.4 mi |