Hyder Solar Hybrid
75100 E County 14 1/2 St, Hyder, AZ 85333Plant Summary Information
Hyder Solar Hybrid is ranked #62 out of 121 solar farms in Arizona in terms of total annual net electricity generation.
Hyder Solar Hybrid generated 5.0 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Hyder Solar Hybrid |
|---|---|
| Utility Name | Arizona Public Service Co |
| Location | Yuma County, AZ |
| Initial Operation Date | November 2011 |
| Last Update | Dec 2025 |
| Annual Generation | 31.2 GWh |
| Annual Consumption | 120.6 k MMBtu |
| Ranked #4,813 out of 13,081 Power Plants Nationwide | |
| Ranked #1,320 out of 7,015 Solar Power Plants Nationwide | |
| Ranked #111 out of 176 Arizona Power Plants | |
| Ranked #62 out of 121 Arizona Solar Power Plants | |
| Fuel Types | Solar |
Map of Hyder Solar Hybrid
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Hyder Solar Hybrid.
Monthly Net Generation for Hyder Solar Hybrid
Monthly Plant Fuel Consumption for Hyder Solar Hybrid
Hyder Solar Hybrid Details
| Summary Information | |
|---|---|
| Plant Name | Hyder Solar Hybrid (57563) |
| Plant Address | 75100 E County 14 1/2 St, Hyder, AZ 85333 |
| Utility | Arizona Public Service Co (803) |
| Latitude, Longitude | 33.02566, -113.34397 |
| Generation Dates on File | Nov 2011 to Dec 2025 |
| Initial Operation Date | November 2011 |
| Annual Generation | 31.2 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | Arizona Public Service Company (AZPS) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Arizona Public Service Co (803) AZ |
| Grid Voltage | 12.50 kV |
| Energy Storage | Yes |
Generator PV1 Details Operating November 2011
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 17 MW |
| Summer Capacity | 17 MW |
| Winter Capacity | 17 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | November 2011 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| DC Net Capacity | 18.8 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator PV2 Details Operating February 2012
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 15 MW |
| Summer Capacity | 14 MW |
| Winter Capacity | 14 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | February 2012 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Solar |
| Multiple Fuels | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| DC Net Capacity | 20.8 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | No |
| Virtual Net Metering Agreement | No |
Generator H116M Details Operating April 2023
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Single Owner |
| Nameplate Capacity | 16 MW |
| Summer Capacity | 16 MW |
| Winter Capacity | 16 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2023 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Electricity used for energy storage |
| Time From Cold Shutdown To Full Load | 10M |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 48 |
|---|---|
| Maximum Charge Rate | 16 MW |
| Maximum Discharge Rate | 16 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 5.6 |
| Storage Enclosure Type | CS |
| Load Following | Yes |
| System Peak Shaving | Yes |
| Excess Wind And Solar Generation | Yes |
| Ac Coupled | Yes |
| Direct Support Of Another Unit | Yes |
| Direct Support Plant Id | 57563 |
| Direct Support Gen Id | PV1 |
| Support T D Asset | No |
Hyder Solar Hybrid Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1310 | Nutmeg Solar | Enfield, CT | 34.5 GWh |
| #1311 | RB Inyokern Solar WDAT 1281 (CSG) | Ridgecrest, CA | 34.5 GWh |
| #1312 | Apple Data Center - PV2 | Conover, NC | 34.5 GWh |
| #1313 | Redcrest Solar Farm | Edison, CA | 34.4 GWh |
| #1314 | NY8 - Branscomb Solar | Schaghticoke, NY | 34.3 GWh |
| #1315 | Desert Breeze Solar, LLC | Hinkley, CA | 34.0 GWh |
| #1316 | Pasquotank | Elizabeth City, NC | 34.0 GWh |
| #1317 | Capon Bridge Solar LLC | Augusta, WV | 34.0 GWh |
| #1318 | Colice Hall Solar | Ahoskie, NC | 34.0 GWh |
| #1319 | Atwell Island | Alpaugh, CA | 33.9 GWh |
| #1321 | SR Platte Solar Farm | Platteville, CO | 33.9 GWh |
| #1322 | Holstein Plant | Maxton, NC | 33.8 GWh |
| #1323 | Dane County Solar LLC | Cottage Grove, WI | 33.7 GWh |
| #1324 | Mt. Jackson Solar | Mt. Jackson, VA | 33.5 GWh |
| #1325 | Whitetail Solar 3 | Chambersburg, PA | 33.4 GWh |
| #1326 | Sun City Project LLC | Avenal, CA | 33.4 GWh |
| #1327 | Riverhead Solar Farm | Calverton, NY | 33.4 GWh |
| #1328 | Halifax (NC) | Roanoke Rapids, NC | 33.4 GWh |
| #1329 | Paloma Solar Hybrid | Gila Bend, AZ | 30.2 GWh |
| #1330 | Saddle Mountain Solar I | Tonopah, AZ | 33.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Hyder Solar Hybrid.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Agua Caliente Solar Project | Dateland, AZ | 524.8 GWh | 9.3 mi |
| Arlington Valley Energy Facility | Arlington, AZ | 3.2 TWh | 34.2 mi |
| Arlington Valley Solar Energy I | Arlington, AZ | 66.2 GWh | 33.7 mi |
| Arlington Valley Solar Energy II | Arlington, AZ | 336.0 GWh | 35.3 mi |
| Gila Bend Hybrid | Gila Bend, AZ | 72.1 GWh | 27.4 mi |
| Harquahala 2 | Tonopah, AZ | 850.8 GWh | 32.9 mi |
| Harquahala Generating Project | Tonopah, AZ | 3.1 TWh | 33.8 mi |
| Harquahala Sun Solar Project | Tonopah, AZ | 470.4 GWh | 31.1 mi |
| Hyder II Hybrid | Hyder, AZ | 25.3 GWh | 0.3 mi |
| McFarland A Solar and Storage | Dateland, AZ | 550.8 GWh | 9.9 mi |
| McFarland B Solar and Storage | Dateland, AZ | 749.4 GWh | 9 mi |
| Mesquite Generating Station Block 2 | Arlington, AZ | 3.8 TWh | 35.4 mi |
| Mesquite Solar 1 | Tonopah, AZ | 392.2 GWh | 33.5 mi |
| Mesquite Solar 2, LLC | Tonopah, AZ | 256.7 GWh | 32.8 mi |
| Mesquite Solar 3, LLC | Tonopah, AZ | 445.9 GWh | 32.4 mi |
| Mesquite Solar 4, LLC | Tonopah, AZ | 142.1 GWh | 32.2 mi |
| Mesquite Solar 5, LLC | Tonopah, AZ | 129.1 GWh | 32.2 mi |
| Saddle Mountain Solar I | Tonopah, AZ | 33.3 GWh | 26.1 mi |
| Solana Generating Station | Gila Bend, AZ | 863.7 GWh | 23.6 mi |
| White Wing Solar | Yuma, AZ | 455.8 GWh | 9.8 mi |