Cedar Springs II
460 Sixteen Mile Rd, Douglas, WY 82633Plant Summary Information
Cedar Springs II is ranked #14 out of 69 power plants in Wyoming in terms of total annual net electricity generation.
Cedar Springs II generated 165.6 GWh during the 3-month period between March 2026 to June 2026.
| Plant Name | Cedar Springs II |
|---|---|
| Utility Name | PacifiCorp |
| Location | Converse County, WY |
| Initial Operation Date | December 2020 |
| Last Update | Jun 2026 |
| Annual Generation | 747.1 GWh |
| Annual Consumption | 2.7 M MMBtu |
| Ranked #963 out of 13,094 Power Plants Nationwide | |
| Ranked #184 out of 1,369 Wind Power Plants Nationwide | |
| Ranked #14 out of 69 Wyoming Power Plants | |
| Ranked #7 out of 27 Wyoming Wind Power Plants | |
| Fuel Types | Wind |
| Previous Operator |
Cedar Springs Transmission, LLC (2019 to 2019) PacifiCorp (2020 to 2025) |
Map of Cedar Springs II
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Cedar Springs II.
Monthly Net Generation for Cedar Springs II
Monthly Plant Fuel Consumption for Cedar Springs II
Cedar Springs II Details
| Summary Information | |
|---|---|
| Plant Name | Cedar Springs II (63915) |
| Plant Address | 460 Sixteen Mile Rd, Douglas, WY 82633 |
| Utility | PacifiCorp (14354) |
| Latitude, Longitude | 42.96901, -105.36562 |
| Generation Dates on File | Dec 2020 to Jun 2026 |
| Initial Operation Date | December 2020 |
| Annual Generation | 747.1 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | WECC |
| Balancing Authority | PacifiCorp - East (PACE) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | PacifiCorp (14354) WY |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator 82634 Details Operating December 2020
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 200 MW |
| Summer Capacity | 198.8 MW |
| Winter Capacity | 198.8 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2020 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 72 |
| Turbine Details | |
| Number Of Turbines | 72 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.82-127 |
| Design Wind Speed | 19 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 292 |
Cedar Springs II Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #174 | Plymouth Wind | Remsen, IA | 766.9 GWh |
| #175 | Cimarron Bend Wind Project II, LLC | Minneola, KS | 761.8 GWh |
| #176 | Buffalo Dunes Wind Project | Satanta, KS | 761.8 GWh |
| #177 | Javelina Wind Energy II, LLC | MIRANDO, TX | 761.6 GWh |
| #178 | Bright Stalk Wind Farm I | Chenoa, IL | 759.8 GWh |
| #179 | Miami Wind Energy Center | Miami, TX | 756.2 GWh |
| #180 | Las Majadas Wind Farm | Santa Monica, TX | 756.0 GWh |
| #181 | King Plains Wind Project | Garber, OK | 751.5 GWh |
| #182 | Cimarron Bend Wind Project I, LLC | Minneola, KS | 748.8 GWh |
| #183 | Cedar Springs I | Douglas, WY | 748.1 GWh |
| #185 | Aragonne Wind LLC | Santa Rosa, NM | 746.9 GWh |
| #186 | Griffin Trail Wind | E Seymour, TX | 738.8 GWh |
| #187 | Diversion Wind Energy LLC | Seymour, TX | 738.1 GWh |
| #188 | Tucannon River Wind Farm | Dayton, WA | 736.8 GWh |
| #189 | Upstream Wind Energy LLC | Neligh, NE | 735.2 GWh |
| #190 | Roosevelt County | Portales, NM | 734.4 GWh |
| #191 | Great Pathfinder Wind | Stratford, IA | 731.4 GWh |
| #192 | Cross Winds Energy Park | Unionville, MI | 728.2 GWh |
| #193 | South Plains Wind Phase I | Floydada, TX | 724.7 GWh |
| #194 | Pryor Mountain Wind | Bridger, MT | 722.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Cedar Springs II.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Alcova | Alcova, WY | 107.2 GWh | 74.5 mi |
| Anticline Wind | Casper, WY | 425.5 GWh | 51 mi |
| Barber Creek | Gillette, WY | 294.0 MWh | 55.8 mi |
| Boswell Wind | Rock River, WY | 1.2 TWh | 77 mi |
| Campbell Hill Windpower | Glenrock, WY | 268.0 GWh | 32.2 mi |
| Cedar Springs I | Douglas, WY | 748.1 GWh | 6.4 mi |
| Cedar Springs III | Douglas, WY | 494.3 GWh | 13.3 mi |
| Cedar Springs Wind IV | Douglas, WY | 1.3 TWh | 19.7 mi |
| Dave Johnston | Glen Rock, WY | 3.1 TWh | 22.7 mi |
| Dunlap | Medicine Bow, WY | 416.7 GWh | 75.7 mi |
| Fremont Canyon | Alcova, WY | 233.5 GWh | 80.2 mi |
| Glendo | Glendo, WY | 67.3 GWh | 40.4 mi |
| Glenrock | Glenrock, WY | 469.2 GWh | 24 mi |
| Guernsey | Guernsey, WY | 14.6 GWh | 56.1 mi |
| Hartzog | Wright, WY | 148.0 MWh | 60 mi |
| Laramie River Station | Wheatland, WY | 7.9 TWh | 64.3 mi |
| Pioneer Wind Park, LLC | Glenrock, WY | 252.6 GWh | 30.4 mi |
| Rolling Hills | Glenrock, WY | 295.1 GWh | 25.4 mi |
| TB Flats | Medicine Bow, WY | 1.4 TWh | 70.3 mi |
| Top of the World Windpower Project | Glenrock, WY | 542.2 GWh | 21.5 mi |