Brady Wind Energy Center
5206 109th Ave SW, Dickinson, ND 58601Plant Summary Information
Brady Wind Energy Center is ranked #16 out of 57 power plants in North Dakota in terms of total annual net electricity generation.
Brady Wind Energy Center generated 170.5 GWh during the 3-month period between September 2024 to December 2024.
Plant Name | Brady Wind Energy Center |
---|---|
Utility Name | Brady Wind, LLC |
Location | Stark County, ND |
Initial Operation Date | November 2016 |
Last Update | Dec 2024 |
Annual Generation | 632.3 GWh |
Annual Consumption | 2.4 M MMBtu |
Ranked #1,081 out of 12,288 Power Plants Nationwide | |
Ranked #247 out of 1,353 Wind Power Plants Nationwide | |
Ranked #16 out of 57 North Dakota Power Plants | |
Ranked #8 out of 40 North Dakota Wind Power Plants | |
Fuel Types | Wind |
Map of Brady Wind Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Brady Wind Energy Center.
Monthly Net Generation for Brady Wind Energy Center
Brady Wind Energy Center Details
Summary Information | |
---|---|
Plant Name | Brady Wind Energy Center (60355) |
Plant Address | 5206 109th Ave SW, Dickinson, ND 58601 |
Utility | Brady Wind, LLC (60148) |
Latitude, Longitude | 46.64647, -102.76509 |
Generation Dates on File | Nov 2016 to Dec 2024 |
Initial Operation Date | November 2016 |
Annual Generation | 632.3 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | No |
Transmission / Distribution Owner | Basin Electric Power Coop (1307) ND |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator BWEC1 Details Operating November 2016
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 150 MW |
Summer Capacity | 150 MW |
Winter Capacity | 150 MW |
Minimum Load | 37 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | November 2016 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 87 |
Turbine Details | |
Number Of Turbines | 87 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 1.79-100 |
Design Wind Speed | 19 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 315 |
Brady Wind Energy Center Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#237 | Horizon Hill Wind Project | Crescent, OK | 654.8 GWh |
#238 | Bloom Wind | Minneola, KS | 651.3 GWh |
#239 | Minonk Wind Farm | Minonk, IL | 651.1 GWh |
#240 | Foxtail Wind, LLC | Forbes, ND | 649.3 GWh |
#241 | Merricourt Wind Energy Center | Kulm, ND | 645.3 GWh |
#242 | FPL Energy Illinois Wind LLC Hybrid | Shabbona, IL | 639.7 GWh |
#243 | Sweetwater Wind 4 LLC | Roscoe, TX | 636.6 GWh |
#244 | South Plains Wind Phase I | Floydada, TX | 634.2 GWh |
#245 | Raymond Wind Farm, LLC | Lyford, TX | 633.6 GWh |
#246 | El Algodon Alto Wind Farm, LLC | Mathis, TX | 632.9 GWh |
#248 | Coyote Wind LLC | Snyder, TX | 632.1 GWh |
#249 | Patriot Wind Farm | Bishop, TX | 632.0 GWh |
#250 | Wild Horse | Ellensburg, WA | 631.0 GWh |
#251 | Tatanka Ridge | Toronto, SD | 627.1 GWh |
#252 | Caney River Wind Project | Howard, KS | 626.6 GWh |
#253 | Bison 4 Wind Energy Center | New Salem, ND | 624.2 GWh |
#254 | Headwaters Wind Farm LLC | Winchester, IN | 622.9 GWh |
#255 | Cedar Springs II | Douglas, WY | 622.5 GWh |
#256 | FPL Energy Crystal Lake Wind LLC | Britt, IA | 618.3 GWh |
#257 | Pilot Hill Wind Farm | Herscher, IL | 618.3 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Brady Wind Energy Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Antelope Valley | Beulah, ND | 5.2 TWh | 66.5 mi |
Bison 2 Wind Energy Center | New Salem, ND | 218.7 GWh | 61.7 mi |
Bison 3 Wind Energy Center | New Salem, ND | 223.3 GWh | 61.7 mi |
Bison 4 Wind Energy Center | New Salem, ND | 624.2 GWh | 61.7 mi |
Bison I Wind Energy Center | New Salem, ND | 165.9 GWh | 61.7 mi |
Brady II Wind Energy Center | Dickinson, ND | 675.7 GWh | 2.7 mi |
Cedar Hills Wind Farm | Rhame, ND | 55.6 GWh | 55.2 mi |
Coyote | Beulah, ND | 2.1 TWh | 59.9 mi |
Diamond Willow Wind Facility | Baker, MT | 86.0 GWh | 72.2 mi |
FPL Energy Oliver Wind I LLC | Center, ND | 176.8 GWh | 81.8 mi |
FPL Energy Oliver Wind II LLC | Center, ND | 180.9 GWh | 81.8 mi |
Garrison | Riverside, ND | 2.1 TWh | 86.5 mi |
Glen Ullin Energy Center | Glen Ullin, ND | 453.5 GWh | 49.9 mi |
Glen Ullin Station 6 | Glen Ullin, ND | 37.6 GWh | 49.3 mi |
Leland Olds | Stanton, ND | 3.0 TWh | 81 mi |
Milton R Young | Center, ND | 4.2 TWh | 78.8 mi |
Oliver Wind III, LLC | Mandan, ND | 434.2 GWh | 78.5 mi |
Oliver Wind IV | Hannover, ND | 248.3 GWh | 63.7 mi |
Sunflower Wind Project | Mandan, ND | 457.5 GWh | 35.3 mi |
Thunder Spirit Wind, LLC | Hettinger, ND | 522.6 GWh | 40.6 mi |