Brady II Wind Energy Center
5206 109th AVE SW, Dickinson, ND 58601Plant Summary Information
Brady II Wind Energy Center is ranked #13 out of 57 power plants in North Dakota in terms of total annual net electricity generation.
Brady II Wind Energy Center generated 189.3 GWh during the 3-month period between December 2024 to March 2025.
Plant Name | Brady II Wind Energy Center |
---|---|
Utility Name | Brady Wind II, LLC |
Location | Stark County, ND |
Initial Operation Date | December 2016 |
Last Update | Mar 2025 |
Annual Generation | 675.7 GWh |
Annual Consumption | 2.5 M MMBtu |
Ranked #1,030 out of 12,288 Power Plants Nationwide | |
Ranked #229 out of 1,353 Wind Power Plants Nationwide | |
Ranked #13 out of 57 North Dakota Power Plants | |
Ranked #5 out of 40 North Dakota Wind Power Plants | |
Fuel Types | Wind |
Map of Brady II Wind Energy Center
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Brady II Wind Energy Center.
Monthly Net Generation for Brady II Wind Energy Center
Brady II Wind Energy Center Details
Summary Information | |
---|---|
Plant Name | Brady II Wind Energy Center (60354) |
Plant Address | 5206 109th AVE SW, Dickinson, ND 58601 |
Utility | Brady Wind II, LLC (60149) |
Latitude, Longitude | 46.61152, -102.78821 |
Generation Dates on File | Dec 2016 to Mar 2025 |
Initial Operation Date | December 2016 |
Annual Generation | 675.7 GWh |
Fuel Types | Wind |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Non-Regulated |
NERC Region | MRO |
Balancing Authority | Southwest Power Pool (SWPP) |
NAICS Code | Utilities (22) |
Sector | IPP Non-CHP (2) |
Water Source | |
Ash Impoundment | |
Transmission / Distribution Owner | Basin Electric Power Coop (1307) ND |
Grid Voltage | 230.00 kV |
Energy Storage | No |
Generator BWEC2 Details Operating December 2016
Technology | Onshore Wind Turbine |
---|---|
Prime Mover | Wind Turbine, Onshore |
Ownership | Single Owner |
Nameplate Capacity | 150 MW |
Summer Capacity | 150 MW |
Winter Capacity | 150 MW |
Minimum Load | 37 MW |
Uprate/Derate Completed | No |
---|---|
Status | Operating |
First Operation Date | December 2016 |
Combined Heat & Power | No |
Sector Name | IPP Non-CHP (2) |
Energy Source | Wind |
Turbines/Hydrokinetic Buoys | 72 |
Turbine Details | |
Number Of Turbines | 72 |
---|---|
Predominant Turbine Manufacturer | GE |
Predominant Turbine Model Number | 2.0-116 |
Design Wind Speed | 19 MPH |
Wind Quality Class | 2 - Medium Wind |
Turbine Hub Height Feet | 315 |
Brady II Wind Energy Center Plant Owners
Owner Name | Address | Ownership | |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#219 | Javelina Wind Energy II, LLC | MIRANDO, TX | 688.7 GWh |
#220 | Sugar Creek Wind One LLC | TBD, IL | 687.5 GWh |
#221 | Peetz Table Wind Energy | Peetz, CO | 687.0 GWh |
#222 | Cedar Point Wind | Limon, CO | 684.0 GWh |
#223 | Buckeye Wind Energy Center | Hays, KS | 683.4 GWh |
#224 | Wildcat Ranch Wind Project | Morton, TX | 682.2 GWh |
#225 | Meadow Lake Wind Farm VI LLC | Remington, IN | 681.7 GWh |
#226 | Oso Grande Wind Farm | Maljamar, NM | 680.6 GWh |
#227 | Chickasaw Wind Farm | New Hampton, IA | 676.5 GWh |
#228 | Reading Wind Project | Reading, KS | 676.4 GWh |
#230 | Wildcat Wind Farm I, LLC | Elwood, IN | 673.8 GWh |
#231 | Windy Flats Wind Project | Centerville, WA | 671.6 GWh |
#232 | Glacier Sands Wind Power, LLC | Mason City, IL | 670.8 GWh |
#233 | Seiling Wind I | Seiling, OK | 669.0 GWh |
#234 | Kelly Creek Wind Project | Cabery, IL | 666.6 GWh |
#235 | Roadrunner Wind Farm | Cisco, TX | 666.3 GWh |
#236 | Brazos Wind Farm | Fluvanna, TX | 658.7 GWh |
#237 | Horizon Hill Wind Project | Crescent, OK | 654.8 GWh |
#238 | Bloom Wind | Minneola, KS | 651.3 GWh |
#239 | Minonk Wind Farm | Minonk, IL | 651.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Brady II Wind Energy Center.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Antelope Valley | Beulah, ND | 5.2 TWh | 69 mi |
Bison 2 Wind Energy Center | New Salem, ND | 218.7 GWh | 63.7 mi |
Bison 3 Wind Energy Center | New Salem, ND | 223.3 GWh | 63.7 mi |
Bison 4 Wind Energy Center | New Salem, ND | 624.2 GWh | 63.7 mi |
Bison I Wind Energy Center | New Salem, ND | 165.9 GWh | 63.7 mi |
Brady Wind Energy Center | Dickinson, ND | 632.3 GWh | 2.7 mi |
Cedar Hills Wind Farm | Rhame, ND | 55.6 GWh | 53 mi |
Coyote | Beulah, ND | 2.1 TWh | 62.3 mi |
Diamond Willow Wind Facility | Baker, MT | 86.0 GWh | 70.4 mi |
FPL Energy Oliver Wind I LLC | Center, ND | 176.8 GWh | 83.9 mi |
FPL Energy Oliver Wind II LLC | Center, ND | 180.9 GWh | 83.9 mi |
Garrison | Riverside, ND | 2.1 TWh | 89 mi |
Glen Ullin Energy Center | Glen Ullin, ND | 453.5 GWh | 52 mi |
Glen Ullin Station 6 | Glen Ullin, ND | 37.6 GWh | 51 mi |
Leland Olds | Stanton, ND | 3.0 TWh | 83.2 mi |
Milton R Young | Center, ND | 4.2 TWh | 80.8 mi |
Oliver Wind III, LLC | Mandan, ND | 434.2 GWh | 80.3 mi |
Oliver Wind IV | Hannover, ND | 248.3 GWh | 65.9 mi |
Sunflower Wind Project | Mandan, ND | 457.5 GWh | 37.2 mi |
Thunder Spirit Wind, LLC | Hettinger, ND | 522.6 GWh | 38.6 mi |