| Aberdeen CT | NorthWestern Energy - (SD) | Aberdeen, SD | 56 GWh | Apr 1978 | Dec 2025 |
Natural Gas
|
| Elk Station | Golden Spread Electric Cooperative, Inc | Abernathy, TX | 891 GWh | May 2015 | Dec 2025 |
Natural Gas
|
| Antelope Station | Golden Spread Electric Cooperative, Inc | Abernathy, TX | 297 GWh | May 2011 | Dec 2025 |
Natural Gas
|
| Adrian | Adrian Public Utilities Comm | Adrian, MN | 12 MWh | Apr 2005 | Dec 2025 |
Distillate Fuel Oil
|
| Ainsworth Wind | Nebraska Public Power District | Ainsworth, NE | 66 GWh | Sep 2005 | Dec 2025 |
Wind
|
| Alexander Wind Farm LLC | SRIV Partnership LLC | Alexander, KS | 168 GWh | Nov 2015 | Dec 2025 |
Wind
|
| Lonesome Creek Station | Basin Electric Power Coop | Alexander, ND | 842 GWh | Oct 2013 | Dec 2025 |
Natural Gas
|
| Iowa Distributed Wind Generation Project | City of Algona - (IA) | Algona, IA | 4 GWh | May 2000 | Dec 2025 |
Wind
|
| Algona | City of Algona - (IA) | Algona, IA | 449 MWh | Nov 1965 | Dec 2025 |
Distillate Fuel Oil : 95.0%
Natural Gas : 5.0%
|
| Alta Municipal Utilities | City of Alta - (IA) | Alta, IA | 54 MWh | Jul 1947 | Dec 2025 |
Distillate Fuel Oil
|
| Waynoka Gas Processing Plant | Targa Pipeline Mid-Continent West OK LLC | Alva, OK | 18 GWh | Jun 2006 | Jul 2026 |
Natural Gas
|
| Sundance Wind Project, LLC | Public Service Co of Oklahoma | Alva, OK | 654 GWh | Mar 2021 | Jul 2026 |
Wind
|
| Harrington | Southwestern Public Service Co | Amarillo, TX | 2 TWh | Dec 1975 | Jul 2026 |
Natural Gas
|
| Nichols | Southwestern Public Service Co | Amarillo, TX | 2 TWh | Dec 1959 | Dec 2025 |
Natural Gas
|
| Pantex | Pantex (NNSA) | Amarillo, TX | 40 GWh | May 2014 | Jul 2026 |
Wind
|
| Anadarko Plant | Western Farmers Elec Coop, Inc | Anadarko, OK | 683 GWh | Jul 1953 | Jul 2026 |
Natural Gas
|
| Southwestern | Public Service Co of Oklahoma | Anadarko, OK | 453 GWh | Jun 1952 | Dec 2025 |
Natural Gas
|
| WFEC GenCo LLC | Western Farmers Elec Coop, Inc | Anadarko, OK | 84 GWh | Apr 2001 | Dec 2024 |
Natural Gas
|
| White Rock East Wind Project | White Rock Wind East, LLC | Anadarko, OK | 711 GWh | Dec 2023 | Jul 2026 |
Wind
|
| White Rock West Wind Project | White Rock Wind West, LLC | Anadarko, OK | 391 GWh | Nov 2023 | Jul 2026 |
Wind
|
| Prairie Sky Solar Farm | Kansas Electric Power Coop Inc | Andover, KS | 2 GWh | Jan 2017 | Dec 2025 |
Solar
|
| Pratt Wind, LLC | Pratt Wind, LLC | Andover, KS | 866 GWh | Nov 2018 | Jul 2026 |
Wind
|
| Ansley | City of Ansley - (NE) | Ansley, NE | 59 MWh | May 1969 | Dec 2025 |
Natural Gas : 63.5%
Distillate Fuel Oil : 36.5%
|
| Anthony | City of Anthony - (KS) | Anthony, KS | 13 MWh | Jul 1972 | Dec 2025 |
Natural Gas : 94.1%
Distillate Fuel Oil : 5.9%
|
| Caddo Wind | ALLETE Clean Energy | Apache, OK | 973 GWh | Dec 2021 | Jul 2026 |
Wind
|
| Pine Ridge | Western Farmers Elec Coop, Inc | Apache, OK | 5 GWh | Feb 2017 | Jul 2026 |
Solar
|
| Oak Grove Power Producers | Cube District Energy, LLC | Arcadia, KS | 11 GWh | Feb 2010 | Dec 2025 |
Landfill Gas
|
| Great Western Wind Energy, LLC | EDF Renewable Asset Holdings, Inc. | Arnett, OK | 958 GWh | Nov 2016 | Jul 2026 |
Wind
|
| Ashdown | Domtar Industries Inc | Ashdown, AR | 576 GWh | Dec 1967 | Jul 2026 |
Black Liquor : 68.7%
Wood/Wood Waste Solids : 12.0%
Natural Gas : 11.5%
Bituminous Coal : 6.3%
Tire-derived Fuels : 1.5%
|
| Ashland | City of Ashland - (KS) | Ashland, KS | 32 MWh | Aug 1953 | Dec 2025 |
Distillate Fuel Oil
|
| Platteview Solar LLC | AES Distributed Energy | Ashland, NE | 151 GWh | Apr 2024 | Jul 2026 |
Solar
|
| Auburn | Auburn Board of Public Works | Auburn, NE | 31 MWh | May 1949 | Dec 2025 |
Natural Gas : 70.4%
Distillate Fuel Oil : 29.6%
|
| Augusta Electric Plant No 1 | City of Augusta - (KS) | Augusta, KS | 5 MWh | Jul 1929 | Dec 2025 |
Distillate Fuel Oil
|
| Augusta Electric Plant No 2 | City of Augusta - (KS) | Augusta, KS | 832 MWh | Jun 1968 | Dec 2025 |
Natural Gas : 92.3%
Distillate Fuel Oil : 7.7%
|
| ABIA Parking Structure | SoCore Energy LLC | Austin, TX | 3 GWh | Mar 2021 | Dec 2025 |
Solar
|
| Wilkes | Southwestern Electric Power Co | Avinger, TX | 995 GWh | Apr 1964 | Dec 2025 |
Natural Gas
|
| Baldwin City Plant No 1 | City of Baldwin City- (KS) | Baldwin City, KS | 13 MWh | Apr 1956 | Dec 2025 |
Distillate Fuel Oil
|
| Baldwin City Plant No 2 | City of Baldwin City- (KS) | Baldwin City, KS | 122 MWh | Jul 2004 | Dec 2025 |
Distillate Fuel Oil : 76.4%
Natural Gas : 23.6%
|
| Balko Wind LLC | Balko Wind LLC | Balko, OK | 516 GWh | Jul 2015 | Jul 2026 |
Wind
|
| Ponderosa Wind II | Ponderosa Wind II, LLC | Balko, OK | 465 GWh | Nov 2024 | Jul 2026 |
Wind
|
| Beatrice | Nebraska Public Power District | Beatrice, NE | 356 GWh | Dec 2004 | Dec 2025 |
Natural Gas
|
| Elk River Wind | Avangrid Power LLC | Beaumont, KS | 265 GWh | Nov 2005 | Dec 2025 |
Wind
|
| Ponderosa Wind Energy Center | Ponderosa Wind, LLC | Beaver, OK | 937 GWh | Oct 2020 | Jul 2026 |
Wind
|
| Bluestem | Bluestem Wind Energy, LLC | Beaver, OK | 794 GWh | Nov 2016 | Jul 2026 |
Wind
|
| High Banks Wind | High Banks Wind, LLC | Belleville, KS | 2 TWh | Nov 2023 | Jul 2026 |
Wind
|
| Belleville | City of Belleville - (KS) | Belleville, KS | 513 MWh | Dec 1954 | Dec 2025 |
Distillate Fuel Oil : 79.7%
Natural Gas : 20.3%
|
| Sarpy County | Omaha Public Power District | Bellevue, NE | 179 GWh | May 1972 | Dec 2025 |
Natural Gas : 95.0%
Distillate Fuel Oil : 5.0%
|
| Papillion Creek Wastewater | City of Omaha - (NE) | Bellevue, NE | 3 GWh | Apr 1987 | Jul 2026 |
Natural Gas : 78.6%
Other Biomass Gas : 21.4%
|
| Beloit | City of Beloit - (KS) | Beloit, KS | 47 MWh | Apr 1950 | Dec 2025 |
Natural Gas : 79.0%
Distillate Fuel Oil : 21.0%
|
| Beloit Solar LLC | PPM Solar LLC | Beloit, KS | 4 GWh | May 2022 | Dec 2025 |
Solar
|
| Elk City Station | Omaha Public Power District | Bennington, NE | 39 GWh | Mar 2002 | Oct 2025 |
Landfill Gas
|
| XNA (NW AR Natnl Airport) | Today's Power, Inc. | Bentonville, AR | 1 GWh | Sep 2025 | Dec 2025 |
Solar
|
| City of Green Forest (Carroll) | Entegrity Solar Green Forest, LLC | Berryville, AR | 2 GWh | Dec 2021 | Dec 2025 |
Solar
|
| Antelope Valley | Basin Electric Power Coop | Beulah, ND | 6 TWh | Jun 1984 | Jul 2026 |
Lignite Coal : 99.4%
Natural Gas : 0.6%
|
| Frontier Windpower II | Deriva Energy | Blackwell, OK | 765 GWh | Jan 2021 | Jul 2026 |
Wind
|
| NextEra-Blackwell Wind, LLC | Blackwell Wind, LLC | Blackwell, OK | 83 GWh | Nov 2012 | Dec 2025 |
Wind
|
| Crofton Bluffs Wind LLC | Crofton Bluffs Wind, LLC | Bloomfield, NE | 108 GWh | Oct 2012 | Dec 2025 |
Wind
|
| Elkhorn Ridge Wind LLC | Elkhorn Ridge Wind, LLC | Bloomfield, NE | 142 GWh | Feb 2009 | Dec 2025 |
Wind
|
| City Light & Water | City of Blue Hill - (NE) | Blue Hill, NE | 24 MWh | Dec 1986 | Dec 2025 |
Distillate Fuel Oil
|
| Little Blue Wind Project, LLC | Little Blue Wind Project, LLC | Blue Hill, NE | 877 GWh | Nov 2021 | Jul 2026 |
Wind
|
| Cottonwood Wind Energy Center | Cottonwood Wind Project | Blue Hill, NE | 365 GWh | Oct 2017 | Jul 2026 |
Wind
|
| Thunderhead Wind Energy LLC | Invenergy Services LLC | Boone, NE | 1 TWh | Oct 2022 | Jul 2026 |
Wind
|
| Black Hawk Station | Borger Energy Associates LP | Borger, TX | 1 TWh | May 1999 | Jul 2026 |
Natural Gas : 86.0%
Other Gas : 14.0%
|
| Engineered Carbons Borger Cogen | Orion Engineered Carbons | Borger, TX | 32 GWh | Sep 1982 | Dec 2025 |
Other Gas : 99.5%
|
| Burke Wind, LLC | Burke Wind LLC | Bowbells, ND | 796 GWh | Nov 2020 | Jul 2026 |
Wind
|
| Bowman Wind | Bowman Wind, LLC | Bowman, ND | 604 GWh | Oct 2025 | Jul 2026 |
Wind
|
| Jeffrey | Central Nebraska Pub P&I Dist | Brady, NE | 81 GWh | Dec 1940 | Dec 2025 |
Water
|
| Rock Falls Wind Farm LLC | Public Service Co of Oklahoma | Braman, OK | 387 GWh | Nov 2017 | Jan 2026 |
Wind
|
| Branch Solar Farm | Oklahoma Gas & Electric Co | Branch, AR | 7 GWh | Sep 2021 | Dec 2025 |
Solar
|
| Exira | Western Minnesota Mun Pwr Agny | Brayton, IA | 243 GWh | Mar 2004 | Dec 2025 |
Natural Gas : 99.0%
Distillate Fuel Oil : 1.0%
|
| Oneta Energy Center | Oneta Power LLC | Broken Arrow, OK | 4 TWh | Jun 2002 | Jul 2026 |
Natural Gas
|
| Broken Bow Wind LLC | Broken Bow Wind LLC | Broken Bow, NE | 222 GWh | Nov 2012 | Dec 2025 |
Wind
|
| Broken Bow | City of Broken Bow - (NE) | Broken Bow, NE | 21 MWh | Nov 1936 | Dec 2025 |
Distillate Fuel Oil : 85.8%
Natural Gas : 14.2%
|
| Broken Bow Wind II, LLC | RWE Clean Energy | Broken Bow, NE | 240 GWh | Sep 2014 | Dec 2025 |
Wind
|
| Broken Bow Dam | USCE-Tulsa District | Broken Bow, OK | 196 GWh | Dec 1969 | Dec 2025 |
Water
|
| Cooper Nuclear Station | Nebraska Public Power District | Brownville, NE | 7 TWh | Feb 1974 | Jul 2026 |
Nuclear
|
| Cedar Bluff Wind, LLC | Cedar Bluff Wind, LLC | Brownwell, KS | 776 GWh | Nov 2015 | Dec 2025 |
Wind
|
| Burlingame | City of Burlingame - (KS) | Burlingame, KS | 9 MWh | Jul 1963 | Dec 2025 |
Natural Gas : 95.7%
Distillate Fuel Oil : 4.3%
|
| Burlington (KS) | City of Burlington - (KS) | Burlington, KS | 207 MWh | Jun 1955 | Dec 2025 |
Distillate Fuel Oil
|
| Wolf Creek Generator | 4 Rivers Electric Cooperative, Inc. | Burlington, KS | 106 MWh | Mar 2014 | Dec 2025 |
Distillate Fuel Oil
|
| Wolf Creek Generating Station | Wolf Creek Nuclear Optg Corp | Burlington, KS | 9 TWh | Aug 1985 | Jul 2026 |
Nuclear
|
| DeGraff Butler Electric | Today's Power, Inc. | Burns, KS | 2 GWh | Apr 2021 | Dec 2025 |
Solar
|
| Burwell | City of Burwell - (NE) | Burwell, NE | 147 MWh | Feb 1955 | Dec 2025 |
Distillate Fuel Oil
|
| Butler Solar Power Project | Missouri Jnt Muni.Pwr Elec. Ut. Comm. | Butler, MO | 4 GWh | Feb 2014 | Jul 2026 |
Solar
|
| Butler Municipal Power Plant | City of Butler - (MO) | Butler, MO | 39 MWh | May 1946 | Dec 2025 |
Distillate Fuel Oil
|
| Choctaw Nation Solar Farm | Oklahoma Gas & Electric Co | Calera, OK | 9 GWh | Jun 2020 | Dec 2025 |
Solar
|
| Buzzard Flop | Peoples Electric Cooperative | Calvin, OK | 13 GWh | Mar 2023 | Dec 2025 |
Natural Gas
|
| Cambridge | City of Cambridge - (NE) | Cambridge, NE | 20 MWh | May 2005 | Dec 2025 |
Distillate Fuel Oil
|
| Crossroads Wind Farm | Oklahoma Gas & Electric Co | Canton, OK | 401 GWh | Dec 2011 | Jul 2026 |
Wind
|
| UL Advanced Wind Turbine Test Facility | West Texas A&M University | Canyon, TX | 12 GWh | Dec 2015 | Dec 2025 |
Wind
|
| SPS5 Hopi | SunE SPS5, LLC | Carlsbad, NM | 21 GWh | Nov 2011 | Dec 2025 |
Solar
|
| Blue Canyon Windpower VI LLC | Blue Canyon Windpower VI LLC | Carnegie, OK | 212 GWh | Nov 2011 | Dec 2025 |
Wind
|
| Blue Canyon Windpower V LLC | Blue Canyon Windpower V LLC | Carnegie, OK | 245 GWh | Sep 2009 | Dec 2025 |
Wind
|
| Blue Canyon Windpower II | Blue Canyon Windpower II LLC | Carnegie, OK | 566 GWh | Nov 2005 | Dec 2025 |
Wind
|
| Skeleton Creek Energy Center Hybrid | Skeleton Creek Energy Center | Carrier, OK | 1 TWh | Nov 2020 | Jul 2026 |
Wind : 66.3%
Solar : 33.7%
|
| Haystack Wind Project, LLC | Haystack Wind Project, LLC | Carroll, NE | 861 GWh | Jan 2022 | Jul 2026 |
Wind
|
| Little Dixie | Peoples Electric Cooperative | Centrahoma, OK | 27 GWh | Jun 2019 | Dec 2025 |
Natural Gas
|
| Centrahoma East | Peoples Electric Cooperative | Centrahoma, OK | 74 GWh | Jun 2019 | Dec 2025 |
Natural Gas
|
| Centrahoma West | Peoples Electric Cooperative | Centrahoma, OK | 85 GWh | Jun 2019 | Dec 2025 |
Natural Gas
|
| Big Bend Dam | USACE-Omaha | Chamberlain, SD | 746 GWh | Aug 1964 | Dec 2025 |
Water
|