Zeuber
6383 Zeuber Road, Little Rock, AR 72206Plant Summary Information
Zeuber is ranked #28 out of 71 solar farms in Arkansas in terms of total annual net electricity generation.
Zeuber generated 1.6 GWh during the 3-month period between September 2025 to December 2025.
| Plant Name | Zeuber |
|---|---|
| Utility Name | Today's Power, Inc. |
| Location | Pulaski County, AR |
| Initial Operation Date | December 2023 |
| Last Update | Dec 2025 |
| Annual Generation | 7.0 GWh |
| Annual Consumption | 24.9 k MMBtu |
| Ranked #7,413 out of 13,081 Power Plants Nationwide | |
| Ranked #2,889 out of 7,015 Solar Power Plants Nationwide | |
| Ranked #69 out of 115 Arkansas Power Plants | |
| Ranked #28 out of 71 Arkansas Solar Power Plants | |
| Fuel Types | Solar |
Map of Zeuber
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Zeuber.
Monthly Net Generation for Zeuber
Monthly Plant Fuel Consumption for Zeuber
Zeuber Details
| Summary Information | |
|---|---|
| Plant Name | Zeuber (68740) |
| Plant Address | 6383 Zeuber Road, Little Rock, AR 72206 |
| Utility | Today's Power, Inc. (61204) |
| Latitude, Longitude | 34.6991, -92.21184 |
| Generation Dates on File | Jan 2024 to Dec 2025 |
| Initial Operation Date | December 2023 |
| Annual Generation | 7.0 GWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Regulated |
| NERC Region | SERC |
| Balancing Authority | Midcontinent Independent Transmission System Operator, Inc.. (MISO) |
| NAICS Code | Utilities (22) |
| Sector | Electric Utility (1) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Entergy Arkansas LLC (814) AR |
| Grid Voltage | 12.47 kV / 0.48 kV |
| Energy Storage | No |
Generator PUCOZ Details Operating December 2023
| Technology | Solar Photovoltaic |
|---|---|
| Prime Mover | Photovoltaic |
| Ownership | Single Owner |
| Nameplate Capacity | 4.6 MW |
| Summer Capacity | 4.6 MW |
| Winter Capacity | 4.6 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | December 2023 |
| Combined Heat & Power | No |
| Sector Name | Electric Utility (1) |
| Energy Source | Solar |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Solar Details | |
| Single Axis Tracking | Yes |
|---|---|
| Azimuth Angle | 180 |
| DC Net Capacity | 5.6 MW |
| Crystalline Silicon | Yes |
| Net Metering Agreement | Yes |
| Net Metering DC Capacity | 4.6 MW |
| Virtual Net Metering Agreement | No |
Zeuber Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #2879 | Turkey Branch Solar LLC | Fairmont, NC | 7.0 GWh |
| #2880 | Harding Solar, LLC | Hookerton, NC | 7.0 GWh |
| #2881 | Klamath Falls Solar 2 CSG | Klamath Falls, OR | 7.0 GWh |
| #2882 | Rice Lake Solar Array | Rice Lake, WI | 7.0 GWh |
| #2883 | GMP Solar/Storage-Milton Hybrid | Milton, VT | 7.0 GWh |
| #2884 | Sheesley (CSG) | Canton, NY | 7.0 GWh |
| #2885 | Lady Slipper Solar Array CSG | Red Wing, MN | 7.0 GWh |
| #2886 | GCC Trident Solar Project | Three Forks, MT | 7.0 GWh |
| #2887 | NY Grand Island 871 Whitehaven Rd Solar | Grand Island, NY | 7.0 GWh |
| #2888 | New Bedford (MA) Plymouth | Plymouth, MA | 7.0 GWh |
| #2890 | Mass Midstate Solar 2 | Warren, MA | 7.0 GWh |
| #2891 | Goose Pond Solar | Southwick, MA | 7.0 GWh |
| #2892 | Meadowbrook Solar Farm | Rockwell, NC | 7.0 GWh |
| #2893 | Middleton Solar Park | Middleton, MA | 6.8 GWh |
| #2894 | Hunt Road Solar | Amesbury, MA | 7.0 GWh |
| #2895 | Raffia Road Solar Project | Enfield, CT | 7.0 GWh |
| #2896 | SunE CPS2 LLC | San Antonio, TX | 7.0 GWh |
| #2897 | OYA Pulaski | Pulaski, NY | 6.9 GWh |
| #2898 | Milford 2 | Milford, UT | 6.9 GWh |
| #2899 | State Highway 17B Solar | Bethel, NY | 6.9 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Zeuber.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| C&L | Star City, AR | 2.2 GWh | 48.3 mi |
| Happy Solar 1 | Searcy, AR | 214.3 GWh | 45 mi |
| Harry L. Oswald | Little Rock, AR | 929.3 GWh | 7.4 mi |
| Hot Spring Generating Facility | Malvern, AR | 3.1 TWh | 46.6 mi |
| Lake Catherine | Jones Mill, AR | 336.2 GWh | 43.5 mi |
| Magnet Cove | Malvern, AR | 3.7 TWh | 39.9 mi |
| Murray | North Little Rock, AR | 116.4 GWh | 10.6 mi |
| NLRED 2MW | North Little Rock, AR | 4.5 GWh | 3.4 mi |
| NLRED 5MW | North Little Rock, AR | 11.3 GWh | 3.6 mi |
| Pine Bluff Energy Center | Pine Bluff, AR | 943.4 GWh | 37.6 mi |
| Redfield Solar | Sheridan, AR | 36.3 GWh | 29.6 mi |
| Remmel | Malvern, AR | 46.1 GWh | 43.1 mi |
| Searcy Solar Hybrid | Searcy, AR | 178.0 GWh | 47.3 mi |
| Searcy Water I | Searcy, AR | 834.0 MWh | 48.2 mi |
| Searcy Water II | Searcy, AR | 3.5 GWh | 44.8 mi |
| Southside SD | Little Rock, AR | 1.7 GWh | 1.9 mi |
| Stuttgart Solar | Stuttgart, AR | 149.5 GWh | 47.4 mi |
| Two Pine Landfill Gas Recovery | North Little Rock, AR | 29.8 GWh | 9.8 mi |
| Whillock | Morrilton, AR | 130.9 GWh | 44.2 mi |
| White Bluff | Redfield, AR | 3.6 TWh | 19.5 mi |