Walnut Unified School District Walnut HS

400 Pierre Rd, Walnut, CA 91789

Plant Summary Information

Walnut Unified School District Walnut HS is ranked #816 out of 849 solar farms in California in terms of total annual net electricity generation.

Walnut Unified School District Walnut HS generated 336.0 MWh during the 3-month period between September 2024 to December 2024.

Plant NameWalnut Unified School District Walnut HS
Utility NameTesla Inc.
LocationLos Angeles County, CA
Initial Operation DateFebruary 2020
Last Update Dec 2024
Annual Generation 809.0 MWh
Annual Consumption 3.1 k MMBtu
Ranked #11,520 out of 12,539 Power Plants Nationwide
Ranked #6,163 out of 6,400 Solar Power Plants Nationwide
Ranked #1,550 out of 1,600 California Power Plants
Ranked #816 out of 849 California Solar Power Plants
Fuel Types Solar

Map of Walnut Unified School District Walnut HS

Full Screen Map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Walnut Unified School District Walnut HS.

Create Your Account Today

Monthly Net Generation for Walnut Unified School District Walnut HS

Walnut Unified School District Walnut HS Details

Summary Information
Plant NameWalnut Unified School District Walnut HS (63510)
Plant Address400 Pierre Rd, Walnut, CA 91789
UtilityTesla Inc. (57313)
Latitude, Longitude34.02188, -117.85051
Generation Dates on FileFeb 2020 to Dec 2024
Initial Operation DateFebruary 2020
Annual Generation 809.0 MWh
Fuel Types Solar
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionWECC
Balancing AuthorityCalifornia Independent System Operator (CISO)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment
Transmission / Distribution OwnerSouthern California Edison Co (17609) CA
Grid Voltage 33.30 kV / 36.60 kV
Energy StorageYes

Generator PV1 Details Operating February 2020

TechnologySolar Photovoltaic
Prime MoverPhotovoltaic
OwnershipWholly Owned by Other Entity
Nameplate Capacity1.8 MW
Summer Capacity1.8 MW
Winter Capacity1.8 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2020
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceSolar
Time From Cold Shutdown To Full Load10M
Solar Details
Fixed TiltYes
Azimuth Angle260
Tilt Angle5
DC Net Capacity2.2 MW
Crystalline SiliconYes
Net Metering AgreementYes
Net Metering DC Capacity1.5 MW
Virtual Net Metering AgreementNo

Generator ST1 Details Operating February 2020

TechnologyBatteries
Prime MoverBattery
OwnershipWholly Owned by Other Entity
Nameplate Capacity0.5 MW
Summer Capacity0.5 MW
Winter Capacity0.5 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateFebruary 2020
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceElectricity used for energy storage
Time From Cold Shutdown To Full Load10M
Energy Storage Details
Nameplate Energy Capacity MWH0.5
Maximum Charge Rate0.1 MW
Maximum Discharge Rate0.1 MW
Storage TechnologyLIB
Nameplate Reactive Power Rating0.1
Storage Enclosure TypeCS
Load ManagementYes
Backup PowerYes
Excess Wind And Solar GenerationP
Ac CoupledYes
Direct Support Of Another UnitYes
Direct Support Plant Id63510
Direct Support Gen IdPV1
Support T D AssetNo

Walnut Unified School District Walnut HS Plant Owners

Owner NameAddressGeneratorOwnership
Solar Integrated Fund VI, LLC6800 Dumbarton Cirlce, Fremont, CA 94555Generator PV1100.00%
Solar Integrated Fund VI, LLC6800 Dumbarton Cirlce, Fremont, CA 94555Generator ST1100.00%

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Solar.

RankPlant NamePlant LocationAnnual Generation
#6153Niagara Bottling StocktonStockton, CA870.0 MWh
#6154Edwards Air Force BaseEdwards, CA866.0 MWh
#6155Park SolarWoodbridge, CT866.0 MWh
#6156CSU Northridge PlantNorthridge, CA865.0 MWh
#6157LSE Pavo SolarWalton, NY861.0 MWh
#6158Manlius WestManlius, NY848.0 MWh
#6159Renewable Energy Center at BJHSt Louis, MO846.0 MWh
#6160Searcy Water ISearcy, AR834.0 MWh
#6161Clovis High SchoolClovis, CA826.0 MWh
#6162CCMUACamden, NJ824.0 MWh
#6164Rockville Solar II, LLCIndianapolis, IN812.0 MWh
#6165ME Novel Lighthouse - Penobscot CSGPatten, ME812.0 MWh
#6166ESA SelmaSelma, NC811.0 MWh
#6167Silver Lake Solar Photovoltaic FacilityPittsfield, MA805.0 MWh
#6168Questa Solar FacilityQuesta, NM804.0 MWh
#6169Haleon York RDC Solar FacilityYork, PA798.0 MWh
#6170Morgan Lancaster 1Lancaster, CA796.0 MWh
#6171English Creek SolarPlant City, FL791.0 MWh
#6172Preston Garden (CSG)Franklin, MN785.0 MWh
#6173Facile SolarElon, NC783.0 MWh

Nearby Power Plants

Below are closest 20 power plants surrounding Walnut Unified School District Walnut HS.

Plant NamePlant LocationAnnual GenerationDistance
Biola University HybridLa Mirada, CA12.8 GWh12.2 mi
Blacksand Generating FacilityBrea, CA39.0 GWh6.2 mi
Brea Expansion PlantBrea, CA235.5 GWh6.2 mi
CamChino Leasing LLCChino, CA6.9 GWh10 mi
Canyon Power PlantAnaheim, CA23.9 GWh11.3 mi
CSUF Nutwood SolarFullerton, CA3.1 GWh10.1 mi
CSUF State CollegeFullerton, CA1.6 GWh10.1 mi
CSUF TrigenerationFullerton, CA37.8 GWh10 mi
Gilead Sciences La Verne Rooftop SolarLa Verne, CA2.5 GWh6.5 mi
Industry MetroLink PV 1Industry, CA1.1 GWh1 mi
Irwindale Brew Yard, LLCIrwindale, CA517.0 MWh8.5 mi
Kaiser East La Palma Ave. Fuel CellAnaheim, CA18.1 GWh11.8 mi
Kroger La HabraLa Habra, CA1.7 GWh8.6 mi
MM West CovinaWest Covina, CA31.0 GWh3.3 mi
Puente Hills Energy RecoveryWhittier, CA151.3 GWh9.9 mi
San Antonio West Solar RooftopChino, CA1.7 GWh11.6 mi
San Dimas Wash Generating StationSan Dimas, CA4.8 GWh7.5 mi
San Gabriel Hydro ProjectAzusa, CA4.9 GWh12.6 mi
Walnut Creek Energy ParkIndustry, CA63.2 GWh5.5 mi
Weymouth Solar PlantLa Verne, CA4.8 GWh7.2 mi