Walnut Creek Energy Park
911 Bixby Drive, Industry, CA 91744Plant Summary Information
Walnut Creek Energy Park is ranked #87 out of 342 natural gas power plants in California in terms of total annual net electricity generation.
Walnut Creek Energy Park is comprised of 5 generators and generated 11.7 GWh during the 3-month period between August 2025 to November 2025.
| Plant Name | Walnut Creek Energy Park |
|---|---|
| Utility Name | Walnut Creek LLC |
| Location | Los Angeles County, CA |
| Initial Operation Date | April 2013 |
| Last Update | Nov 2025 |
| Annual Generation | 44.6 GWh |
| Annual Consumption | 452.2 k MMBtu |
| Ranked #4,243 out of 12,574 Power Plants Nationwide | |
| Ranked #1,123 out of 2,244 Natural Gas Power Plants Nationwide | |
| Ranked #507 out of 1,603 California Power Plants | |
| Ranked #87 out of 342 California Natural Gas Power Plants | |
| Fuel Types | Natural Gas |
| Previous Operators |
Edison Mission Energy (2013 to 2014) NRG Walnut Creek LLC (2015 to 2018) Walnut Creek LLC (2019 to 2024) |
Map of Walnut Creek Energy Park
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Walnut Creek Energy Park.
Monthly Net Generation for Walnut Creek Energy Park
Walnut Creek Energy Park Details
| Summary Information | |
|---|---|
| Plant Name | Walnut Creek Energy Park (57515) |
| Plant Address | 911 Bixby Drive, Industry, CA 91744 |
| Utility | Walnut Creek LLC (59980) |
| Latitude, Longitude | 34.00871, -117.94486 |
| Generation Dates on File | Mar 2013 to Nov 2025 |
| Initial Operation Date | April 2013 |
| Annual Generation | 44.6 GWh |
| Fuel Types | Natural Gas |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | WECC |
| Balancing Authority | California Independent System Operator (CISO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | Rowland Water Dist (reclaimed) |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Southern California Edison Co (17609) CA |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
| Natural Gas Information | |
| Local Distribution Company (LDC) | SOUTHERN CALIFORNIA GAS COMPANY |
| Natural Gas Storage | No |
| Liquefied Natural Gas Storage | No |
Generator GT1 Details Operating April 2013
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | CAISO WALCRK_2_CTG1 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CAISO WALCRK_2_CTG1 |
| Nameplate Capacity | 100 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 100.1 MW |
| Winter Capacity | 100.1 MW |
| Minimum Load | 48 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2013 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT2 Details Operating April 2013
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | CAISO WALCRK_2_CTG2 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CAISO WALCRK_2_CTG2 |
| Nameplate Capacity | 100 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 100.1 MW |
| Winter Capacity | 100.1 MW |
| Minimum Load | 48 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2013 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT3 Details Operating April 2013
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | CAISO WALCRK_2_CTG3 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CAISO WALCRK_2_CTG3 |
| Nameplate Capacity | 100 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 100.1 MW |
| Winter Capacity | 100.1 MW |
| Minimum Load | 48 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2013 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT4 Details Operating April 2013
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | CAISO WALCRK_2_CTG4 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CAISO WALCRK_2_CTG4 |
| Nameplate Capacity | 100 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 100.1 MW |
| Winter Capacity | 100.1 MW |
| Minimum Load | 48 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | April 2013 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Generator GT5 Details Operating May 2013
| Technology | Natural Gas Fired Combustion Turbine |
|---|---|
| Prime Mover | Combustion Turbine |
| Ownership | Single Owner |
| RTO ISO LMP Node Designation | CAISO WALCRK_2_CTG5 |
| RTO ISO Location Designation For Reporting Wholesale Sales Data | CAISO WALCRK_2_CTG5 |
| Nameplate Capacity | 100 MW |
| Nameplate Power Factor | 0.85 |
| Summer Capacity | 100.1 MW |
| Winter Capacity | 100.1 MW |
| Minimum Load | 48 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | May 2013 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Natural Gas |
| Solid Fuel Gasification | No |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Cofire Fuels | No |
| Switch Between Oil And Natural Gas | No |
Walnut Creek Energy Park Plant Owners
| Owner Name | Address | Generator | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1113 | Valmont Combustion Turbine Project | Boulder, CO | 46.0 GWh |
| #1114 | Barrow | Barrow, AK | 45.9 GWh |
| #1115 | NYU LANGONE HEALTH | New York, NY | 46.1 GWh |
| #1116 | Warrick | Newburgh, IN | 3.0 TWh |
| #1117 | Feather River Energy Center | Yuba City, CA | 45.7 GWh |
| #1118 | St Francisville Mill | St. Francisville, LA | 110.3 GWh |
| #1119 | Orbit Bloom Fuel Cell | Medford, NY | 45.6 GWh |
| #1120 | Hoffmann LaRoche | Nutley, NJ | 45.3 GWh |
| #1121 | Otter Creek Ethanol Poet - Ashton | Ashton, IA | 44.9 GWh |
| #1122 | Wolf Run Energy | Wilmot Township, PA | 44.9 GWh |
| #1124 | Orchard Park | Chambersburg, PA | 46.7 GWh |
| #1125 | Gilroy Power Plant | Gilroy, CA | 44.2 GWh |
| #1126 | DeBary | DeBary, FL | 50.1 GWh |
| #1127 | Fort Dodge | Dodge City, KS | 44.1 GWh |
| #1128 | Florida's Natural Growers | Lake Wales, FL | 44.0 GWh |
| #1129 | Bristol Myers Squibb Lawrenceville | Lawrenceville, NJ | 44.2 GWh |
| #1130 | Waterbury Generation | Waterbury, CT | 43.8 GWh |
| #1131 | F B Culley | Newburgh, IN | 1.1 TWh |
| #1132 | West Marinette 34 | Peshtigo, WI | 43.6 GWh |
| #1133 | Naval Sub Base New London Fuel Cell | Groton, CT | 43.6 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Walnut Creek Energy Park.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Alticor Inc - Solar Project | Buena Park, CA | 1.6 GWh | 9.5 mi |
| Biola University Hybrid | La Mirada, CA | 12.9 GWh | 8 mi |
| Blacksand Generating Facility | Brea, CA | 39.0 GWh | 7.3 mi |
| Brea Expansion Plant | Brea, CA | 234.3 GWh | 8 mi |
| Buidling L | Santa Fe Springs, CA | 2.3 GWh | 8.6 mi |
| Building F | Santa Fe Springs, CA | 2.3 GWh | 8.9 mi |
| Building G | Santa Fe Springs, CA | 2.0 GWh | 9 mi |
| CSUF Nutwood Solar | Fullerton, CA | 3.1 GWh | 9.5 mi |
| CSUF State College | Fullerton, CA | 1.6 GWh | 9.5 mi |
| CSUF Trigeneration | Fullerton, CA | 37.0 GWh | 9.5 mi |
| Golden Springs Building C-1 | Santa Fe Springs, CA | 1.3 GWh | 9 mi |
| Golden Springs Building D | Santa Fe Springs, CA | 651.0 MWh | 9.1 mi |
| Industry MetroLink PV 1 | Industry, CA | 1.1 GWh | 5.7 mi |
| Irwindale Brew Yard, LLC | Irwindale, CA | 517.0 MWh | 7.8 mi |
| Kroger La Habra | La Habra, CA | 1.7 GWh | 6 mi |
| MM West Covina | West Covina, CA | 31.0 GWh | 2.8 mi |
| Puente Hills Energy Recovery | Whittier, CA | 150.5 GWh | 4.6 mi |
| Santa Fe Springs Rooftop Solar BLDG H | Santa Fe Springs, CA | 2.3 GWh | 8.8 mi |
| Santa Fe Springs Rooftop Solar BLDG M | Santa Fe Springs, CA | 2.5 GWh | 8.8 mi |
| Walnut Unified School District Walnut HS | Walnut, CA | 809.0 MWh | 5.5 mi |