Smoky Hills Wind Project Phase II

223 North Hwy 14, Lincoln, KS 67455

Plant Summary Information

Smoky Hills Wind Project Phase II is ranked #41 out of 148 power plants in Kansas in terms of total annual net electricity generation.

Smoky Hills Wind Project Phase II generated 139.1 GWh during the 3-month period between September 2023 to December 2023.

Plant NameSmoky Hills Wind Project Phase II
Utility NameSmoky Hills Wind Project II LLC
LocationLincoln County, KS
Initial Operation DateNovember 2008
Last Update Dec 2023
Annual Generation 437.7 GWh
Annual Consumption 1.6 M MMBtu
Ranked #1,433 out of 11,623 Power Plants Nationwide
Ranked #412 out of 1,344 Wind Power Plants Nationwide
Ranked #41 out of 148 Kansas Power Plants
Ranked #33 out of 50 Kansas Wind Power Plants
Fuel Types Wind

Map of Smoky Hills Wind Project Phase II

Full Screen Map
Use Ctrl + scroll to zoom the map
Use two fingers to move the map

Register Now for Comprehensive Access

Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Smoky Hills Wind Project Phase II.

Create Your Account Today

Monthly Net Generation for Smoky Hills Wind Project Phase II

80k80k60k60k40k40k20k20k00200920092010201020112011201220122013201320142014201520152016201620172017201820182019201920202020202120212022202220232023
Download SVG
Download PNG
Download CSV

Smoky Hills Wind Project Phase II Details

Summary Information
Plant NameSmoky Hills Wind Project Phase II (56985)
Plant Address223 North Hwy 14, Lincoln, KS 67455
UtilitySmoky Hills Wind Project II LLC (56285)
Latitude, Longitude38.89265, -98.16888
Generation Dates on FileJan 2009 to Dec 2023
Initial Operation DateNovember 2008
Annual Generation 437.7 GWh
Fuel Types Wind
 
Federal Energy Regulatory Commission (FERC) Information
FERC Cogeneration StatusNo
FERC Small Power Producer StatusNo
FERC Exempt Wholesale Generator StatusNo
Regulatory Information
Regulatory StatusNon-Regulated
NERC RegionMRO
Balancing AuthoritySouthwest Power Pool (SWPP)
NAICS CodeUtilities (22)
Sector IPP Non-CHP (2)
Water Source
Ash Impoundment
Transmission / Distribution OwnerMidwest Energy Inc (12524) KS
Grid Voltage 230.00 kV
Energy StorageNo

Generator SMKII Details Operating January 2009

TechnologyOnshore Wind Turbine
Prime MoverWind Turbine, Onshore
OwnershipSingle Owner
Nameplate Capacity148.5 MW
Summer Capacity148.5 MW
Winter Capacity148.5 MW
Minimum Load0.1 MW
Uprate/Derate Completed No
StatusOperating
First Operation DateJanuary 2009
Combined Heat & Power No
Sector NameIPP Non-CHP (2)
Energy SourceWind
Turbines/Hydrokinetic Buoys99
Turbine Details
Number Of Turbines99
Predominant Turbine ManufacturerGE
Predominant Turbine Model Number1.5 SE
Design Wind Speed24 MPH
Wind Quality Class1 - High Wind
Turbine Hub Height Feet264

Smoky Hills Wind Project Phase II Plant Owners

Owner NameAddressOwnership
We couldn't locate any owners for this plant

Power Plants with Similar Net Generation

Power plants with a similar annual net generation from Wind.

RankPlant NamePlant LocationAnnual Generation
#402Cimarron Wind Energy LLCCimmaron, KS448.0 GWh
#403White Creek Wind FarmRoosevelt, WA446.8 GWh
#404Heartland Divide Wind Project, LLCMelville, IA444.5 GWh
#405Judith Gap Wind Energy CenterHarlowton, MT444.2 GWh
#406Polaris Wind ParkNorth Star Township, MI443.3 GWh
#407Fowler Ridge IV Wind Farm LLCFowler, IN443.2 GWh
#408Wellsburg Wind ProjectWellsburg, IA441.8 GWh
#409Day County Wind LLCConde, SD441.2 GWh
#410Adams WindLenox, IA440.1 GWh
#411Los Vientos Windpower IVRio Grande City, TX439.5 GWh
#413Oliver Wind III, LLCMandan, ND434.2 GWh
#414Pioneer Trail Wind Farm, LLCPaxton, IL433.8 GWh
#415DunlapMedicine Bow, WY432.0 GWh
#416Shiloh Wind Project 2 LLCBirds Landing, CA431.7 GWh
#417Lake Benton IIRuthton, MN431.4 GWh
#418Laurel Wind FarmLaurel, IA431.3 GWh
#419Gunsight Mountain Wind Energy LLCBig Spring, TX429.5 GWh
#420Sweetwater Wind 2 LLCSweetwater, TX429.5 GWh
#421Magic Valley Wind Farm I LLCSan Perlita, TX428.2 GWh
#422Inadale Wind Farm LLC HybridRoscoe, TX427.2 GWh

Nearby Power Plants

Below are closest 20 power plants surrounding Smoky Hills Wind Project Phase II.

Plant NamePlant LocationAnnual GenerationDistance
BeloitBeloit, KS114.0 MWh39.2 mi
Beloit Solar LLCBeloit, KS4.7 GWh38.7 mi
Cloud County Wind FarmConcordia, KS317.6 GWh46.3 mi
Diamond Vista Wind Project, LLCTampa, KS915.5 GWh57.7 mi
EllinwoodEllinwood, KS48.0 MWh43.4 mi
Great Bend - SunflowerGreat Bend, KS32.0 GWh50.4 mi
HoisingtonHoisington, KS62.0 MWh41.9 mi
Hutchinson Energy CenterHutchinson, KS24.9 GWh57.7 mi
Kansas Ethanol, LLCLyons, KS113.4 GWh41.9 mi
LincolnLincoln, KS16.0 MWh10 mi
McPherson 2McPherson, KS37.8 GWh45 mi
McPherson 3McPherson, KS15.5 GWh46 mi
Minneapolis City ofMinneapolis, KS84.0 MWh29.3 mi
OsborneOsborne, KS7.8 MWh47.1 mi
Post Rock Wind Power Project, LLCEllsworth, KS382.0 GWh7.9 mi
Russell DowntownRussell, KS78.0 MWh37 mi
Russell Energy CenterRussell, KS2.4 GWh36.1 mi
Smoky Hills Wind Project Phase ILincoln, KS272.0 GWh1 mi
SterlingSterling, KS157.0 MWh46.9 mi
Westar Cities SolarHutchinson, KS2.2 GWh61.2 mi