Smoky Hills Wind Project Phase I
223 North Highway 14, Lincoln, KS 67455Plant Summary Information
Smoky Hills Wind Project Phase I is ranked #49 out of 174 power plants in Kansas in terms of total annual net electricity generation.
Smoky Hills Wind Project Phase I generated 75.0 GWh during the 3-month period between September 2024 to December 2024.
| Plant Name | Smoky Hills Wind Project Phase I |
|---|---|
| Utility Name | Smoky Hills Wind Farm I LLC |
| Location | Lincoln County, KS |
| Initial Operation Date | January 2008 |
| Last Update | Dec 2024 |
| Annual Generation | 250.8 GWh |
| Annual Consumption | 941.1 k MMBtu |
| Ranked #2,197 out of 12,539 Power Plants Nationwide | |
| Ranked #667 out of 1,362 Wind Power Plants Nationwide | |
| Ranked #49 out of 174 Kansas Power Plants | |
| Ranked #40 out of 52 Kansas Wind Power Plants | |
| Fuel Types | Wind |
Map of Smoky Hills Wind Project Phase I
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Smoky Hills Wind Project Phase I.
Monthly Net Generation for Smoky Hills Wind Project Phase I
Smoky Hills Wind Project Phase I Details
| Summary Information | |
|---|---|
| Plant Name | Smoky Hills Wind Project Phase I (56488) |
| Plant Address | 223 North Highway 14, Lincoln, KS 67455 |
| Utility | Smoky Hills Wind Farm I LLC (55886) |
| Latitude, Longitude | 38.87994, -98.16016 |
| Generation Dates on File | Jan 2008 to Dec 2024 |
| Initial Operation Date | January 2008 |
| Annual Generation | 250.8 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | 07-83-000 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | MRO |
| Balancing Authority | Southwest Power Pool (SWPP) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Westar Energy Inc (22500) KS |
| Grid Voltage | 230.00 kV |
| Energy Storage | No |
Generator 1 Details Operating December 2008
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 100.8 MW |
| Summer Capacity | 100.8 MW |
| Winter Capacity | 100.8 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | December 2008 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 56 |
| Turbine Details | |
| Number Of Turbines | 56 |
|---|---|
| Predominant Turbine Manufacturer | Vestas |
| Predominant Turbine Model Number | V80-1.8 |
| Design Wind Speed | 24 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 328 |
Smoky Hills Wind Project Phase I Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #657 | Brookfield | Pigeon, MI | 255.0 GWh |
| #658 | Arkwright Summit Wind Farm LLC | Fredonia, NY | 254.6 GWh |
| #659 | Stanton Wind Energy LLC | Lenorah, TX | 253.9 GWh |
| #660 | Broken Bow Wind II, LLC | Broken Bow, NE | 253.6 GWh |
| #661 | Penascal II Wind Project LLC | Sarita, TX | 253.4 GWh |
| #662 | South Trent Wind Farm | Sweetwater, TX | 252.5 GWh |
| #663 | Ironwood Wind | Spearville, KS | 251.7 GWh |
| #664 | Red Barn Energy | Montfort, WI | 251.6 GWh |
| #665 | Hancock County Wind Energy Center | Garner, IA | 251.5 GWh |
| #666 | Minco Wind II, LLC | Minco, OK | 251.0 GWh |
| #668 | San Roman Wind I, LLC | Los Fresnos, TX | 250.7 GWh |
| #669 | Rockland Wind Farm | American Falls, ID | 250.6 GWh |
| #670 | Laurel Mountain Hybrid | Belington, WV | 247.4 GWh |
| #671 | Blackstone Wind Farm LLC | Ransom, IL | 250.1 GWh |
| #672 | Wheatridge 1 | Lexington, OR | 249.3 GWh |
| #673 | Rising Tree Wind Farm | Mojave, CA | 249.0 GWh |
| #674 | Golden Hills Wind | Livermore, CA | 247.4 GWh |
| #675 | Farmers City Wind LLC | Tarkio, MO | 246.4 GWh |
| #676 | Klondike Windpower II | Wasco, OR | 245.8 GWh |
| #677 | Sky River Wind Energy Center | Tehachapi, CA | 245.0 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Smoky Hills Wind Project Phase I.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| Beloit | Beloit, KS | 192.0 MWh | 40 mi |
| Beloit Solar LLC | Beloit, KS | 4.6 GWh | 39.5 mi |
| Cloud County Wind Farm | Concordia, KS | 334.8 GWh | 46.8 mi |
| Ellinwood | Ellinwood, KS | 118.0 MWh | 42.9 mi |
| Great Bend - Sunflower | Great Bend, KS | 51.9 GWh | 50.2 mi |
| Hoisington | Hoisington, KS | 32.0 MWh | 41.7 mi |
| Hutchinson Energy Center | Hutchinson, KS | 29.1 GWh | 56.7 mi |
| Kansas Ethanol, LLC | Lyons, KS | 116.3 GWh | 41.1 mi |
| Lincoln | Lincoln, KS | 22.0 MWh | 10.9 mi |
| Lindsborg | Lindsborg, KS | 2.4 GWh | 32 mi |
| McPherson 2 | McPherson, KS | 15.2 GWh | 44 mi |
| McPherson 3 | McPherson, KS | 14.5 GWh | 45 mi |
| Minneapolis City of | Minneapolis, KS | 99.0 MWh | 29.4 mi |
| Osborne | Osborne, KS | 15.7 MWh | 48.1 mi |
| Post Rock Wind Power Project, LLC | Ellsworth, KS | 405.7 GWh | 7.9 mi |
| Russell Downtown | Russell, KS | 87.0 MWh | 37.5 mi |
| Russell Energy Center | Russell, KS | 700.0 MWh | 36.6 mi |
| Smoky Hills Wind Project Phase II | Lincoln, KS | 414.3 GWh | 1 mi |
| Solomon-DS&O | Solomon, KS | 2.4 GWh | 42.5 mi |
| Sterling | Sterling, KS | 32.0 MWh | 46.1 mi |