Santan
1005 S. Val Vista Drive, Gilbert, AZ 85296Plant Summary Information
Santan is ranked #2 out of 166 power plants in Arizona in terms of total annual net electricity generation.
Santan is comprised of 9 generators and generated 1.3 TWh during the 3-month period between February 2025 to May 2025.
Plant Name | Santan |
---|---|
Utility Name | Salt River Project |
Location | Maricopa County, AZ |
Initial Operation Date | October 1974 |
Last Update | May 2025 |
Annual Generation | 6.1 TWh |
Annual Consumption | 48.9 M MMBtu |
Ranked #169 out of 12,312 Power Plants Nationwide | |
Ranked #69 out of 2,220 Natural Gas Power Plants Nationwide | |
Ranked #2 out of 166 Arizona Power Plants | |
Ranked #1 out of 35 Arizona Natural Gas Power Plants | |
Fuel Types | Natural Gas |
Map of Santan
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Santan.
Monthly Net Generation for Santan
Santan Details
Summary Information | |
---|---|
Plant Name | Santan (8068) |
Plant Address | 1005 S. Val Vista Drive, Gilbert, AZ 85296 |
Utility | Salt River Project (16572) |
Latitude, Longitude | 33.3325, -111.7503 |
Generation Dates on File | Jan 2001 to May 2025 |
Initial Operation Date | October 1974 |
Annual Generation | 6.1 TWh |
Fuel Types | Natural Gas |
Federal Energy Regulatory Commission (FERC) Information | |
FERC Cogeneration Status | No |
FERC Small Power Producer Status | No |
FERC Exempt Wholesale Generator Status | No |
Regulatory Information | |
---|---|
Regulatory Status | Regulated |
NERC Region | WECC |
Balancing Authority | Salt River Project (SRP) |
NAICS Code | Utilities (22) |
Sector | Electric Utility (1) |
Water Source | Eastern Canal (SRP) |
Ash Impoundment | No |
Transmission / Distribution Owner | Salt River Project (16572) AZ |
Grid Voltage | 230.00 kV / 69.00 kV |
Energy Storage | No |
Natural Gas Information | |
Pipeline Name |
TRANSWESTERN PIPELINE COMPANY EL PASO NATURAL GAS CO LLC |
Natural Gas Storage | No |
Generator ST1 Details Operating October 1974
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Single Shaft |
Ownership | Single Owner |
Duct Burners | No |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 103.5 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 92 MW |
Winter Capacity | 103.5 MW |
Minimum Load | 80 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 1974 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST3 Details Operating October 1974
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Single Shaft |
Ownership | Single Owner |
Duct Burners | No |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 103.5 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 92 MW |
Winter Capacity | 103.5 MW |
Minimum Load | 80 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | October 1974 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST2 Details Operating December 1974
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Single Shaft |
Ownership | Single Owner |
Duct Burners | No |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 103.5 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 92 MW |
Winter Capacity | 103.5 MW |
Minimum Load | 80 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | December 1974 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Other Planned Modifications | No |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST4 Details Operating May 1975
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Single Shaft |
Ownership | Single Owner |
Duct Burners | No |
Can Bypass Heat Recovery Steam Generator | No |
Nameplate Capacity | 103.5 MW |
Nameplate Power Factor | 0.9 |
Summer Capacity | 92 MW |
Winter Capacity | 103.5 MW |
Minimum Load | 80 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | May 1975 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST5A Details Operating April 2005
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | STS5 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | Yes |
Nameplate Capacity | 153.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 163 MW |
Winter Capacity | 194 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | April 2005 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST5B Details Operating April 2005
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | STS5 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | Yes |
Nameplate Capacity | 153.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 163 MW |
Winter Capacity | 194 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | April 2005 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST5S Details Operating April 2005
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | STS5 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 314.5 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 290 MW |
Winter Capacity | 296 MW |
Minimum Load | 60 MW |
Uprate/Derate Completed | No |
Status | Operating |
First Operation Date | April 2005 |
---|---|
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST6A Details Operating March 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Combustion Turbine Part |
Unit Code | STS6 |
Ownership | Single Owner |
Can Bypass Heat Recovery Steam Generator | Yes |
Nameplate Capacity | 153.8 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 171 MW |
Winter Capacity | 186 MW |
Minimum Load | 90 MW |
Uprate/Derate Completed | Yes |
Uprate Or Derate Completed | April 2024 |
Status | Operating |
---|---|
First Operation Date | March 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Generator ST6S Details Operating March 2006
Technology | Natural Gas Fired Combined Cycle |
---|---|
Prime Mover | Combined Cycle Steam Part |
Unit Code | STS6 |
Ownership | Single Owner |
Duct Burners | Yes |
Nameplate Capacity | 136.1 MW |
Nameplate Power Factor | 0.85 |
Summer Capacity | 131 MW |
Winter Capacity | 140 MW |
Minimum Load | 45 MW |
Uprate/Derate Completed | Yes |
Uprate Or Derate Completed | April 2024 |
Status | Operating |
---|---|
First Operation Date | March 2006 |
Combined Heat & Power | No |
Sector Name | Electric Utility (1) |
Energy Source | Natural Gas |
Startup Source | Natural Gas |
Solid Fuel Gasification | No |
Carbon Capture Technology | No |
Time From Cold Shutdown To Full Load | 1H |
Multiple Fuels | No |
Cofire Fuels | No |
Switch Between Oil And Natural Gas | No |
Santan Plant Owners
Owner Name | Address | Generator | Ownership |
---|---|---|---|
We couldn't locate any owners for this plant |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Natural Gas.
Rank | Plant Name | Plant Location | Annual Generation |
---|---|---|---|
#59 | Montgomery County | Willis, TX | 6.4 TWh |
#60 | Clean Energy Future-Lordstown, LLC | Lordstown, OH | 6.3 TWh |
#61 | Wolf Hollow II | Granbury, TX | 6.3 TWh |
#62 | Sithe Independence Station | Oswego, NY | 6.3 TWh |
#63 | P L Bartow | St. Petersburg, FL | 6.2 TWh |
#64 | Marcus Hook Energy LP | Marcus Hook, PA | 6.2 TWh |
#65 | CPV Three Rivers Energy Center | Morris, IL | 6.1 TWh |
#66 | Guadalupe Generating Station | Marion, TX | 6.1 TWh |
#67 | Manatee | Parrish, FL | 6.1 TWh |
#68 | Bethlehem Power Plant | Bethlehem, PA | 6.1 TWh |
#70 | Hunterstown Power Plant | Gettysburg, PA | 6.0 TWh |
#71 | Port Everglades | Ft. Lauderdale, FL | 6.0 TWh |
#72 | Hickory Run Energy Station | New Castle, PA | 6.0 TWh |
#73 | Oregon Clean Energy Center | Oregon, OH | 5.9 TWh |
#74 | Lake Road Generating Plant | Dayville, CT | 5.8 TWh |
#75 | St. Charles Power Station (LA) | La Place, LA | 5.8 TWh |
#76 | Channelview Cogeneration Plant | Channelview, TX | 5.8 TWh |
#77 | Polk | Mulberry, FL | 5.8 TWh |
#78 | Lake Side Power Plant | Vineyard, UT | 5.8 TWh |
#79 | Chouteau | Pryor, OK | 5.7 TWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Santan.
Plant Name | Plant Location | Annual Generation | Distance |
---|---|---|---|
Arizona State University CHP | Tempe, AZ | 42.3 GWh | 11.8 mi |
AZ State University - Tempe Campus Solar | Tempe, AZ | 1.1 GWh | 12.1 mi |
Banner Solar Ironwood | Queen Creek, AZ | 3.8 GWh | 13.4 mi |
Copper Crossing Energy and Research Cent | Florence, AZ | 5.1 GWh | 19.7 mi |
Gilbert Solar Facility I, LLC | Gilbert, AZ | 3.8 GWh | 3.4 mi |
Intel - Ocotillo Campus Solar | Chandler, AZ | 2.3 GWh | 10.3 mi |
Jewish Community Center PV | Scottsdale, AZ | 1.8 GWh | 21.2 mi |
Kyrene | Tempe, AZ | 812.2 GWh | 10.8 mi |
Mesa Carport PV | Mesa, AZ | 7.5 GWh | 8.6 mi |
Mormon Flat | Apache Junction, AZ | 53.5 GWh | 23.4 mi |
Ocotillo | Tempe, AZ | 510.4 GWh | 11.2 mi |
Paradise Valley H.S. PV | Phoenix, AZ | 2.1 GWh | 25.7 mi |
Phoenix Airport East Economy Lot | Phoenix, AZ | 1.3 GWh | 15.2 mi |
Phoenix Airport Rental Car Center | Phoenix, AZ | 4.4 GWh | 18.3 mi |
Poseidon Solar, LLC | Globe, AZ | 50.2 GWh | 19.4 mi |
Queen Creek Solar Farm | Queen Creek, AZ | 40.7 GWh | 9.2 mi |
Stewart Mountain | Phoenix, AZ | 45.7 GWh | 20.3 mi |
TJX Phoenix | Phoenix, AZ | 5.0 GWh | 25.4 mi |
Union HS at Casa Grande | Casa Grande, AZ | 2.9 GWh | 27.3 mi |
West Phoenix | Phoenix, AZ | 4.1 TWh | 24.7 mi |