Roseland Solar Project, LLC
309 FM 2603, Riesel, TX 76682Plant Summary Information
Roseland Solar Project, LLC is ranked #6 out of 6,397 solar farms nationwide in terms of total annual net electricity generation.
Roseland Solar Project, LLC generated 239.6 GWh during the 3-month period between December 2025 to March 2026.
| Plant Name | Roseland Solar Project, LLC |
|---|---|
| Utility Name | Enel Green Power Roseland Solar, LLC |
| Location | Falls County, TX |
| Initial Operation Date | July 2023 |
| Last Update | Mar 2026 |
| Annual Generation | 1.1 TWh |
| Annual Consumption | 4.0 M MMBtu |
| Ranked #714 out of 12,332 Power Plants Nationwide | |
| Ranked #6 out of 6,397 Solar Power Plants Nationwide | |
| Ranked #115 out of 814 Texas Power Plants | |
| Ranked #3 out of 219 Texas Solar Power Plants | |
| Fuel Types | Solar |
Map of Roseland Solar Project, LLC
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Roseland Solar Project, LLC.
Monthly Net Generation for Roseland Solar Project, LLC
Monthly Plant Fuel Consumption for Roseland Solar Project, LLC
Roseland Solar Project, LLC Details
| Summary Information | |
|---|---|
| Plant Name | Roseland Solar Project, LLC (65028) |
| Plant Address | 309 FM 2603, Riesel, TX 76682 |
| Utility | Enel Green Power Roseland Solar, LLC (64438) |
| Latitude, Longitude | 31.46124, -96.82493 |
| Generation Dates on File | Jul 2023 to Mar 2026 |
| Initial Operation Date | July 2023 |
| Annual Generation | 1.1 TWh |
| Fuel Types | Solar |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | Yes |
| FERC Exempt Wholesale Generator Docket Number | 22-75-000 |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | No |
| Transmission / Distribution Owner | Oncor Electric Delivery Company LLC (44372) TX |
| Grid Voltage | 345.00 kV |
| Energy Storage | Yes |
Generator ROSEB Details Operating July 2023
| Technology | Batteries |
|---|---|
| Prime Mover | Battery |
| Ownership | Wholly Owned by Other Entity |
| Nameplate Capacity | 51.8 MW |
| Summer Capacity | 51.8 MW |
| Winter Capacity | 51.8 MW |
| Minimum Load | 0.1 MW |
| Uprate/Derate Completed | No |
| Status | Operating |
|---|---|
| First Operation Date | July 2023 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Electricity used for energy storage |
| Carbon Capture Technology | No |
| Time From Cold Shutdown To Full Load | 10M |
| Multiple Fuels | No |
| Energy Storage Details | |
| Nameplate Energy Capacity MWH | 84.5 |
|---|---|
| Maximum Charge Rate | 50 MW |
| Maximum Discharge Rate | 50 MW |
| Storage Technology | LIB |
| Nameplate Reactive Power Rating | 80 |
| Storage Enclosure Type | CS |
| Arbitrage | P |
| Frequency Regulation | Yes |
| Voltage Or Reactive Power Support | Yes |
| Direct Support Of Another Unit | No |
| Support T D Asset | No |
Roseland Solar Project, LLC Plant Owners
| Owner Name | Address | Ownership |
|---|---|---|
| Enel Kansas, LLC | 100 Brickstone Square, Suite 300, Andover, MA 1810 | 100.00% |
| Enel Kansas, LLC | 100 Brickstone Square, Suite 300, Andover, MA 1810 | 100.00% |
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Solar.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #1 | Gemini Solar Hybrid | Unincorporated, NV | 2.1 TWh |
| #2 | Hornet Solar (TX) | Tulia, TX | 1.6 TWh |
| #3 | Hecate Energy Frye Solar LLC | Kress, TX | 1.3 TWh |
| #4 | Fox Squirrel Solar | Mt Sterling, OH | 1.2 TWh |
| #5 | Sonoran Solar Energy | Buckeye, AZ | 1.1 TWh |
| #7 | Roadrunner, LLC Hybrid | McCamey, TX | 1.1 TWh |
| #8 | Topaz Solar Farm | Santa Margarita, CA | 1.1 TWh |
| #9 | Aktina Solar | El Campo, TX | 1.0 TWh |
| #10 | 2W Permian Solar Project Hybrid | Andrews, TX | 1.0 TWh |
| #11 | Mockingbird Solar Center | Brookston, TX | 944.4 GWh |
| #12 | Old 300 Solar Center, LLC | Needville, TX | 935.4 GWh |
| #13 | Double Back Diamond | Virden, IL | 906.1 GWh |
| #14 | Eagle Shadow Mountain Solar Farm | Moapa, NV | 901.5 GWh |
| #15 | Solar Star 1 | Rosamond, CA | 893.5 GWh |
| #16 | Waco Solar | Mt Calm, TX | 883.9 GWh |
| #17 | Daggett 3 | Daggett, CA | 869.3 GWh |
| #18 | Harquahala 2 | Tonopah, AZ | 830.1 GWh |
| #19 | Desert Quartzite | Blythe, CA | 851.3 GWh |
| #20 | Solana Generating Station | Gila Bend, AZ | 869.9 GWh |
| #21 | Greasewood II LLC | Girvin, TX | 857.2 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Roseland Solar Project, LLC.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| AbbVie Waco | Waco, TX | 811.0 MWh | 22.2 mi |
| Blevins Solar & Storage | TX | 124.0 GWh | 27.4 mi |
| BPL Crown Solar LLC | Chilton, TX | 215.9 GWh | 17.1 mi |
| BPL Sol Solar LLC | Chilton, TX | 212.6 GWh | 17.1 mi |
| Copperhead Solar, LLC | Riesel, TX | 290.3 GWh | 2.2 mi |
| Diver Solar, LLC | Thornton, TX | 276.9 GWh | 29.5 mi |
| Eddy II | Eddy, TX | 16.6 GWh | 28.3 mi |
| Griffin Solar | Robinson, TX | 9.2 GWh | 18.7 mi |
| Hubbard Wind | Mt Calm, TX | 927.5 GWh | 21.7 mi |
| Limestone Wind Project | Coolidge, TX | 1.1 TWh | 29.6 mi |
| Major Oak Power | Bremond, TX | 2.1 TWh | 26.6 mi |
| Marlin Solar | Marlin, TX | 9.9 GWh | 12.4 mi |
| Oak Grove (TX) | Franklin, TX | 10.9 TWh | 27.8 mi |
| Pitts Dudik Solar | Hubbard, TX | 101.5 GWh | 30 mi |
| PP Jaguar BESS LLC | TX | 11.5 GWh | 12.9 mi |
| Prairie Hill Wind Project | Mart, TX | 94.0 GWh | 7.7 mi |
| Sandy Creek Energy Station | Riesel, TX | 3.2 TWh | 7.8 mi |
| Sun Valley Solar Project | Abbott, TX | 568.6 GWh | 30.4 mi |
| True North Solar, LLC | Otto, TX | 568.6 GWh | 1.9 mi |
| Waco Solar | Mt Calm, TX | 883.9 GWh | 17.2 mi |