Hubbard Wind
1023 HCR 3363, Mt Calm, TX 76648Plant Summary Information
Hubbard Wind is ranked #26 out of 226 wind farms in Texas in terms of total annual net electricity generation.
Hubbard Wind generated 141.7 GWh during the 3-month period between July 2025 to October 2025.
| Plant Name | Hubbard Wind |
|---|---|
| Utility Name | Hubbard Wind LLC |
| Location | Limestone County, TX |
| Initial Operation Date | November 2021 |
| Last Update | Oct 2025 |
| Annual Generation | 971.8 GWh |
| Annual Consumption | 3.6 M MMBtu |
| Ranked #748 out of 12,553 Power Plants Nationwide | |
| Ranked #66 out of 1,366 Wind Power Plants Nationwide | |
| Ranked #125 out of 804 Texas Power Plants | |
| Ranked #26 out of 226 Texas Wind Power Plants | |
| Fuel Types | Wind |
Map of Hubbard Wind
Full Screen MapRegister Now for Comprehensive Access
Subscribe now to access all power plant data, utility information, FERC EQR data, and more for Hubbard Wind.
Monthly Net Generation for Hubbard Wind
Hubbard Wind Details
| Summary Information | |
|---|---|
| Plant Name | Hubbard Wind (65048) |
| Plant Address | 1023 HCR 3363, Mt Calm, TX 76648 |
| Utility | Hubbard Wind LLC (64468) |
| Latitude, Longitude | 31.77471, -96.8282 |
| Generation Dates on File | Nov 2021 to Oct 2025 |
| Initial Operation Date | November 2021 |
| Annual Generation | 971.8 GWh |
| Fuel Types | Wind |
| Federal Energy Regulatory Commission (FERC) Information | |
| FERC Cogeneration Status | No |
| FERC Small Power Producer Status | No |
| FERC Exempt Wholesale Generator Status | No |
| Regulatory Information | |
|---|---|
| Regulatory Status | Non-Regulated |
| NERC Region | TRE |
| Balancing Authority | Electric Reliability Council of Texas, Inc. (ERCO) |
| NAICS Code | Utilities (22) |
| Sector | IPP Non-CHP (2) |
| Water Source | |
| Ash Impoundment | |
| Transmission / Distribution Owner | Lone Star Transmission () TX |
| Grid Voltage | 345.00 kV |
| Energy Storage | No |
Generator HW001 Details Operating November 2021
| Technology | Onshore Wind Turbine |
|---|---|
| Prime Mover | Wind Turbine, Onshore |
| Ownership | Single Owner |
| Nameplate Capacity | 300 MW |
| Summer Capacity | 300 MW |
| Winter Capacity | 300 MW |
| Minimum Load | 30 MW |
| Uprate/Derate Completed | No |
|---|---|
| Status | Operating |
| First Operation Date | November 2021 |
| Combined Heat & Power | No |
| Sector Name | IPP Non-CHP (2) |
| Energy Source | Wind |
| Turbines/Hydrokinetic Buoys | 108 |
| Turbine Details | |
| Number Of Turbines | 108 |
|---|---|
| Predominant Turbine Manufacturer | GE |
| Predominant Turbine Model Number | 2.82-127 |
| Design Wind Speed | 13.4 MPH |
| Wind Quality Class | 2 - Medium Wind |
| Turbine Hub Height Feet | 291.9 |
Hubbard Wind Plant Owners
| Owner Name | Address | Ownership | We couldn't locate any owners for this plant |
|---|
Power Plants with Similar Net Generation
Power plants with a similar annual net generation from Wind.
| Rank | Plant Name | Plant Location | Annual Generation |
|---|---|---|---|
| #56 | Solomon Forks Wind Project, LLC | Colby, KS | 1.0 TWh |
| #57 | Lincoln Land Wind | TBD, IL | 1.0 TWh |
| #58 | Roosevelt County | Portales, NM | 1.0 TWh |
| #59 | Mohave County Wind Farm | Willow Beach, AZ | 1.0 TWh |
| #60 | Dakota Range Wind | Marvin, SD | 1.0 TWh |
| #61 | Priddy Wind Project | Goldthwaite, TX | 1.0 TWh |
| #62 | Limestone Wind Project | Coolidge, TX | 1.0 TWh |
| #63 | Triple H Wind Project | Highmore, SD | 1.0 TWh |
| #64 | Milligan 1 Wind Farm | Western, NE | 996.7 GWh |
| #65 | Soldier Creek Wind | Corning, KS | 992.1 GWh |
| #67 | Pomeroy Wind Farm | Fonda, IA | 965.9 GWh |
| #68 | Boswell Wind | Rock River, WY | 961.0 GWh |
| #69 | Caddo Wind | Apache, OK | 959.7 GWh |
| #70 | TG East | Truscott, TX | 953.0 GWh |
| #71 | Javelina Wind Energy, LLC | Mirando City, TX | 947.1 GWh |
| #72 | Nobles 2 Wind Project | Wilmont, MN | 946.8 GWh |
| #73 | Flat Ridge 2 Wind Energy LLC | Zenda, KS | 942.1 GWh |
| #74 | Sapphire Sky Wind Energy LLC | Farmer City, IL | 937.2 GWh |
| #75 | South Plains II | Lockney, TX | 930.8 GWh |
| #76 | Irish Creek Wind | Frankfort, KS | 925.1 GWh |
Nearby Power Plants
Below are closest 20 power plants surrounding Hubbard Wind.
| Plant Name | Plant Location | Annual Generation | Distance |
|---|---|---|---|
| AbbVie Waco | Waco, TX | 811.0 MWh | 29.5 mi |
| Ash Creek Solar | Abbott, TX | 320.8 GWh | 14.9 mi |
| BPL Files Solar | Itasca, TX | 228.8 GWh | 31.7 mi |
| BPL Sol Solar LLC | Chilton, TX | 208.5 GWh | 33.2 mi |
| Briar Creek Solar 1 | Corsicana, TX | 217.5 GWh | 24.7 mi |
| Copperhead Solar, LLC | Riesel, TX | 299.7 GWh | 22.5 mi |
| Elm Branch Solar 1 | Bardwell, TX | 250.8 GWh | 32.4 mi |
| Griffin Solar | Robinson, TX | 9.2 GWh | 27.8 mi |
| Limestone Wind Project | Coolidge, TX | 1.0 TWh | 13.1 mi |
| Markum Solar Farm | Valley Mills, TX | 365.3 GWh | 32.6 mi |
| Pisgah Ridge Solar, LLC | Richland, TX | 513.8 GWh | 22.8 mi |
| Pitts Dudik Solar | Hubbard, TX | 105.3 GWh | 8.6 mi |
| Prairie Hill Wind Project | Mart, TX | 111.5 GWh | 16.2 mi |
| Roseland Solar Project, LLC | Riesel, TX | 1.0 TWh | 21.7 mi |
| Sandy Creek Energy Station | Riesel, TX | 3.2 TWh | 22.1 mi |
| Sun Valley Solar Project | Abbott, TX | 546.3 GWh | 12.8 mi |
| Thad Hill Energy Center | Clifton, TX | 4.2 TWh | 31.7 mi |
| True North Solar, LLC | Otto, TX | 527.8 GWh | 21.2 mi |
| Waco Solar | Mt Calm, TX | 911.3 GWh | 4.5 mi |
| Whitney | Clifton, TX | 69.4 GWh | 32.3 mi |